County: CHEROKEE Highway: FM 343 Date: 01/09/2019 (5 years ago) Engineer's Estimate: $734,897 Control Number: 0926-01-023
Project: STP 2019(429)HES District: TYLER Time: 90 WORKING DAYS Type: STRUCTURES & DRAINAGE IMPROVEMENTS

Bidders

Name Total Amount Place Over/Under Est Amt Left From Low Bid Delta Between Bidders
Engineer's Estimate $734,896.80
HIGHWAY 19 CONSTRUCTION LLC   $638,597.67 1
-13.1% | -$96,299.13
BAKER & REID COMPANY, LLC   $703,503.93 2
-4.27% | -$31,392.87
10.16% | $64,906.26
STATELINE CONSTRUCTION, LLC   $722,972.75 3
-1.62% | -$11,924.05
13.21% | $84,375.08
2.77% | $19,468.82
B & E CONSTRUCTION INC   $726,163.20 4
-1.19% | -$8,733.60
13.71% | $87,565.53
0.44% | $3,190.45
L. S. EQUIPMENT CO., INC.   $746,152.50 5
1.53% | $11,255.70
16.84% | $107,554.83
2.75% | $19,989.30
EAST TEXAS BRIDGE, INC.   $754,839.45 6
2.71% | $19,942.65
18.2% | $116,241.78
1.16% | $8,686.95
J.R. POPE COMPANY, INC.   $779,425.20 7
6.06% | $44,528.40
22.05% | $140,827.53
3.26% | $24,585.75
LONGVIEW BRIDGE AND ROAD, LTD.   $782,947.76 8
6.54% | $48,050.96
22.6% | $144,350.09
0.45% | $3,522.56
TALBRAN ENTERPRISES LLC   $788,295.50 9
7.27% | $53,398.70
23.44% | $149,697.83
0.68% | $5,347.74
PIERCE R & B LLC   $874,784.50 10
19.04% | $139,887.70
36.99% | $236,186.83
10.97% | $86,489.00
ENCINO LANDSCAPE, INC.   $929,069.85 11
26.42% | $194,173.05
45.49% | $290,472.18
6.21% | $54,285.35
REYNOLDS & KAY, LTD.   $1,111,763.00 12
51.28% | $376,866.20
74.09% | $473,165.33
19.66% | $182,693.15
FNH CONSTRUCTION, LLC   $1,141,004.00 13
55.26% | $406,107.20
78.67% | $502,406.33
2.63% | $29,241.00

Bid Items

Items: 54, 0 filtered
CHEROKEE FM 343  |  TYLER  |  0926-01-023  |  01/09/2019  |  $734,897  |  STP 2019(429)HES  |  STRUCTS & DRAINAGE IMPRVS  |  90 WORKING DAYS
Item code Description Unit Quantity Engineer's Estimate HIGHWAY 19 CONSTRUCTION LLC BAKER & REID COMPANY, LLC STATELINE CONSTRUCTION, LLC B & E CONSTRUCTION INC L. S. EQUIPMENT CO., INC. EAST TEXAS BRIDGE, INC. J.R. POPE COMPANY, INC. LONGVIEW BRIDGE AND ROAD, LTD. TALBRAN ENTERPRISES LLC PIERCE R & B LLC ENCINO LANDSCAPE, INC. REYNOLDS & KAY, LTD. FNH CONSTRUCTION, LLC
100 6002 PREPARING ROW STA 4.200 $1,000.000 $1,000.000 $650.000 $2,000.000 $6,000.000 $1,000.000 $5,000.000 $100.000 $1,600.000 $2,000.000 $3,000.000 $4,000.000 $1,785.000 $17,000.000
104 6017 REMOVING CONC (DRIVEWAYS) SY 119.000 $13.000 $25.000 $23.000 $15.000 $13.000 $15.000 $20.000 $20.000 $30.000 $12.000 $22.000 $50.000 $34.000 $20.000
132 6021 EMBANKMENT (VEHICLE)(ORD COMP)(TY C) CY 500.000 $25.000 $30.000 $19.000 $15.000 $11.000 $25.000 $15.000 $35.000 $20.000 $30.000 $32.000 $30.000 $35.000 $5.000
150 6001 BLADING STA 58.000 $150.000 $500.000 $126.000 $190.000 $185.000 $100.000 $200.000 $150.000 $117.000 $200.000 $175.000 $200.000 $200.000 $450.000
160 6003 FURNISHING AND PLACING TOPSOIL (4") SY 22,879.000 $1.000 $2.000 $0.900 $2.750 $1.000 $1.000 $1.350 $2.500 $1.700 $1.500 $2.000 $2.000 $3.900 $6.000
