CASTRO US 385 (0226-06-036)

Items: 160

County: CASTRO
Length: N/A
Highway: US 385
District: LUBBOCK
Control Number: 0226-06-036
DBE Goal: 0.0%
Project: C 226-6-36
Guaranty: N/A
Time: 288 WORKING DAYS
Engineer's Estimate: $47,743,990.20
Date: 02/01/2024 (2 years ago)
Contract Number: N/A
Type: SUPER 2
Mail/Deliver Bids To: N/A
HEATH BOZEMAN
Actions:
Notice Questions HCS Excel Tabs Print Print Notice
Bidders (2)
E
Engineer's Estimate
$47,743,990.20
$54,353,806.68
Over/Under Est: 13.84% $6,609,816.48
$59,421,540.28
Over/Under Est: 24.46% $11,677,550.08
Amt Left: 9.32% $5,067,733.60
Subcontractor Percentage Amount
INDUSTRIAL FABRICS, INC. 7.22% $3,924,344.84
JR WEST TEXAS CONCRETE LLC 4.96% $2,695,948.81
TRP CONSTRUCTION GROUP, LLC 1.48% $804,436.34
MURRAY CONSTRUCTION 0.52% $282,639.79
ARTEX ELECTRIC, INC. 0.48% $260,898.27
LMSE TRUCKING, LLC 0.46% $250,027.51
WIMS ENVIRONMENTAL CONSTRUCTION, LTD. 0.27% $146,755.28
A BROTHERS MILLING, LLC 0.17% $92,401.47
HJC FARMS, INC. 0.16% $86,966.09
WITHERS CONSTRUCTION, LLC 0.14% $76,095.33
PROFESSIONAL TRAFFIC CONTROL LLC 0.11% $59,789.19
BARRICADES UNLIMITED 0.11% $59,789.19
Total: 16.08% $8,740,092.11

Bid Items & Bid Tabulations

160 Total 0 of 160
CASTRO  |  US 385  |  LUBBOCK  |  0226-06-036  |  02/01/2024  |  $47,743,990.20  |  C 226-6-36  |  SUPER 2  |  288 WORKING DAYS
Item Code
Description
Unit
Quantity
Engineer's Estimate
DUININCK, INC.
J. LEE MILLIGAN, INC.
PREPARING ROW
STA 25.500 $5,000.000 $19,000.000 $10,000.000
REMOVING CONC (RIPRAP)
SY 1,714.780 $75.000 $26.500 $33.000
REMOVING CONC (DRIVEWAYS)
SY 6,466.000 $50.000 $18.500 $50.000
REMOVE CONC (GUTTER)
LF 76.000 $20.000 $10.000 $23.000
REMOVING STAB BASE & ASPH PAV (0-2")
SY 884.000 $50.000 $20.500 $16.500
OBLITERATING ABANDONED ROAD
STA 2.000 $2,500.000 $2,100.000 $5,700.000
EXCAVATION (ROADWAY)
CY 100,000.000 $15.000 $14.000 $24.100
SUBGRADE WIDENING (DENS CONT)
STA 219.300 $430.000 $4,100.000 $1,740.000
SUBGRADE WIDENING (DENS CONT)
SY 1,706.780 $7.000 $32.000 $20.000
BACKFILL (TY B)
STA 1,863.900 $210.000 $115.000 $185.000
BLADING
STA 1,863.900 $160.000 $56.500 $175.000
PROOF ROLLING
HR 20.000 $250.000 $210.000 $170.000
PRIME COAT (MC-30)
GAL 5,757.220 $7.000 $5.450 $7.000
EMULS ASPH (EROSN CONT)(CSS-1H)
GAL 262,158.440 $3.600 $3.200 $4.000
FOG SEAL (CSS-1H)
GAL 22,153.070 $5.000 $4.300 $4.000
FLEXIBLE PAVEMENT STRUCTURE REPAIR(6")
SY 16,153.770 $100.000 $65.000 $80.000
FLEXIBLE PAVEMENT STRUCTURE REPAIR(2")
