BOWIE FM 991 (0010-19-012)

Items: 22

County: BOWIE
Length: N/A
Highway: FM 991
District: ATLANTA
Control Number: 0010-19-012
DBE Goal: N/A
Project: STP 2018(645)HES
Guaranty: N/A
Time: 395 WORKING DAYS
Engineer's Estimate: $1,965,618.75
Date: 03/06/2018 (8 years ago)
Contract Number: N/A
Type: SAFETY TREAT FIXED OBJECTS
Mail/Deliver Bids To: N/A
SEE PLANS OR PROPOSAL BOOK
Actions:
Notice HCS Excel Tabs Print Print Notice
Pay Estimates:
Bidders (11)
E
Engineer's Estimate
$1,965,618.75
$1,463,551.05
Over/Under Est: -25.54% -$502,067.70
Over/Under Est: -20.88% -$410,341.00
Amt Left: 6.27% $91,726.70
Over/Under Est: -18.36% -$360,839.80
Amt Left: 9.65% $141,227.90
Delta: -3.18% -$49,501.20
Over/Under Est: -16.25% -$319,339.39
Amt Left: 12.49% $182,728.31
Delta: -2.59% -$41,500.41
$1,657,787.20
Over/Under Est: -15.66% -$307,831.55
Amt Left: 13.27% $194,236.15
Delta: -0.70% -$11,507.84
$1,708,444.75
Over/Under Est: -13.08% -$257,174.00
Amt Left: 16.73% $244,893.70
Delta: -3.06% -$50,657.55
$1,864,881.86
Over/Under Est: -5.12% -$100,736.89
Amt Left: 27.42% $401,330.81
Delta: -9.16% -$156,437.11
Over/Under Est: -2.09% -$41,042.78
Amt Left: 31.5% $461,024.92
Delta: -3.20% -$59,694.11
$2,602,548.50
Over/Under Est: 32.4% $636,929.75
Amt Left: 77.82% $1,138,997.45
Delta: -35.23% -$677,972.53
Over/Under Est: 34.06% $669,479.25
Amt Left: 80.05% $1,171,546.95
Delta: -1.25% -$32,549.50
Over/Under Est: 62.35% $1,225,617.05
Amt Left: 118.05% $1,727,684.75
Delta: -21.11% -$556,137.80