162 6002 BLOCK SODDING SY 142.000 $4.000 $8.000 $8.400 $10.000 $10.000 $4.000 $6.500 $7.000 $8.250 $7.200 $8.250 $5.000 $8.750 $6.000
164 6054 BOND FBR MTRX SEED (PERM)(RURAL)(SAND) SY 22,737.000 $1.000 $0.700 $0.800 $0.750 $1.000 $0.700 $1.000 $0.900 $0.800 $1.000 $0.760 $0.850 $0.850 $1.000
164 6055 BONDED FBR MTRX SEED (TEMP)(WARM) SY 11,369.000 $0.850 $0.700 $0.750 $0.650 $1.000 $0.700 $1.000 $0.800 $0.740 $0.700 $0.760 $0.800 $0.800 $1.000
164 6056 BONDED FBR MTRX SEED (TEMP)(COOL) SY 11,369.000 $0.850 $0.630 $0.720 $0.100 $1.000 $0.700 $0.200 $0.800 $0.700 $0.700 $0.760 $0.800 $0.750 $1.000
168 6001 VEGETATIVE WATERING MG 500.000 $10.000 $10.000 $18.000 $5.000 $11.000 $0.010 $5.000 $9.000 $18.000 $50.000 $20.000 $15.000 $14.000 $30.000
400 6006 CUT & RESTORING PAV SY 26.000 $150.000 $180.000 $74.500 $172.000 $100.000 $95.000 $100.000 $350.000 $65.000 $150.000 $220.000 $100.000 $163.000 $200.000
400 6008 CUT & RESTORE ASPH PAVING SY 330.000 $142.000 $50.000 $48.000 $65.000 $65.000 $95.000 $35.000 $100.000 $85.000 $150.000 $195.000 $100.000 $92.000 $85.000
400 6012 CUT AND RESTORE PAV (FLEX BASE) SY 92.000 $75.000 $35.000 $67.000 $42.000 $51.000 $50.000 $35.000 $60.000 $63.000 $100.000 $55.000 $200.000 $62.000 $85.000
401 6001 FLOWABLE BACKFILL CY 63.000 $190.000 $180.000 $148.000 $225.000 $115.000 $290.000 $225.000 $180.000 $195.000 $200.000 $195.000 $250.000 $245.000 $300.000
402 6001 TRENCH EXCAVATION PROTECTION LF 80.000 $5.000 $10.000 $2.500 $50.000 $5.000 $10.000 $30.000 $10.000 $14.000 $5.000 $10.000 $15.000 $6.000 $4.000
403 6001 TEMPORARY SPL SHORING SF 1,224.000 $28.000 $25.000 $35.500 $23.000 $16.000 $62.000 $35.000 $10.000 $42.000 $12.000 $35.000 $30.000 $45.000 $42.000
420 6071 CL C CONC (COLLAR) EA 8.000 $800.000 $1,000.000 $1,400.000 $850.000 $835.000 $700.000 $1,000.000 $1,500.000 $975.000 $800.000 $1,100.000 $1,200.000 $784.000 $1,500.000
420 6074 CL C CONC (MISC) CY 5.000 $850.000 $1,000.000 $616.000 $800.000 $650.000 $600.000 $700.000 $800.000 $1,305.000 $647.000 $1,500.000 $500.000 $873.000 $1,500.000
432 6024 RIPRAP (STONE COMMON)(DRY)(12 IN) CY 206.000 $130.000 $100.000 $156.000 $110.000 $125.000 $150.000 $150.000 $190.000 $195.000 $150.000 $145.000 $150.000 $220.000 $150.000
432 6027 RIPRAP (STONE COMMON)(DRY)(24 IN) CY 6.000 $150.000 $350.000 $347.000 $600.000 $168.000 $150.000 $200.000 $190.000 $325.000 $150.000 $300.000 $200.000 $288.000 $250.000
464 6003 RC PIPE (CL III)(18 IN) LF 2,230.000 $48.000 $35.000 $39.000 $34.000 $43.000 $40.000 $45.000 $45.000 $38.000 $34.000 $42.000 $60.000 $49.000 $65.000
464 6005 RC PIPE (CL III)(24 IN) LF 60.000 $60.000 $45.000 $55.000 $60.000 $63.000 $60.000 $60.000 $60.000 $61.500 $55.000 $65.000 $75.000 $75.000 $95.000
464 6007 RC PIPE (CL III)(30 IN) LF 68.000 $75.000 $65.000 $67.000 $125.000 $70.000 $90.000 $95.000 $120.000 $75.000 $70.000 $95.000 $90.000 $90.000 $105.000
