Show Job Controls
Bid Cobra

BRAZOS FM 974 (0540-03-039)

Items: 77

County: BRAZOS
Length: 0.0000 MILES (2.3797 MILES)
Highway: FM 974
District: BRYAN
Control Number: 0540-03-039
DBE Goal: 0.0%
Project: SSW 540-3-39
Guaranty: $86,000.00
Time: 217 WORKING DAYS
Engineer's Estimate: $4,315,845.66
Date: 07/01/2026 1:00 PM CDT (17 days ago)
Contract Number: 7263013
Type: WIDEN ROAD - ADD SHOULDERS
Project ID: A00206416
Project Description: REHABILITATE ROADWAY AND WIDEN SHOULDERS
Mail/Deliver Bids To:
TEXAS DEPARTMENT OF TRANSPORTATION
ATTN: CONSTRUCTION DIVISION - RM M1C3.02
6230 E STASSNEY LN, AUSTIN, TX 78744
JAMES ROBBINS
JOHN SHEPHERD
Actions:
Notice Questions HCS Excel Tabs Print Print Notice
Bidders (8)
E
Engineer's Estimate
$4,315,845.66
Over/Under Est: -12.61% -$544,253.58
Over/Under Est: -1% -$43,369.33
Amt Left: 13.28% $500,884.25
Over/Under Est: -0.7% -$30,307.71
Amt Left: 13.63% $513,945.87
Delta: -0.31% -$13,061.62
$4,384,483.00
Over/Under Est: 1.59% $68,637.34
Amt Left: 16.25% $612,890.92
Delta: -2.31% -$98,945.05
Over/Under Est: 25.12% $1,084,278.70
Amt Left: 43.18% $1,628,532.28
Delta: -23.16% -$1,015,641.36
Over/Under Est: 27.85% $1,202,086.79
Amt Left: 46.3% $1,746,340.37
Delta: -2.18% -$117,808.09
$5,665,103.85
Over/Under Est: 31.26% $1,349,258.19
Amt Left: 50.2% $1,893,511.77
Delta: -2.67% -$147,171.40
$6,311,852.15
Over/Under Est: 46.25% $1,996,006.49
Amt Left: 67.35% $2,540,260.07
Delta: -11.42% -$646,748.30

Bid Items & Bid Tabulations

77 Total 0 of 77
BRAZOS  |  FM 974  |  BRYAN  |  0540-03-039  |  07/01/2026 1:00 PM CDT  |  $4,315,845.66  |  SSW 540-3-39  |  WIDEN ROAD - ADD SHOULDERS  |  217 WORKING DAYS
Item Code
Description
Unit
Quantity
Engineer's Estimate
BIG CREEK CONSTRUCTION, LTD.
KNIFE RIVER CORPORATION - SOUTH
LARRY YOUNG PAVING, INC.
BRAZOS PAVING, INC.
TEXAS MATERIALS GROUP, INC.
CLARK CONSTRUCTION OF TEXAS, INC.
STX CIVIL
A. L. HELMCAMP, INC.
PREPARING ROW
STA 159.000 $1,216.080 $750.000 $370.000 $380.000 $690.000 $545.000 $496.990 $409.100 $320.000
REMOV CONC (MOWSTRIP)
SY 18.000 $16.000 $150.000 $25.000 $27.000 $140.000 $43.000 $40.000 $23.730 $42.000
REMOV CONC (DRIVEWAYS)
SY 87.000 $31.330 $50.000 $17.000 $18.000 $21.000 $54.000 $50.000 $23.710 $53.000
RMV (2"-8") TRT/UNTRT BASE & ASPH PAV
SY 144.000 $1.660 $20.000 $20.000 $6.750 $20.000 $35.000 $2.080 $9.120 $50.000
EXCAV (ROADWAY)
CY 11,856.400 $15.000 $15.000 $12.000 $18.000 $16.500 $37.000 $29.390 $20.950 $32.000
EMBANK (FNL)(DC)(TY C)
CY 2,424.900 $20.000 $15.000 $11.000 $10.000 $11.550 $16.000 $28.740 $8.900 $42.000
BACKFILL (TY A OR B)
STA 159.000 $160.000 $225.000 $75.000 $200.000 $350.000 $492.000 $769.520 $366.060 $260.000
FURN & PLACE TOPSOIL (4")
SY 42,397.000 $1.600 $0.750 $0.750 $0.500 $1.050 $1.290 $5.350 $3.240 $2.500