SY 5,384.620 $50.000 $30.000 $40.000
PLANE ASPH CONC PAV(0" TO 3")
SY 10,749.000 $10.000 $7.400 $7.800
CEM STABIL BKFL
CY 28.000 $300.000 $340.000 $335.000
TEMPORARY SPL SHORING
SF 1,000.000 $65.000 $51.000 $50.000
DRILL SHAFT (RDWY ILL POLE) (30 IN)
LF 112.000 $400.000 $325.000 $390.000
CL C CONC (RAC-R)
CY 12.000 $2,200.000 $2,000.000 $2,000.000
CONC STR REPAIR(DECK REP (FULL DEPTH))
SF 300.000 $335.000 $255.000 $250.000
RIPRAP (CONC)(5 IN)
CY 136.700 $900.000 $740.000 $725.000
RIPRAP (MOW STRIP)(4 IN)
CY 66.080 $750.000 $765.000 $780.000
RAIL (TY T223)
LF 153.200 $250.000 $190.000 $183.500
CMP (GAL STL 24 IN)
LF 236.000 $165.000 $110.000 $105.650
CMP (GAL STL 30 IN)
LF 6.000 $300.000 $570.000 $560.000
CMP (GAL STL 36 IN)
LF 48.000 $200.000 $400.000 $390.000
CONC BOX CULV (4 FT X 4 FT)(EXTEND)
LF 27.000 $1,000.000 $1,100.000 $1,070.000
CONC BOX CULV (5 FT X 2 FT)(EXTEND)
LF 375.200 $1,200.000 $875.000 $860.000
CONC BOX CULV (5 FT X 3 FT)(EXTEND)
LF 74.400 $1,300.000 $995.000 $975.000
CONC BOX CULV (7 FT X 3 FT)(EXTEND)
LF 11.200 $1,200.000 $1,600.000 $1,545.000
RC PIPE (CL III)(24 IN)
LF 510.000 $160.000 $120.000 $120.000
RC PIPE (CL III)(36 IN)
LF 48.000 $275.000 $255.000 $250.000
SET (REPLACE PIPE RUNNER ASSEMBLY)
EA 8.000 $4,000.000 $2,400.000 $2,335.000
SET (TY I) (36 IN) (6: 1) (C)
EA 6.000 $6,500.000 $20,500.000 $20,000.000
SET (TY I)(S= 4 FT)(HW= 4 FT)(6:1) (C)
EA 2.000 $18,900.000 $38,500.000 $37,800.000
SET (TY I)(S= 5 FT)(HW= 2 FT)(4:1) (C)
EA 8.000 $10,000.000 $3,400.000 $3,335.000
SET (TY I)(S= 5 FT)(HW= 2 FT)(6:1) (C)
EA 30.000 $12,200.000 $7,400.000 $7,230.000
SET (TY I)(S= 5 FT)(HW= 3 FT)(4:1) (C)
EA 3.000 $10,000.000 $5,500.000 $5,340.000
SET (TY I)(S= 5 FT)(HW= 3 FT)(6:1) (C)
EA 7.000 $10,000.000 $17,000.000 $16,500.000
SET (TY I)(S= 7 FT)(HW= 3 FT)(6:1) (C)
EA 2.000 $15,000.000 $29,500.000 $28,900.000
SET (TY II) (24 IN) (CMP) (6: 1) (P)
EA 52.000 $1,500.000 $2,700.000 $2,670.000
SET (TY II) (24 IN) (RCP) (6: 1) (P)
EA 20.000 $2,800.000 $3,000.000 $2,890.000
SET (TY II) (30 IN) (CMP) (6: 1) (P)
EA 2.000 $5,000.000 $3,600.000 $3,560.000
SET (TY II) (36 IN) (CMP) (6: 1) (P)
EA 8.000 $5,100.000 $4,900.000 $4,785.000
CLEAN EXIST CULVERTS
EA 88.000 $3,000.000 $2,800.000 $4,500.000
REMOV STR (SET)
EA 14.000 $1,500.000 $315.000 $310.000
REMOV STR (PIPE)
EA 14.000 $1,500.000 $400.000 $390.000
MOBILIZATION
LS 1.000 $4,310,971.750 $5,400,000.000 $5,904,000.000
BARRICADES, SIGNS AND TRAFFIC HANDLING
MO 20.000 $8,500.000 $36,000.000 $50,000.000