464 6008 RC PIPE (CL III)(36 IN) LF 22.000 $105.000 $80.000 $97.000 $225.000 $100.000 $125.000 $150.000 $210.000 $110.000 $100.000 $140.000 $120.000 $160.000 $130.000
465 6126 INLET (COMPL)(PSL)(FG)(3FTX3FT-3FTX3FT) EA 1.000 $4,800.000 $3,500.000 $3,400.000 $3,375.000 $3,500.000 $1,800.000 $3,500.000 $4,000.000 $3,800.000 $3,600.000 $3,500.000 $5,000.000 $3,500.000 $6,500.000
466 6052 HEADWALL (CH - FW - 45) (DIA= 30 IN) EA 2.000 $3,570.000 $4,500.000 $4,480.000 $6,657.000 $8,500.000 $7,500.000 $3,500.000 $7,000.000 $5,200.000 $10,500.000 $6,500.000 $7,000.000 $6,300.000 $3,000.000
466 6054 HEADWALL (CH - FW - 45) (DIA= 36 IN) EA 1.000 $8,000.000 $5,000.000 $5,040.000 $9,105.000 $9,000.000 $65,000.000 $8,000.000 $6,000.000 $6,800.000 $12,000.000 $7,500.000 $8,500.000 $7,000.000 $4,000.000
466 6097 HEADWALL (CH - PW - 0) (DIA= 24 IN) EA 1.000 $3,200.000 $3,000.000 $3,360.000 $4,875.000 $4,500.000 $4,500.000 $2,500.000 $4,500.000 $4,200.000 $8,000.000 $6,500.000 $6,000.000 $4,700.000 $2,500.000
466 6101 HEADWALL (CH - PW - 0) (DIA= 36 IN) EA 1.000 $4,500.000 $3,600.000 $5,600.000 $8,860.000 $6,500.000 $8,500.000 $3,500.000 $7,500.000 $6,300.000 $10,000.000 $7,500.000 $6,500.000 $7,500.000 $4,000.000
466 6246 HEADWALL (CH - PW - 0)(DIA=36 IN)(MOD) EA 1.000 $26,000.000 $43,152.000 $67,000.000 $56,875.000 $15,000.000 $6,500.000 $50,000.000 $47,250.000 $85,000.000 $12,000.000 $40,000.000 $8,000.000 $65,000.000 $6,000.000
467 6358 SET (TY II) (18 IN) (RCP) (4: 1) (C) EA 3.000 $650.000 $425.000 $555.000 $675.000 $955.000 $700.000 $525.000 $650.000 $516.000 $1,100.000 $550.000 $800.000 $730.000 $1,850.000
467 6362 SET (TY II) (18 IN) (RCP) (6: 1) (C) EA 2.000 $855.000 $475.000 $730.000 $725.000 $1,100.000 $800.000 $575.000 $725.000 $582.000 $1,100.000 $650.000 $1,000.000 $785.000 $2,000.000
467 6363 SET (TY II) (18 IN) (RCP) (6: 1) (P) EA 144.000 $645.000 $475.000 $510.000 $555.000 $815.000 $800.000 $575.000 $725.000 $582.000 $650.000 $600.000 $900.000 $785.000 $1,000.000
467 6390 SET (TY II) (24 IN) (RCP) (4: 1) (C) EA 5.000 $1,115.000 $625.000 $780.000 $910.000 $1,400.000 $800.000 $750.000 $850.000 $715.000 $900.000 $850.000 $1,200.000 $905.000 $2,100.000
467 6394 SET (TY II) (24 IN) (RCP) (6: 1) (C) EA 1.000 $850.000 $825.000 $1,350.000 $1,090.000 $1,100.000 $800.000 $1,000.000 $1,050.000 $912.000 $900.000 $1,150.000 $1,400.000 $1,100.000 $2,400.000
467 6395 SET (TY II) (24 IN) (RCP) (6: 1) (P) EA 4.000 $1,130.000 $825.000 $1,030.000 $1,090.000 $975.000 $800.000 $1,000.000 $1,050.000 $912.000 $1,150.000 $1,150.000 $1,400.000 $1,100.000 $2,400.000
467 6450 SET (TY II) (36 IN) (RCP) (4: 1) (C) EA 1.000 $1,700.000 $2,125.000 $1,600.000 $2,245.000 $2,700.000 $2,000.000 $2,300.000 $1,800.000 $1,700.000 $2,250.000 $2,250.000 $2,000.000 $2,000.000 $3,000.000
496 6007 REMOV STR (PIPE) LF 106.000 $14.000 $50.000 $51.000 $17.000 $21.000 $5.000 $20.000 $15.000 $20.000 $5.000 $15.000 $20.000 $37.000 $40.000
