Show Job Controls
Bid Cobra

BROWN US 67 (0054-06-113)

Items: 58

County: BROWN
Length: 5.9980 MILES
Highway: US 67
District: BROWNWOOD
Control Number: 0054-06-113
DBE Goal: 0.0%
Project: STP 2026(883)HES
Guaranty: $0.00
Time: 100 WORKING DAYS
Engineer's Estimate: $2,463,639.10
Date: 07/02/2026 1:00 PM CDT (16 days ago)
Contract Number: 7263241
Type: HAZARD ELIMINATION & SAFETY
Project ID: A00216048
Contract Type: FEDERAL
Project Description: FOR THE CONSTRUCTION OF CABLE MEDIAN BARRIER
Mail/Deliver Bids To:
TEXAS DEPARTMENT OF TRANSPORTATION
ATTN: CONSTRUCTION DIVISION - RM M1C3.02
6230 E STASSNEY LN, AUSTIN, TX 78744
BLAKE STEMBRIDGE
NATHAN MCMAHON
Actions:
Notice Questions HCS Excel Tabs Print Print Notice
Bidders (3)
E
Engineer's Estimate
$2,463,639.10
Over/Under Est: -6.08% -$149,810.15
$2,435,515.03
Over/Under Est: -1.14% -$28,124.07
Amt Left: 5.26% $121,686.08
$2,517,955.07
Over/Under Est: 2.2% $54,315.97
Amt Left: 8.82% $204,126.12
Delta: -3.38% -$82,440.04