CONSTRUCTION EXITS (INSTALL) (TY 1)
SY 222.220 $40.000 $55.500 $73.000
CONSTRUCTION EXITS (REMOVE)
SY 222.220 $13.000 $17.000 $20.000
CONSTRUCTION PERIMETER FENCE
LF 290.000 $20.000 $9.100 $25.000
SANDBAGS FOR EROSION CONTROL
EA 2,350.000 $20.000 $7.950 $20.000
TEMP SEDMT CONT FENCE (INSTALL)
LF 900.000 $10.000 $5.700 $11.000
TEMP SEDMT CONT FENCE (REMOVE)
LF 450.000 $1.000 $3.400 $9.500
BIODEG EROSN CONT LOGS (INSTL) (18")
LF 18,300.000 $10.000 $5.700 $8.000
BIODEG EROSN CONT LOGS (REMOVE)
LF 9,150.000 $2.000 $3.400 $4.500
CONCRETE GUTTER (MODIFIED)
LF 76.000 $50.000 $82.000 $80.000
INTERSECTIONS (ACP)
SY 12,966.000 $80.000 $61.500 $57.000
DRIVEWAYS (CONC)
SY 6,466.000 $155.000 $115.000 $115.000
DRIVEWAYS (ACP)
SY 18,580.000 $75.000 $65.000 $75.000
TURNOUTS (ACP)
SY 922.000 $90.000 $150.000 $160.000
RUMBLE STRIPS (SHOULDER) ASPHALT
LF 340,448.000 $0.250 $0.070 $0.300
RUMBLE STRIPS (CENTERLINE) ASPHALT
LF 186,524.000 $0.250 $0.070 $0.300
MTL W-BEAM GD FEN (STEEL POST)
LF 875.000 $35.000 $38.500 $37.500
TERMINAL ANCHOR SECTION
EA 4.000 $700.000 $115.000 $115.000
MTL BEAM GD FEN TRANS (THRIE-BEAM)
EA 4.000 $2,500.000 $3,200.000 $3,115.000
REMOVE METAL BEAM GUARD FENCE
LF 875.000 $5.000 $3.400 $3.350
REMOVE TERMINAL ANCHOR SECTION
EA 4.000 $225.000 $340.000 $335.000
RM MTL BM GD FENCE TRANS (THRIE-BEAM)
EA 4.000 $275.000 $340.000 $335.000
GUARDRAIL END TREATMENT (INSTALL)
EA 4.000 $4,000.000 $4,100.000 $3,975.000
GUARDRAIL END TREATMENT (REMOVE)
EA 4.000 $450.000 $340.000 $335.000
MAILBOX INSTALL-S (TWW-POST) TY 4
EA 96.000 $350.000 $370.000 $390.000
MAILBOX INSTALL-D (TWW-POST) TY 4
EA 1.000 $550.000 $455.000 $500.000
MAILBOX INSTALL-M (TWW-POST) TY 4
EA 10.000 $750.000 $740.000 $920.000
IN RD IL (TY SA) 40T-12 (250W EQ) LED
EA 14.000 $8,000.000 $7,000.000 $7,785.000
CONDT (PVC) (SCH 80) (2")
LF 2,460.000 $22.000 $20.000 $28.000
CONDT (PVC) (SCH 80) (2") (BORE)
LF 325.000 $33.000 $30.000 $39.000
ELEC CONDR (NO.6) BARE
LF 2,785.000 $2.500 $2.750 $3.350
ELEC CONDR (NO.6) INSULATED
LF 5,570.000 $3.000 $2.750 $3.350
GROUND BOX TY A (122311)W/APRON
EA 1.000 $3,000.000 $1,500.000 $1,670.000
ELC SRV TY A 240/480 060(NS)SS(E)SP(O)
EA 1.000 $11,000.000 $7,500.000 $11,200.000
ALUMINUM SIGNS (TY A)
SF 73.000 $35.000 $34.000 $35.000
IN SM RD SN SUP&AM TY10BWG(1)SA(P)
EA 145.000 $905.000 $680.000 $945.000
IN SM RD SN SUP&AM TY10BWG(1)SA(T)
EA 92.000 $1,050.000 $795.000 $1,085.000
IN SM RD SN SUP&AM TY10BWG(1)SA(U)
EA 9.000 $1,100.000 $855.000 $1,365.000
