BRAZOS FM 974 (0540-03-039)
Items: 77
County: BRAZOS
Length: 0.0000 MILES (2.3797 MILES)
Highway: FM 974
District: BRYAN
Control Number: 0540-03-039
DBE Goal: 0.0%
Project: SSW 540-3-39
Guaranty: $86,000.00
Time: 217 WORKING DAYS
Engineer's Estimate: $4,315,845.66
Date: 07/01/2026 1:00 PM CDT (17 days ago)
Contract Number: 7263013
Type: WIDEN ROAD - ADD SHOULDERS
Project ID: A00206416
Project Description: REHABILITATE ROADWAY AND WIDEN SHOULDERS
Mail/Deliver Bids To:
TEXAS DEPARTMENT OF TRANSPORTATION
ATTN: CONSTRUCTION DIVISION - RM M1C3.02
6230 E STASSNEY LN, AUSTIN, TX 78744
JAMES ROBBINS
JOHN SHEPHERD
BRAZOS FM 974 (0540-03-039)
Project Name: N/A
Project: SSW 540-3-39
Engineer's Estimate: $4,315,845.66
Length: 0.0000 MILES (2.3797 MILES)
Project Class: SAFETY IMPROVEMENT PROJECTS
Limits From: 3 MI S OF FM 2776
Limits To: FM 2776
Project Description: REHABILITATE ROADWAY AND WIDEN SHOULDERS
Bidders (8)
| Bidder | Total Amount | Over/Under Est | Amt Left From Low Bid | Delta Between Bidders |
|---|---|---|---|---|
|
E
Engineer's Estimate
|
$4,315,845.66 | |||
| $3,771,592.08 |
-12.61%
-$544,253.58
|
|||
| $4,272,476.33 |
-1%
-$43,369.33
|
13.28%
$500,884.25
|
||
| $4,285,537.95 |
-0.7%
-$30,307.71
|
13.63%
$513,945.87
|
-0.31%
-$13,061.62
|
|
| $4,384,483.00 |
1.59%
$68,637.34
|
16.25%
$612,890.92
|
-2.31%
-$98,945.05
|
|
| $5,400,124.36 |
25.12%
$1,084,278.70
|
43.18%
$1,628,532.28
|
-23.16%
-$1,015,641.36
|
|
| $5,517,932.45 |
27.85%
$1,202,086.79
|
46.3%
$1,746,340.37
|
-2.18%
-$117,808.09
|
|
| $5,665,103.85 |
31.26%
$1,349,258.19
|
50.2%
$1,893,511.77
|
-2.67%
-$147,171.40
|
|
| $6,311,852.15 |
46.25%
$1,996,006.49
|
67.35%
$2,540,260.07
|
-11.42%
-$646,748.30
|
E
Engineer's Estimate
$4,315,845.66
$3,771,592.08
Over/Under Est:
-12.61%
-$544,253.58
$4,272,476.33
Over/Under Est:
-1%
-$43,369.33
Amt Left:
13.28%
$500,884.25
$4,285,537.95
Over/Under Est:
-0.7%
-$30,307.71
Amt Left:
13.63%
$513,945.87
Delta:
-0.31%
-$13,061.62
$4,384,483.00
Over/Under Est:
1.59%
$68,637.34
Amt Left:
16.25%
$612,890.92
Delta:
-2.31%
-$98,945.05
$5,400,124.36
Over/Under Est:
25.12%
$1,084,278.70
Amt Left:
43.18%
$1,628,532.28
Delta:
-23.16%
-$1,015,641.36
$5,517,932.45
Over/Under Est:
27.85%
$1,202,086.79
Amt Left:
46.3%
$1,746,340.37
Delta:
-2.18%
-$117,808.09
$5,665,103.85
Over/Under Est:
31.26%
$1,349,258.19
Amt Left:
50.2%
$1,893,511.77
Delta:
-2.67%
-$147,171.40
$6,311,852.15
Over/Under Est:
46.25%
$1,996,006.49
Amt Left:
67.35%
$2,540,260.07
Delta:
-11.42%
-$646,748.30
Bid Items & Bid Tabulations
77
Total
0 of 77
INCLUDES FORCE ACCOUNT WORK AMOUNTS AS FOLLOWS:
| Description | Amount |
|---|---|
| EROSION CONTROL MAINTENANCE: CONTRACTOR FORCE ACCOUNT WORK (NON-PART) | $12,529.42 |
| SAFETY CONTINGENCY: CONTRACTOR FORCE ACCOUNT WORK (NON-PART) | $98,905.42 |
| Total: | $111,434.84 |