BROADCAST SEED (PERM_RURAL_SAND)
SY 42,397.000 $0.200 $0.160 $0.180 $0.250 $0.200 $0.220 $0.280 $0.220 $0.250
BROADCAST SEED (TEMP_WARM)
SY 21,195.000 $0.190 $0.140 $0.150 $0.250 $0.200 $0.160 $0.220 $0.180 $0.200
BROADCAST SEED (TEMP_COOL)
SY 21,195.000 $0.200 $0.140 $0.150 $0.250 $0.200 $0.160 $0.220 $0.180 $0.200
VEGETATIVE WATERING
TGL 426.000 $42.320 $10.000 $58.000 $31.000 $65.000 $27.000 $42.750 $42.240 $42.000
FL BS (CMP IN PLC)(TY A GR 1-2) (10")
SY 52,999.000 $22.000 $23.000 $27.000 $28.000 $27.000 $34.500 $34.400 $40.170 $27.000
REWORK BS MTL (TY B)(8")(ORD COMP)
SY 42,405.000 $2.750 $3.000 $1.250 $2.250 $5.000 $5.450 $2.460 $6.060 $7.000
LIME (COM OR QK)(SLURRY) OR QK(DRY)
TON 211.000 $400.000 $325.000 $300.000 $390.000 $400.000 $335.000 $325.000 $392.810 $300.000
LIME TRT (EXIST MATL)(10")
SY 15,015.000 $7.000 $3.000 $2.500 $5.250 $3.200 $7.250 $5.800 $5.880 $10.000
CEMENT
TON 853.000 $220.000 $225.000 $199.000 $210.000 $251.000 $216.000 $225.000 $283.590 $260.000
CEMENT TRT (EXIST MATL)(10")
SY 60,066.000 $3.000 $2.500 $1.250 $2.500 $3.000 $1.800 $2.610 $4.070 $3.000
ASPH (AC-20-5TR)
GAL 41,335.000 $3.600 $3.750 $4.450 $5.000 $4.500 $4.500 $6.870 $5.850 $5.500
ASPH (RC-250)
GAL 15,018.000 $5.750 $5.000 $4.750 $5.250 $4.000 $5.000 $7.480 $5.650 $5.500
AGGR (TY-PB OR PL, GR-4)(SAC-A)
CY 853.000 $200.000 $160.000 $227.000 $200.000 $170.000 $221.000 $240.510 $165.030 $215.000
AGGR (TY-B OR L, GR-5)
CY 406.000 $150.000 $105.000 $180.000 $170.000 $146.000 $145.000 $223.520 $145.740 $210.000
CUT & RESTORING PAV
SY 17.000 $83.420 $200.000 $60.000 $100.000 $144.000 $245.000 $285.800 $222.600 $240.000
CEM STABIL BKFL
CY 41.000 $297.010 $150.000 $125.000 $120.000 $102.000 $200.000 $185.000 $152.060 $195.000
TRENCH EXCAVATION PROTECTION
LF 43.000 $9.300 $25.000 $50.000 $24.000 $2.000 $13.000 $12.000 $5.000 $13.000
RIPRAP (MOW STRIP)(4 IN)
CY 103.000 $652.130 $650.000 $800.000 $670.000 $600.000 $866.000 $800.000 $630.130 $850.000
RIPRAP (STONE PROTECTION)(18 IN)
CY 4.000 $229.120 $350.000 $330.000 $300.000 $444.000 $270.000 $250.000 $148.760 $265.000
RC PIPE (CL III)(18 IN)
LF 761.000 $75.000 $85.000 $80.000 $75.000 $106.200 $65.000 $60.000 $95.350 $63.000
RC PIPE (CL III)(24 IN)
LF 143.000 $150.000 $125.000 $95.000 $89.000 $124.000 $135.000 $125.000 $120.510 $130.000
RC PIPE (CL III)(36 IN)
LF 48.000 $226.720 $225.000 $200.000 $210.000 $227.000 $270.000 $250.000 $240.890 $265.000
SET (TY II) (18 IN) (RCP) (6: 1) (P)
EA 52.000 $1,200.000 $1,500.000 $1,650.000 $1,300.000 $2,033.000 $1,030.000 $950.000 $2,353.630 $1,000.000
SET (TY II) (24 IN) (RCP) (6: 1) (P)
EA 8.000 $2,218.750 $2,200.000 $2,100.000 $2,600.000 $2,700.000 $2,705.000 $2,500.000 $2,889.960 $2,625.000
SET (TY II) (36 IN) (RCP) (3: 1) (C)