Bid Items & Bid Tabulations

58 Total 0 of 58
BROWN  |  US 67  |  BROWNWOOD  |  0054-06-113  |  07/02/2026 1:00 PM CDT  |  $2,463,639.10  |  STP 2026(883)HES  |  HAZARD ELIM & SAFETY  |  100 WORKING DAYS
Item Code
Description
Unit
Quantity
Engineer's Estimate
GRATIOT CONSTRUCTION, LTD.
PRATER DIRT WORK LLC
HJC FARMS, INC.
PREPARING ROW
STA 15.000 $800.000 $950.000 $500.000 $989.000
EXCAV (ROADWAY)
CY 1,869.000 $18.500 $12.000 $7.000 $19.350
EMBANK (FNL)(OC)(TY C)
CY 2,405.000 $22.000 $23.000 $11.000 $27.950
BROADCAST SEED (PERM_RURAL_SAND)
SY 18,643.000 $0.300 $0.500 $0.330 $0.330
VEGETATIVE WATERING
TGL 418.000 $30.000 $25.000 $12.000 $50.000
FL BS (CMP IN PLC)(TYD GR1-2)(FNAL POS)
CY 811.000 $75.000 $48.500 $75.000 $79.550
ASPH (RC-250)
GAL 516.000 $10.000 $18.000 $20.000 $26.250
AGGR (TY-B, GR-5)(SAC-B)
CY 19.000 $300.000 $290.000 $300.000 $148.750
SP MIXES SP-C PG76-22
TON 399.000 $200.000 $188.000 $195.000 $271.250
PLANE ASPH CONC PAV(0" TO 3")
SY 378.000 $6.000 $26.000 $33.000 $25.800
CL C CONC (RAIL FOUNDATION)
CY 274.000 $815.000 $508.000 $667.000 $682.630
RIPRAP (CONC)(5 IN)
CY 58.000 $650.000 $650.000 $551.250 $698.750
RIPRAP (CONC)(CL A)
CY 176.000 $675.000 $700.000 $551.250 $698.750
RIPRAP (MOW STRIP)(4 IN)
CY 138.000 $650.000 $670.000 $551.250 $625.000
RIPRAP (MOW STRIP)(5 IN)
CY 1,296.000 $450.000 $505.000 $551.250 $522.000
RC PIPE (CL III)(18 IN)
LF 20.000 $144.000 $200.000 $70.000 $161.250
INLET (COMPL)(DROP)
EA 1.000 $9,000.000 $7,900.000 $7,500.000 $6,880.000
ADJUSTING INLETS
EA 2.000 $3,000.000 $2,100.000 $2,500.000 $6,665.000
REMOV STR (PIPE)
LF 70.000 $28.000 $40.000 $50.000 $21.500
MOBILIZATION
LS 1.000 $220,400.000 $128,000.000 $210,000.000 $104,848.250
BARRICADES, SIGNS AND TRAFFIC HANDLING
MO 6.000 $6,500.000 $7,500.000 $7,000.000 $1,846.850
PORTABLE CHANGEABLE MESSAGE SIGN
DAY 228.000 $88.000 $10.000 $100.000 $50.000
TMA (STATIONARY)
DAY 400.000 $135.000 $5.000 $190.000 $150.000
TMA (MOBILE OPERATION)
DAY 25.000 $300.000 $50.000 $300.000 $150.000
TEMP SEDMT CONT FENCE (INSTALL)
LF 315.000 $8.000 $6.000 $10.000 $7.000
TEMP SEDMT CONT FENCE (REMOVE)
LF 315.000 $1.500 $1.000 $2.200 $1.000
BIODEG EROSN CONT LOGS (INSTL) (12")
LF 515.000 $6.200 $10.000 $4.000 $8.000
BIODEG EROSN CONT LOGS (REMOVE)
LF 515.000 $1.700 $1.000 $2.000 $1.000
PORT CTB (DES SOURCE)(SGL SLP)(TY 1)
LF 1,230.000 $20.000 $26.000 $12.000 $21.000
PORT CTB (REMOVE)(SGL SLP)(TY 1)
LF 1,230.000 $20.000 $29.000 $12.000 $21.000
PERM CTB (SGL SLOPE) (TY 1) (54 )
LF 855.000 $140.000 $139.000 $140.000 $141.900
MILL RUMBLE STRIPS (ASPHALT) (SHLDR)
LF 604.000 $4.500 $19.000 $19.540 $19.620
MTL W-BEAM GD FEN (STEEL POST)
LF 2,187.500 $32.000 $33.000 $26.250 $32.000
DOWNSTREAM ANCHOR TERMINAL SECTION
EA 5.000 $1,500.000 $1,700.000 $1,260.000 $1,325.000
MTL W - BEAM GD FEN (LOW FILL CULVERT)
LF 125.000 $100.000 $130.000 $90.000 $110.000
MTL BM GD FEN TRANS (31"-28")(25')
EA 2.000 $850.000 $1,200.000 $1,050.000 $1,050.000
REMOVE METAL BEAM GUARD FENCE
LF 75.000 $8.000 $6.000 $12.600 $2.000
CABLE BARRIER SYSTEM (INSTALL)(TL-4)
LF 26,374.000 $12.500 $11.300 $10.500 $12.000
CABLE BARRIER TERM SEC (INSTL)(TL-4)
EA 34.000 $1,800.000 $2,400.000 $2,782.500 $3,000.000
GUARDRAIL END TREATMENT (INSTALL)
EA 5.000 $3,500.000 $3,300.000 $3,150.000 $3,550.000
CRASH CUSH ATTEN (REMOVE)
EA 1.000 $1,500.000 $750.000 $1,296.750 $1,000.000
CRASH CUSH ATTEN (INSTL)(L)(N)(TL3)
EA 2.000 $30,000.000 $30,000.000 $28,565.000 $33,000.000
CRASH CUSH ATTEN (INSTL)(S)(N)(TL3)
EA 1.000 $10,000.000 $9,000.000 $7,738.500 $10,000.000
IN SM RD SN SUP&AM TY10BWG(1)SA(P)
EA 6.000 $900.000 $550.000 $775.000 $850.000
REMOVE SM RD SN SUP&AM
EA 30.000 $100.000 $100.000 $125.000 $125.000
INSTL DEL ASSM (D-SW)SZ 1(BRF)GF2(BI)
EA 51.000 $47.000 $50.000 $30.000 $30.000
INSTL DEL ASSM (D-SY)SZ 1(BRF)CTB (BI)
EA 22.000 $35.000 $50.000 $30.000 $25.000
WK ZN PAV MRK REMOV (Y)6"(SLD)
LF 2,641.000 $1.700 $5.250 $2.370 $5.050
REFL PAV MRK TY I (W)8"(DOT)(100MIL)
LF 300.000 $2.300 $4.700 $4.730 $4.460
REFL PAV MRK TY I (W)8"(SLD)(100MIL)
LF 450.000 $2.600 $2.900 $4.460 $2.740
REFL PAV MRK TY I (W)(ARROW)(100MIL)
EA 4.000 $300.000 $380.000 $215.250 $360.130
REFL PAV MRK TY I (W)(WORD)(100MIL)
EA 4.000 $300.000 $420.000 $288.750 $397.750
REF PAV MRK TY I(W)36"(YLD TRI)(100MIL)
EA 20.000 $45.000 $140.000 $42.000 $134.380
REFL PAV MRK TY I (W)6"(BRK)(100MIL)
LF 660.000 $1.350 $3.500 $3.570 $3.440
REFL PAV MRK TY I (Y)6"(SLD)(100MIL)
LF 1,414.000 $1.500 $3.500 $3.570 $3.440
REFL PAV MRKR TY II-A-A
EA 3.000 $50.000 $11.000 $21.000 $10.750
REFL PAV MRKR TY II-C-R
EA 22.000 $10.000 $11.000 $21.000 $10.750
ELIM EXT PM & MRKS (6")
LF 660.000 $5.000 $10.700 $2.670 $10.110
Totals: $2,463,639.100 $2,313,828.950 $2,435,515.025 $2,517,955.070
INCLUDES FORCE ACCOUNT WORK AMOUNTS AS FOLLOWS:
Description Amount
EROSION CONTROL MAINTENANCE: CONTRACTOR FORCE ACCOUNT WORK (PART) $5,000.00
SAFETY CONTINGENCY: CONTRACTOR FORCE ACCOUNT WORK (PART) $45,000.00
Total: $50,000.00