Job Info for 6451-57-001

County: BRAZOS Highway: US0190 Date: 05/02/2024 (6 months ago) Engineer's Estimate: $5,296,203 Control Number: 6451-57-001
Project: RMC - 645157001 District: BRYAN Time: 44 W Type: MILL AND INLAY
Bidder's List
Email All | Notice | Questions
HCS
Pay Estimates: 1 | 2
Plans: Plans | Proposal

Bidders

Name Total Amount Place Over/Under Est Amt Left From Low Bid Delta Between Bidders
Engineer's Estimate $5,296,202.92
KNIFE RIVER CORPORATION - SOUTH   $4,330,955.33 1
-18.23% | -$965,247.59
CORNERSTONE PAVING AND CONSTRUCTION, L.L.C.   $4,597,601.75 2
-13.19% | -$698,601.17
6.16% | $266,646.42
BIG CREEK CONSTRUCTION, LTD.   $5,238,529.95 3
-1.09% | -$57,672.97
20.96% | $907,574.62
13.94% | $640,928.20
TEXAS MATERIALS GROUP, INC.   $5,360,843.46 4
1.22% | $64,640.54
23.78% | $1,029,888.13
2.33% | $122,313.51
BRAZOS PAVING, INC.   $5,470,533.69 5
3.29% | $174,330.77
26.31% | $1,139,578.36
2.05% | $109,690.23
FNH CONSTRUCTION, LLC   $7,304,700.40 6
37.92% | $2,008,497.48
68.66% | $2,973,745.07
33.53% | $1,834,166.71
Subcontractor Percentage Amount
CEN-TEX SEEDING, INC. 0.00% $0.00
PROFESSIONAL TRAFFIC CONTROL LLC 0.00% $0.00
STRIPE LINES, INC. 0.00% $0.00
Total: 0.00% $0.00