EA 4.000 $4,255.000 $4,500.000 $3,900.000 $4,200.000 $3,342.000 $4,872.000 $4,500.000 $7,034.410 $4,725.000
CLEAN EXIST CULVERTS
EA 2.000 $3,619.240 $3,000.000 $5,000.000 $2,500.000 $4,504.000 $1,625.000 $1,500.000 $2,569.540 $1,575.000
REMOV STR (SET)
EA 62.000 $500.000 $500.000 $300.000 $330.000 $700.000 $758.000 $700.000 $761.330 $735.000
REMOV STR (PIPE)
LF 54.000 $31.120 $30.000 $45.000 $20.000 $26.750 $49.000 $45.000 $31.600 $48.000
REMOV STR (PIPE)
EA 32.000 $1,072.500 $500.000 $585.000 $770.000 $850.000 $1,300.000 $1,200.000 $789.940 $1,260.000
MOBILIZATION
LS 1.000 $392,349.600 $275,000.000 $339,069.000 $250,000.000 $193,720.000 $335,950.000 $455,000.000 $429,333.140 $1,450,000.000
BARRICADES, SIGNS AND TRAFFIC HANDLING
MO 15.000 $4,000.000 $3,000.000 $13,000.000 $8,000.000 $2,472.500 $950.000 $5,191.000 $2,812.600 $7,700.000
PORTABLE CHANGEABLE MESSAGE SIGN
EA 2.000 $5,166.670 $10,000.000 $5,000.000 $5,700.000 $20,525.000 $9,500.000 $25,000.000 $8,797.410 $23,000.000
TMA (STATIONARY)
DAY 218.000 $200.000 $150.000 $175.000 $260.000 $244.000 $450.000 $225.000 $167.460 $300.000
TMA (MOBILE OPERATION)
DAY 15.000 $283.950 $500.000 $500.000 $750.000 $566.000 $450.000 $300.000 $84.020 $750.000
ROCK FILTER DAMS (INSTALL) (TY 2)
LF 1,180.000 $35.000 $30.000 $35.000 $44.000 $47.750 $37.000 $45.000 $35.030 $30.000
ROCK FILTER DAMS (REMOVE)
LF 1,180.000 $10.000 $7.000 $10.000 $13.000 $21.500 $10.000 $20.000 $1.060 $10.000
TEMP SEDMT CONT FENCE (INSTALL)
LF 2,660.000 $4.000 $4.000 $3.500 $4.500 $4.750 $3.600 $3.500 $3.050 $3.750
TEMP SEDMT CONT FENCE (REMOVE)
LF 2,660.000 $2.790 $1.000 $1.000 $1.250 $1.200 $1.000 $1.000 $0.990 $1.250
DRIVEWAYS (CONC)
SY 87.000 $150.000 $150.000 $300.000 $110.000 $98.000 $238.000 $220.000 $117.950 $240.000
DRIVEWAYS (ACP)
SY 490.000 $35.000 $45.000 $85.000 $68.000 $51.500 $100.000 $46.880 $33.850 $154.000
DRIVEWAYS (SURF TREAT)
SY 2,279.000 $30.000 $25.000 $125.000 $41.000 $29.250 $102.000 $44.350 $30.670 $75.000
TURNOUTS (SURF TREAT)
SY 502.000 $73.650 $45.000 $56.000 $29.000 $34.200 $58.000 $35.950 $30.680 $65.000
MTL W-BEAM GD FEN (TIM POST)
LF 1,350.000 $24.090 $30.000 $23.000 $29.000 $33.500 $25.000 $28.350 $31.980 $30.000
REMOVE METAL BEAM GUARD FENCE
LF 248.000 $2.930 $5.000 $5.000 $6.250 $6.000 $5.250 $3.150 $1.810 $3.500
GUARDRAIL END TREATMENT (INSTALL)
EA 8.000 $3,331.430 $3,250.000 $3,250.000 $4,100.000 $3,629.000 $3,515.000 $3,097.500 $4,097.010 $3,100.000
GUARDRAIL END TREATMENT (REMOVE)
EA 2.000 $243.570 $500.000 $500.000 $630.000 $300.000 $540.000 $262.500 $181.020 $275.000
MAILBOX INSTALL-S (TWW-POST) TY 4
EA 29.000 $500.000 $320.000 $315.000 $400.000 $602.750 $341.000 $235.000 $349.970 $250.000
MAILBOX INSTALL-D (TWW-POST) TY 4
EA 5.000 $309.930 $370.000 $365.000 $460.000 $713.000 $395.000 $255.000 $398.240 $270.000