496 6016 REMOV STR (PIPE) EA 75.000 $325.000 $200.000 $210.000 $200.000 $360.000 $5.000 $500.000 $100.000 $300.000 $250.000 $300.000 $500.000 $500.000 $500.000
500 6001 MOBILIZATION LS 1.000 $70,000.000 $60,000.000 $68,000.000 $60,000.000 $34,579.200 $50,000.000 $70,000.000 $60,000.000 $32,000.000 $50,000.000 $86,200.000 $100,000.000 $225,400.000 $100,000.000
502 6001 BARRICADES, SIGNS AND TRAFFIC HANDLING MO 6.000 $4,800.000 $1,500.000 $2,240.000 $3,200.000 $6,500.000 $2,500.000 $5,000.000 $1,700.000 $3,300.000 $7,000.000 $5,000.000 $5,000.000 $3,000.000 $8,500.000
506 6001 ROCK FILTER DAMS (INSTALL) (TY 1) LF 270.000 $23.000 $25.000 $28.000 $27.000 $48.000 $25.000 $15.000 $30.000 $27.500 $35.000 $38.000 $30.000 $29.000 $30.000
506 6002 ROCK FILTER DAMS (INSTALL) (TY 2) LF 465.000 $28.000 $35.000 $32.000 $33.000 $45.000 $32.000 $20.000 $35.000 $35.000 $40.000 $40.000 $35.000 $37.000 $30.000
506 6011 ROCK FILTER DAMS (REMOVE) LF 735.000 $5.500 $10.000 $11.000 $11.000 $10.000 $5.000 $3.000 $10.000 $14.000 $10.000 $10.000 $10.000 $15.000 $15.000
506 6029 EARTHWORK (EROSN & SEDMT CONT, IN VEH) CY 300.000 $17.000 $10.000 $17.000 $25.000 $8.000 $25.000 $25.000 $20.000 $15.000 $50.000 $55.000 $20.000 $17.000 $30.000
506 6030 BACKHOE WORK (EROSION & SEDMT CONT) HR 75.000 $85.000 $10.000 $94.000 $45.000 $65.000 $25.000 $75.000 $75.000 $195.000 $100.000 $95.000 $90.000 $48.000 $150.000
506 6038 TEMP SEDMT CONT FENCE (INSTALL) LF 300.000 $2.850 $3.000 $3.000 $3.000 $3.000 $2.500 $3.000 $3.500 $2.850 $4.000 $5.000 $4.000 $3.000 $4.000
506 6039 TEMP SEDMT CONT FENCE (REMOVE) LF 300.000 $0.750 $1.000 $1.100 $1.000 $1.000 $1.000 $0.500 $1.500 $1.200 $2.000 $1.000 $1.000 $1.000 $2.000
506 6046 TRACKHOE WORK (EROSION & SEDMT CONT) HR 75.000 $150.000 $10.000 $126.000 $65.000 $135.000 $100.000 $75.000 $120.000 $225.000 $100.000 $120.000 $150.000 $80.000 $150.000
508 6001 CONSTRUCTING DETOURS SY 603.000 $45.000 $62.000 $64.000 $69.000 $60.000 $60.000 $75.000 $90.000 $70.000 $100.000 $75.000 $80.000 $100.000 $45.000
530 6017 DRIVEWAYS (CONC) (HES) SY 119.000 $90.000 $1.000 $120.000 $115.000 $112.000 $80.000 $80.000 $80.000 $105.000 $120.000 $115.000 $100.000 $114.000 $125.000
658 6049 INSTL OM ASSM (OM-2Z)(FLX)GND(BI) EA 34.000 $75.000 $35.000 $21.000 $35.000 $45.000 $100.000 $70.000 $85.000 $74.000 $40.000 $74.000 $80.000 $64.000 $100.000
6001 6001 PORTABLE CHANGEABLE MESSAGE SIGN DAY 14.000 $100.000 $100.000 $144.000 $115.000 $130.000 $150.000 $200.000 $100.000 $100.000 $150.000 $225.000 $150.000 $85.000 $150.000
6185 6002 TMA (STATIONARY) DAY 2.000 $200.000 $1,000.000 $360.000 $1,000.000 $250.000 $300.000 $800.000 $250.000 $200.000 $300.000 $350.000 $250.000 $585.000 $550.000
Totals: $734,896.80 $638,597.67 $703,503.93 $722,972.75 $726,163.20 $746,152.50 $754,839.45 $779,425.20 $782,947.76 $788,295.50 $874,784.50 $929,069.85 $1,111,763.00 $1,141,004.00