IN SM RD SN SUP&AM TYS80(1)SA(T)
EA 2.000 $1,200.000 $965.000 $1,335.000
IN SM RD SN SUP&AM TYS80(1)SA(U)
EA 7.000 $1,500.000 $1,000.000 $1,445.000
IN SM RD SN SUP&AM TYS80(1)SA(U-WC)
EA 18.000 $1,540.000 $1,100.000 $1,555.000
REMOVE SM RD SN SUP&AM
EA 228.000 $125.000 $115.000 $125.000
REMOVE DELIN & OBJECT MARKER ASSMS
EA 382.000 $25.000 $22.500 $17.000
INSTL DEL ASSM (D-SW)SZ 1(BRF)GF2(BI)
EA 26.000 $40.000 $54.500 $55.000
INSTL DEL ASSM (D-SW)SZ 1(WFLX)GND(BI)
EA 87.000 $123.000 $100.000 $165.000
INSTL DEL ASSM (D-SW)SZ 1(WFLX)SRF(BI)
EA 6.000 $80.000 $115.000 $190.000
INSTL OM ASSM (OM-2Z)(WFLX)GND(BI)
EA 190.000 $130.000 $100.000 $175.000
WK ZN PAV MRK NON-REMOV (W)4"(BRK)
LF 16,790.000 $0.500 $0.240 $0.230
WK ZN PAV MRK NON-REMOV (W)4"(LNDP)
LF 3,630.000 $0.750 $0.400 $0.390
WK ZN PAV MRK NON-REMOV (W)4"(SLD)
LF 423,975.000 $0.600 $0.200 $0.200
WK ZN PAV MRK NON-REMOV (W)8"(SLD)
LF 13,520.000 $1.000 $0.450 $0.440
WK ZN PAV MRK NON-REMOV (W)24"(SLD)
LF 359.000 $5.000 $4.550 $4.450
WK ZN PAV MRK NON-REMOV (W)(ARROW)
EA 22.000 $68.000 $85.500 $83.400
WK ZN PAV MRK NON-REMOV (W)(RR XING)
EA 1.000 $50.000 $285.000 $278.000
WK ZN PAV MRK NON-REMOV(W)36"(YLD TRI)
EA 12.000 $33.000 $28.500 $27.800
WK ZN PAV MRK NON-REMOV (Y)4"(BRK)
LF 20,320.000 $0.250 $0.240 $0.230
WK ZN PAV MRK NON-REMOV (Y)4"(SLD)
LF 395,680.000 $0.500 $0.220 $0.210
WK ZN PAV MRK NON-REMOV (Y)12"(SLD)
LF 83.000 $7.000 $5.700 $5.550
WK ZN PAV MRK NON-REMOV (Y)(MED NOSE)
EA 3.000 $50.000 $170.000 $167.000
WK ZN PAV MRK SHT TERM (TAB)TY W
EA 40,150.000 $2.250 $1.650 $1.750
WK ZN PAV MRK SHT TERM (TAB)TY Y-2
EA 30,700.000 $2.500 $1.650 $1.800
WK ZN PAV MRK NON-REMOV (W) (LNDP ARW)
EA 20.000 $25.000 $170.000 $167.000
REFL PAV MRK TY I (W)6"(LNDP)(100MIL)
LF 3,630.000 $2.250 $1.150 $1.100
REFL PAV MRK TY I (W)8"(SLD)(100MIL)
LF 8,170.000 $1.150 $1.400 $1.400
REFL PAV MRK TY I (W)(RR XING)(090MIL)
EA 5.000 $51.000 $680.000 $667.000
RE PM W/RET REQ TY I (W)6"(BRK)(100MIL)
LF 16,790.000 $0.750 $0.830 $0.810
RE PM W/RET REQ TY I (W)6"(SLD)(100MIL)
LF 371,975.000 $0.750 $0.730 $0.710
RE PM W/RET REQ TY I (Y)6"(BRK)(100MIL)
LF 14,510.000 $0.750 $0.830 $0.810
RE PM W/RET REQ TY I (Y)6"(SLD)(100MIL)
LF 325,840.000 $0.850 $0.730 $0.710
PREFAB PAV MRK TY C (W) (24") (SLD)
LF 359.000 $20.000 $13.500 $13.350
PREFAB PAV MRK TY C (W) (ARROW)
EA 22.000 $290.000 $255.000 $250.000
PREFAB PAV MRK TY C (W) (LNDP ARROW)
EA 20.000 $575.000 $510.000 $500.000
PREFAB PAV MRK TY C (W) (RR XING)