Bid Items

Items: 34, 0 filtered
BRAZOS US0190  |  BRYAN  |  6451-57-001  |  05/02/2024  |  $5,296,203  |  RMC - 645157001  |  MILL AND INLAY  |  44 W
Item code Description Unit Quantity Engineer's Estimate KNIFE RIVER CORPORATION - SOUTH CORNERSTONE PAVING AND CONSTRUCTION, L.L.C. BIG CREEK CONSTRUCTION, LTD. TEXAS MATERIALS GROUP, INC. BRAZOS PAVING, INC. FNH CONSTRUCTION, LLC
134 6004 BACKFILL (TY A OR B) STA 319.070 $356.000 $166.000 $415.000 $300.000 $595.000 $1,260.000 $450.000
354 6021 PLANE ASPH CONC PAV(0" TO 2") SY 8,890.000 $5.320 $9.300 $2.660 $3.000 $4.100 $4.250 $10.000
354 6045 PLANE ASPH CONC PAV (2") SY 21,270.000 $11.180 $2.450 $2.660 $3.500 $1.000 $6.650 $10.000
500 6001 MOBILIZATION LS 1.000 $119,073.960 $67,220.000 $250,000.000 $500,000.000 $175,500.000 $93,000.000 $700,000.000
502 6001 BARRICADES, SIGNS AND TRAFFIC HANDLING MO 3.000 $6,858.960 $9,688.000 $5,000.000 $5,000.000 $2,200.000 $15,000.000 $20,000.000
506 6038 TEMP SEDMT CONT FENCE (INSTALL) LF 500.000 $4.160 $5.000 $5.000 $4.000 $2.700 $6.100 $4.000
506 6039 TEMP SEDMT CONT FENCE (REMOVE) LF 500.000 $1.450 $2.000 $2.000 $1.000 $2.700 $2.450 $2.000
530 6002 INTERSECTIONS (ACP) SY 5,855.000 $62.570 $32.500 $31.000 $36.000 $40.000 $30.500 $45.000
530 6005 DRIVEWAYS (ACP) SY 320.000 $88.250 $276.000 $60.150 $36.000 $175.400 $37.200 $45.000
533 6003 RUMBLE STRIPS (SHOULDER) ASPHALT LF 64,174.000 $0.630 $0.060 $0.060 $0.300 $0.250 $0.150 $1.000
662 6005 WK ZN PAV MRK NON-REMOV (W)6"(BRK) LF 1,021.500 $0.490 $0.400 $0.380 $0.320 $0.400 $0.500 $3.000
662 6008 WK ZN PAV MRK NON-REMOV (W)6"(SLD) LF 47,726.000 $0.750 $0.400 $0.380 $0.320 $0.400 $0.500 $3.000
662 6037 WK ZN PAV MRK NON-REMOV (Y)6"(SLD) LF 7,677.000 $0.660 $0.400 $0.380 $0.320 $0.400 $0.500 $3.000
662 6109 WK ZN PAV MRK SHT TERM (TAB)TY W EA 4,308.000 $1.730 $2.000 $1.000 $2.000 $2.000 $1.850 $5.000
666 6036 REFL PAV MRK TY I (W)8"(SLD)(100MIL) LF 12,264.000 $1.900 $1.200 $1.090 $1.000 $1.100 $2.000 $6.000
666 6048 REFL PAV MRK TY I (W)24"(SLD)(100MIL) LF 48.000 $14.360 $8.700 $7.810 $7.000 $8.000 $9.750 $20.000
666 6102 REF PAV MRK TY I(W)36"(YLD TRI)(100MIL) EA 106.000 $93.580 $110.000 $99.200 $40.000 $100.000 $53.750 $500.000
666 6225 PAVEMENT SEALER 6" LF 6,040.000 $0.690 $0.250 $0.200 $0.200 $0.200 $0.070 $3.000
666 6306 RE PM W/RET REQ TY I (W)6"(BRK)(100MIL) LF 8,910.000 $0.980 $0.900 $0.810 $0.650 $0.850 $0.850 $3.000
666 6309 RE PM W/RET REQ TY I (W)6"(SLD)(100MIL) LF 35,462.000 $1.440 $0.900 $0.810 $0.650 $0.850 $0.850 $3.000
666 6321 RE PM W/RET REQ TY I (Y)6"(SLD)(100MIL) LF 35,088.000 $1.530 $0.900 $0.810 $0.650 $0.850 $0.850 $3.000
668 6077 PREFAB PAV MRK TY C (W) (ARROW) EA 30.000 $266.630 $286.000 $258.000 $275.000 $260.000 $370.000 $250.000
668 6085 PREFAB PAV MRK TY C (W) (WORD) EA 30.000 $327.010 $305.000 $275.000 $320.000 $280.000 $450.000 $500.000
672 6010 REFL PAV MRKR TY II-C-R EA 445.000 $6.530 $8.000 $7.200 $7.000 $7.200 $7.350 $5.000
677 6001 ELIM EXT PAV MRK & MRKS (4") LF 6,040.000 $1.100 $0.500 $0.450 $1.000 $0.470 $0.750 $3.000
678 6002 PAV SURF PREP FOR MRK (6") LF 6,040.000 $0.190 $0.250 $0.220 $0.100 $0.230 $0.020 $3.000
3080 6007 STONE-MTRX-ASPH SMA-D SAC-A PG76-22 TON 17,914.380 $161.560 $138.000 $146.500 $165.000 $174.000 $175.400 $200.000
3080 6029 TACK COAT GAL 16,285.800 $4.200 $4.200 $3.500 $4.000 $4.200 $5.200 $8.000
3081 6009 TOM-F PG76-22 SAC-A TON 6,187.793 $159.880 $155.000 $165.000 $170.000 $193.000 $162.600 $200.000
3081 6015 TACK COAT GAL 14,995.800 $7.160 $4.200 $3.500 $4.000 $4.250 $5.800 $8.000
6001 6002 PORTABLE CHANGEABLE MESSAGE SIGN EA 2.000 $7,857.890 $6,200.000 $5,000.000 $5,000.000 $5,000.000 $21,990.000 $16,500.000
6056 6001 PREFORMED IN-LANE(TRANS) RUMBLE STRIP LF 108.000 $15.330 $15.000 $14.000 $30.000 $21.430 $28.100 $20.000
6185 6002 TMA (STATIONARY) DAY 38.000 $324.530 $580.000 $150.000 $250.000 $400.000 $240.000 $250.000
6185 6005 TMA (MOBILE OPERATION) DAY 6.000 $356.890 $900.000 $150.000 $500.000 $512.000 $570.000 $550.000
Totals: $5,296,202.92 $4,330,955.34 $4,597,601.76 $5,238,529.95 $5,360,843.47 $5,470,533.69 $7,304,700.40