Bid Items & Bid Tabulations

22 Total 0 of 22
BOWIE  |  FM 991  |  ATLANTA  |  0010-19-012  |  03/06/2018  |  $1,965,618.75  |  STP 2018(645)HES  |  SAFETY TREAT FIXED OBJECTS  |  395 WORKING DAYS
Item Code
Description
Unit
Quantity
Engineer's Estimate
CDM HOLDINGS, LLC
STATELINE CONSTRUCTION, LLC
EAST TEXAS BRIDGE, INC.
LONGVIEW BRIDGE AND ROAD, LTD.
H. V. CAVER, INC.
LC JORDAN & SON
PIERCE R & B LLC
HIGHWAY 19 CONSTRUCTION LLC
FNH CONSTRUCTION, LLC
HODGES AND SON CONSTRUCTION COMPANY, INC.
CHAMPION INFRASTRUCTURE, LLC
BLADING
STA 430.000 $325.000 $75.000 $245.000 $135.000 $200.000 $300.000 $150.000 $270.000 $450.000 $200.000 $500.000 $100.000
BLOCK SODDING
SY 2,994.000 $5.000 $5.000 $5.000 $5.300 $5.250 $10.000 $6.000 $5.000 $5.000 $5.500 $4.000 $7.000
BROADCAST SEED (PERM) (RURAL) (SANDY)
SY 11,963.000 $0.250 $0.350 $0.250 $0.250 $0.220 $0.200 $0.250 $0.220 $0.190 $0.500 $1.000 $0.600
VEGETATIVE WATERING
MG 195.000 $10.000 $35.000 $15.000 $11.000 $15.000 $30.000 $100.000 $25.000 $50.000 $50.000 $1.000 $150.000
CUT & RESTORE CONC PAVING
SY 37.000 $250.000 $180.000 $75.000 $250.000 $150.000 $175.000 $210.000 $175.000 $125.000 $85.000 $300.000 $260.000
CUT & RESTORE ASPH PAVING
SY 300.000 $75.000 $115.000 $55.000 $75.000 $100.000 $90.000 $100.000 $105.000 $75.000 $65.000 $200.000 $240.000
CUT AND RESTORE PAV (FLEX BASE)
SY 1,349.000 $25.000 $50.000 $35.000 $25.000 $75.000 $30.000 $40.000 $60.000 $25.000 $45.000 $160.000 $160.000
RIPRAP (CONC)(4 IN)
CY 110.000 $410.000 $325.000 $420.000 $450.000 $500.000 $500.000 $450.000 $450.000 $600.000 $650.000 $600.000 $580.000
RC PIPE (CL III)(18 IN)
LF 3,802.000 $40.000 $42.000 $31.000 $40.000 $36.000 $34.300 $39.000 $40.000 $31.000 $60.000 $70.000 $80.000
RC PIPE (CL III)(21 IN)
LF 8.000 $65.000 $50.000 $56.000 $55.000 $55.000 $49.000 $50.000 $60.000 $45.000 $70.000 $90.000 $100.000
RC PIPE (CL III)(24 IN)
LF 352.000 $62.000 $50.000 $68.000 $55.000 $48.000 $49.500 $45.000 $60.000 $45.000 $85.000 $100.000 $120.000
RC PIPE (CL III)(30 IN)
LF 52.000 $85.000 $67.500 $106.000 $75.000 $64.000 $80.000 $80.000 $105.000 $80.000 $95.000 $100.000 $160.000
RC PIPE (CL III)(36 IN)
LF 36.000 $100.000 $100.000 $135.000 $100.000 $85.000 $100.000 $110.000 $175.000 $150.000 $125.000 $160.000 $240.000
SET (TY II) (18 IN) (RCP) (6: 1) (P)
EA 1,429.000 $675.000 $505.000 $510.000 $550.000 $540.000 $585.000 $640.000 $550.000 $555.000 $850.000 $800.000 $1,100.000
SET (TY II) (21 IN) (RCP) (6: 1) (P)
EA 8.000 $1,120.000 $875.000 $895.000 $850.000 $900.000 $800.000 $850.000 $2,175.000 $952.000 $1,850.000 $950.000 $1,300.000
SET (TY II) (24 IN) (RCP) (6: 1) (P)
EA 136.000 $1,175.000 $835.000 $795.000 $850.000 $865.000 $800.000 $900.000 $1,100.000 $940.000 $2,000.000 $1,200.000 $1,800.000
SET (TY II) (30 IN) (RCP) (6: 1) (P)
EA 16.000 $1,600.000 $1,550.000 $2,010.000 $3,000.000 $1,500.000 $1,500.000 $1,500.000 $3,000.000 $2,060.000 $2,500.000 $2,100.000 $2,200.000
SET (TY II) (36 IN) (RCP) (6: 1) (P)
EA 6.000 $3,800.000 $3,300.000 $4,100.000 $4,500.000 $3,000.000 $2,625.000 $4,000.000 $4,750.000 $3,500.000 $3,000.000 $3,400.000 $3,800.000
REMOV STR (PIPE)
LF 292.000 $12.000 $17.500 $12.000 $10.000 $24.000 $10.000 $10.000 $25.000 $25.000 $30.000 $12.000 $40.000
REMOV STR (PIPE)
EA 149.000 $300.000 $350.000 $200.000 $300.000 $475.000 $160.000 $100.000 $300.000 $200.000 $250.000 $500.000 $450.000
MOBILIZATION
LS 1.000 $178,000.000 $100,600.000 $154,000.000 $150,000.000 $120,000.000 $125,000.000 $180,000.000 $186,000.000 $330,000.000 $225,000.000 $200,000.000 $200,000.000
BARRICADES, SIGNS AND TRAFFIC HANDLING
MO 42.000 $2,500.000 $750.000 $1,800.000 $1,200.000 $1,200.000 $1,500.000 $1.000 $2,500.000 $2,000.000 $5,500.000 $2,000.000 $4,800.000
Totals: $1,965,618.750 $1,463,551.050 $1,555,277.750 $1,604,778.950 $1,646,279.360 $1,657,787.200 $1,708,444.750 $1,864,881.860 $1,924,575.970 $2,602,548.500 $2,635,098.000 $3,191,235.800