EA 1.000 $700.000 $740.000 $725.000
PREFAB PAV MRK TY C (Y) (12") (SLD)
LF 83.000 $10.000 $11.500 $11.150
PREFAB PAV MRK TY C (Y) (MED NOSE)
EA 3.000 $250.000 $400.000 $390.000
REFL PAV MRKR TY I-C
EA 1,267.000 $5.000 $5.700 $5.550
REFL PAV MRKR TY II-A-A
EA 8,064.000 $6.000 $5.100 $5.000
ELIM EXT PAV MRK & MRKS (4")
LF 52,000.000 $1.100 $0.850 $0.830
ELIM EXT PAV MRK & MRKS (8")
LF 1,850.000 $1.250 $0.850 $0.830
ELIM EXT PAV MRK & MRKS (12")
LF 58,460.000 $1.500 $0.740 $0.720
PAV SURF PREP FOR MRK (6")
LF 430.000 $0.500 $1.150 $1.100
PAV SURF PREP FOR MRK (12")
LF 83.000 $1.000 $2.250 $2.250
PAV SURF PREP FOR MRK (24")
LF 359.000 $1.000 $4.550 $4.450
PAV SURF PREP FOR MRK (ARROW)
EA 42.000 $40.000 $62.500 $61.000
PAV SURF PREP FOR MRK (RR XING)
EA 1.000 $200.000 $225.000 $225.000
PAV SURF PREP FOR MRK (36")(YLD TRI)
EA 12.000 $12.000 $57.000 $56.000
PAV SURF PREP FOR MRK (MED NOSE)
EA 1.000 $75.000 $34.000 $34.000
VEH SIG SEC (12")LED(RED)
EA 8.000 $380.000 $400.000 $445.000
INSTL RDSD FLSH BCN ASSM (SOLAR PWRD)
EA 4.000 $13,750.000 $9,000.000 $9,200.000
REMOV RDSD FLSH BCN AM (SOLAR PWRD)
EA 4.000 $550.000 $1,000.000 $835.000
FULL - WIDTH MOWING
CYC 4.000 $5,500.000 $20,500.000 $16,700.000
LITTER REMOVAL
CYC 4.000 $2,250.000 $16,000.000 $20,000.000
DITCH CLEANING AND RESHAPING (FOOT)
LF 15,000.000 $3.000 $8.100 $2.250
POST AND CABLE FENCE(REMV / REPL POSTS)
EA 28.000 $40.000 $115.000 $112.000
POST AND CABLE FENCE(RMV/REPL CNC ANCH)
EA 9.000 $65.000 $340.000 $335.000
POST AND CABLE FENCE (REMV/ REPL CABLE)
LF 750.000 $4.000 $20.000 $19.500
REINFORCED FAB FOR ASPH PVMNT OVERLAYS
SY 658,479.090 $6.500 $6.950 $6.650
ASPH FOR REINF FAB (PG76-28)
GAL 98,771.860 $7.000 $3.950 $7.000
D-GR HMA TY-C SAC-B PG70-28
TON 46,811.700 $130.000 $182.600 $180.000
D-GR HMA TY-D SAC-B PG70-28
TON 14,551.140 $130.000 $220.000 $171.000
TACK COAT
GAL 127,570.510 $5.000 $0.010 $7.350
STONE-MTRX-ASPH SMA-D SAC-A PG76-28
TON 91,676.660 $155.000 $200.000 $220.000
TACK COAT
GAL 33,964.430 $5.000 $0.010 $7.350
TEMP CONSTRUCTION ACCESS
LS 1.000 $500,000.000 $91,000.000 $89,000.000
INSTALL BRIDGE IDENTIFICATION NUMBERS
EA 3.000 $500.000 $910.000 $1,100.000
PORTABLE CHANGEABLE MESSAGE SIGN
DAY 556.000 $50.000 $115.000 $180.000
TMA (STATIONARY)
DAY 470.000 $210.000 $285.000 $535.000
TMA (MOBILE OPERATION)
DAY 73.000 $315.000 $1,300.000 $1,125.000
TEMP SPEED MONITOR SYS
EA 2.000 $16,500.000 $8,500.000 $13,500.000
Totals: $47,743,990.199 $54,353,806.720 $59,421,540.298