IN SM RD SN SUP&AM TY10BWG(1)SA(P)
EA 71.000 $550.000 $550.000 $515.000 $650.000 $804.000 $557.000 $650.000 $621.490 $690.000
IN SM RD SN SUP&AM TY10BWG(1)SA(U)
EA 2.000 $957.800 $950.000 $950.000 $1,200.000 $1,342.000 $1,029.000 $790.000 $930.430 $830.000
REMOVE SM RD SN SUP&AM
EA 73.000 $129.060 $110.000 $110.000 $140.000 $155.000 $119.000 $100.000 $94.130 $110.000
INSTL DEL ASSM (D-SW)SZ 1(BRF)GF2(BI)
EA 16.000 $37.330 $35.000 $32.000 $40.000 $18.000 $35.000 $20.000 $60.000 $27.000
INSTL OM ASSM (OM-2Z)(WFLX)GND
EA 12.000 $98.480 $90.000 $85.000 $110.000 $18.000 $92.000 $56.000 $120.000 $60.000
REMOVE DELIN & OBJECT MARKER ASSMS
EA 12.000 $24.500 $25.000 $20.000 $25.000 $6.000 $22.000 $15.000 $35.000 $16.000
INSTL OM SM RD SIGN (1-OM-PW)R
EA 4.000 $105.000 $25.000 $25.000 $32.000 $85.000 $27.000 $11.000 $10.620 $12.000
WK ZN PAV MRK NON-REMOV (W)6"(SLD)
LF 31,796.000 $0.270 $0.200 $0.170 $0.250 $0.500 $0.250 $0.250 $0.340 $0.200
WK ZN PAV MRK NON-REMOV (Y)6"(SLD)
LF 31,796.000 $0.330 $0.350 $0.350 $0.500 $0.500 $0.250 $0.250 $0.340 $0.400
WK ZN PAV MRK SHT TERM (TAB)TY Y-2
EA 4,769.000 $2.920 $1.500 $1.100 $0.500 $0.700 $1.080 $2.250 $1.010 $0.600
REFL PAV MRK TY I (W)24"(SLD)(100MIL)
LF 52.000 $6.000 $20.000 $20.000 $28.000 $9.500 $7.850 $8.500 $13.270 $21.000
RE PM TY II (W) 6" (SLD)
LF 31,436.000 $0.500 $0.450 $0.450 $0.750 $0.500 $0.350 $0.250 $0.290 $0.500
RE PM TY II (W) 24" (SLD)
LF 52.000 $4.750 $8.000 $8.000 $11.000 $6.000 $6.750 $4.000 $1.210 $8.500
RE PM TY II (Y) 6" (BRK)
LF 1,679.000 $0.500 $0.450 $0.450 $0.750 $0.500 $0.400 $0.250 $0.300 $0.500
RE PM TY II (Y) 6" (SLD)
LF 19,841.000 $0.580 $0.450 $0.450 $0.750 $0.500 $0.350 $0.250 $0.290 $0.500
REFL PAV MRK TY I (W)6"(SLD)(100MIL)
LF 31,436.000 $0.980 $0.960 $1.000 $1.250 $0.800 $0.650 $0.750 $0.650 $1.000
REFL PAV MRK TY I (Y)6"(BRK)(100MIL)
LF 1,679.000 $1.280 $1.000 $1.000 $1.500 $0.800 $0.680 $0.750 $0.660 $1.000
REFL PAV MRK TY I (Y)6"(SLD)(100MIL)
LF 19,841.000 $1.010 $1.000 $1.000 $1.500 $0.800 $0.650 $0.750 $0.650 $1.000
PRFB RUMBLE STRIP (BLK)(1')(CENTERLINE)
LF 15,898.000 $2.640 $0.100 $0.100 $0.250 $1.100 $4.000 $1.250 $3.800 $0.150
PRFB RUMBLE STRIP (BLK)(1')(EDGELINE)
LF 31,436.000 $3.500 $0.100 $0.100 $0.250 $1.100 $3.450 $1.250 $3.800 $0.150
REFL PAV MRKR TY II-A-A
EA 363.000 $5.920 $8.000 $8.000 $11.000 $7.150 $6.750 $5.000 $4.830 $8.400
Totals: $4,315,845.660 $3,771,592.080 $4,272,476.330 $4,285,537.950 $4,384,482.995 $5,400,124.360 $5,517,932.442 $5,665,103.850 $6,311,852.150
INCLUDES FORCE ACCOUNT WORK AMOUNTS AS FOLLOWS:
Description Amount
EROSION CONTROL MAINTENANCE: CONTRACTOR FORCE ACCOUNT WORK (NON-PART) $12,529.42
SAFETY CONTINGENCY: CONTRACTOR FORCE ACCOUNT WORK (NON-PART) $98,905.42
Total: $111,434.84