Show Job Controls
Bid Cobra

CHAMBERS FM 563 (1023-01-039)

Items: 42

County: CHAMBERS
Length: 11.6290 MILES
Highway: FM 563
District: BEAUMONT
Control Number: 1023-01-039
DBE Goal: 0.0%
Project: STP 2026(911)HES
Guaranty: $50,000.00
Time: 60 WORKING DAYS
Engineer's Estimate: $2,493,248.19
Date: 1:00 PM AUGUST 05, 2026 (in 5 weeks)
Contract Number: 8263027
Type: SURFACING/ROADWAY RESTORATION
Project ID: A00211687
Contract Type: Federal
Project Description: 2023 HSIP CURVE (FM 563) FLASHING CHEVRONS, EDGELINE & CENTERLINE RS
Mail/Deliver Bids To:
TEXAS DEPARTMENT OF TRANSPORTATION
ATTN: CONSTRUCTION DIVISION - RM M1C3.02
6230 E STASSNEY LN, AUSTIN, TX 78744
ROBERTO RODRIGUEZ
CHAMBERS FM 563 (1023-01-039)
Project Name: N/A
Project: STP 2026(911)HES
Length: 8.1680 MILES
Project Type: CONSTRUCTION
Limits From: LIBERTY COUNTY LINE, SOUTH
Limits To: IH 10 WBFR
Project Description: 2023 HSIP CURVE (FM 563) FLASHING CHEVRONS, EDGELINE & CENTERLINE RS
CHAMBERS FM 563 (1023-01-040)
Project Name: FM 563-(LIBERTY C/L TO IH 10) OVERLAY
Project: STP 2026(912)MM
Length: 3.4610 MILES
Project Type: OVERLAY
Limits From: LIBERTY COUNTY LINE, SOUTH
Limits To: IH 10 WBFR
Project Description: FM 563-(LIBERTY COUNTY LINE, SOUTH TO IH 10 WBFR)1.5" TYPE D LU, 2.0" TYPE C OVERLAY
Actions:
Notice Questions HCS Excel Print Print Notice

Bid Items & Bid Tabulations

42 Total 0 of 42
CHAMBERS  |  FM 563  |  BEAUMONT  |  1023-01-039  |  1:00 PM AUGUST 05, 2026  |  $2,493,248.19  |  STP 2026(911)HES  |  SURF/ROADWAY RESTOR  |  60 WORKING DAYS
Item Code
Description
Unit
Quantity
PREPARING ROW
STA 9.000
REMOV CONC (CURB)
LF 180.000
BACKFILL (TY A OR B)
STA 24.000
SPEC EXCAV WORK (BACKHOE)
HR 40.000
HYDRO MULCH SEED (TEMP_WARM_COOL)
SY 24,365.000
VEGETATIVE WATERING
TGL 204.000
D-GR HMA TY-D PG 64-22 (EXEMPT)
TON 4,482.000
TACK COAT
GAL 2,173.000
SP MIXES SP-C SAC-A PG76-22
TON 5,975.000
TACK COAT
GAL 3,260.000
FLEXIBLE PAVEMENT STRUCTURE REPAIR(8")
SY 464.000
PLANE ASPH PAV (0" TO 3.5")
SY 844.000
MOBILIZATION
LS 1.000
BARRICADES, SIGNS AND TRAFFIC HANDLING
MO 4.000
TMA (STATIONARY)
DAY 31.000
TMA (MOBILE OPERATION)
DAY 28.000
DRIVEWAYS (BASE)
SY 1,385.000
DRIVEWAYS AND TURNOUTS (ACP)
SY 4,789.000
MILL RUMBLE STRIPS (ASPH) (CENTERLINE)
LF 18,274.000
MAILBOX INSTALL-S (TWW-POST) TY 4
EA 17.000
MAILBOX INSTALL-D (TWW-POST) TY 4
EA 3.000
MAILBOX INSTALL-M (TWW-POST) TY 4
EA 3.000
CONDT (PVC) (SCH 40) (3/4")
LF 1,740.000
CONDT (PVC) (SCH 40) (3/4") (BORE)
LF 260.000
ELEC CONDR (NO.10) INSULATED
LF 4,000.000
ELEC CONDR (NO.8) BARE
LF 2,000.000
GROUND BOX TY A (122311)
EA 1.000
ELC SRV TY T 120/240 000(NS)GS(N)SP(U)
EA 1.000
WK ZN PAV MRK SHT TERM (TAB)TY Y
EA 930.000
WK ZN PAV MRK SHT TERM (TAB)TY Y-2
EA 2,595.000
REFL PAV MRK TY I (W)8"(SLD)(090MIL)
LF 675.000
RE PROFILE PM TY I(W)6"(SLD)(100MIL)
LF 36,548.000
REFL PAV MRK TY I (Y)6"(BRK)(090MIL)
LF 3,080.000
REFL PAV MRK TY I (Y)6"(SLD)(090MIL)
LF 14,816.000
PREFAB PM TY C (W)(24")(SLD)
LF 51.000
PREFAB PM TY C (W)(ARROW)
EA 2.000
PREFAB PM TY C (W)(36")(YLD TRI)
EA 10.000
REFL PAV MRKR TY I-C
EA 16.000
REFL PAV MRKR TY II-A-A
EA 271.000
INSTALL RDSD FLASH BEACON ASSEMBLY
EA 13.000
LEAD LED CHEVRON
EA 6.000
LED CHEVRON
EA 76.000
INCLUDES FORCE ACCOUNT WORK AMOUNTS AS FOLLOWS:
Description Amount
EROSION CONTROL MAINTENANCE: CONTRACTOR FORCE ACCOUNT WORK (PART) $4,000.00
SAFETY CONTINGENCY: CONTRACTOR FORCE ACCOUNT WORK (PART) $4,000.00
Total: $8,000.00