Show Job Controls
Bid Cobra

BEXAR IH 10 (0025-02-234)

Items: 75

County: BEXAR
Length: 0.0000 MILES
Highway: IH 10
District: SAN ANTONIO
Control Number: 0025-02-234
DBE Goal: 0.0%
Project: F 2026(916)
Guaranty: $100,000.00
Time: 382 WORKING DAYS
Engineer's Estimate: $10,408,179.05
Date: 1:00 PM AUGUST 05, 2026 (in 5 weeks)
Contract Number: 8263010
Type: ADVANCED TRAFFIC MANAGEMENT SYSTEM
Project ID: A00218304
Contract Type: Federal
Project Description: ITS INFRASTRUCTURE EXPANSION INCLUDING NEW CCTV AND DMS
Mail/Deliver Bids To:
TEXAS DEPARTMENT OF TRANSPORTATION
ATTN: CONSTRUCTION DIVISION - RM M1C3.02
6230 E STASSNEY LN, AUSTIN, TX 78744
BEXAR IH 10 (0025-02-234)
Project Name: N/A
Project: F 2026(916)
Length: 0.0000 MILES
Project Type: CONSTRUCTION
Limits From: IH 10
Limits To: SPACE CENTER DR
Project Description: ITS INFRASTRUCTURE EXPANSION INCLUDING NEW CCTV AND DMS
BEXAR IH 410 (0521-06-175)
Project Name: IH 10: 0521-06-175; ITS
Project: F 2026(916)
Length: 0.0000 MILES
Project Type: CORRIDOR TRAFFIC MANAGEMENT
Limits From: IH 10
Limits To: SPACE CENTER DR
Project Description: ITS INFRASTRUCTURE EXPANSION INCLUDING NEW CCTV AND DMS
Actions:
Notice Questions HCS Excel Print Print Notice

Bid Items & Bid Tabulations

75 Total 0 of 75
BEXAR  |  IH 10  |  SAN ANTONIO  |  0025-02-234  |  1:00 PM AUGUST 05, 2026  |  $10,408,179.05  |  F 2026(916)  |  ADVANCED TRAF MGT SYSTEM  |  382 WORKING DAYS
Item Code
Description
Unit
Quantity
BLOCK SODDING
SY 162.000
VEGETATIVE WATERING
TGL 13.000
DRILL SHAFT (36 IN)
LF 132.000
DRILL SHAFT (48 IN)
LF 189.000
DRILL SHAFT (SIGN MTS) (54 IN)
LF 186.000
DRILL SHAFT (HIGH MAST POLE) (60 IN)
LF 30.000
RIPRAP (CONC)(4 IN)
CY 24.500
RIPRAP (MOW STRIP)(4 IN)
CY 168.500
JACK BOR OR TUN PIPE(16 IN)(STL CASING)
LF 270.000
MOBILIZATION
LS 1.000
BARRICADES, SIGNS AND TRAFFIC HANDLING
MO 24.000
TMA (STATIONARY)
DAY 120.000
TMA (MOBILE OPERATION)
DAY 6.000
MTL W-BEAM GD FEN (TIM POST)
LF 2,800.000
DOWNSTREAM ANCHOR TERMINAL SECTION
EA 11.000
CONNECTOR PLATE FOR THRIE BEAM
EA 3.000
GUARDRAIL END TREATMENT (INSTALL)
EA 14.000
GUARDRAIL END TREATMENT (REMOVE)
EA 3.000
HI MST IL POLE (125 FT)(100 MPH)
EA 1.000
CONDT (PVC) (SCH 40) (2")
LF 14,510.000
CONDT (PVC) (SCH 40) (3") (CONC ENCSE)
LF 103,825.000
CONDT (PVC) (SCH 80) (2") (BORE)
LF 9,950.000
CONDT (PVC) (SCH 80) (3") (BORE)
LF 28,095.000
CONDT (RM) (3")
LF 1,800.000
CONDT (RM) (4")
LF 730.000
CONDUIT (PREPARE)
LF 3,770.000
FIBER OPTIC CABLE ROAD MARKER
EA 68.000
ELEC CONDR (NO.14) INSULATED
LF 40,085.000
ELEC CONDR (NO.8) INSULATED
LF 640.000
ELEC CONDR (NO.6) INSULATED
LF 60,955.000
TRAY CABLE (4 CONDR) (14 AWG)
LF 3,175.000
ITS GND BOX(PCAST) TY 1 (243636)W/APRN
EA 75.000
ITS GND BOX(PCAST) TY 2 (366048)W/APRN
EA 24.000
GROUND BOX TY A (122311)W/APRON
EA 101.000
GROUND BOX TY D (162922)W/APRON
EA 5.000
REMOVE ELECTRICAL SERVICES
EA 2.000
ELC SRV TY D 120/240 100(NS)SS(N)SP(O)
EA 24.000
ELC SRV TY D 120/240 200(NS)SS(N)SP(O)
EA 1.000
REMOVE SM RD SN SUP&AM
EA 9.000
INS OH SN SUP(30 FT BAL TEE)
EA 6.000
PED POLE ASSEMBLY
EA 22.000
INSTALL DMS (POLE MTD CABINET)
EA 6.000
INSTALL DMS (FOUNDATION MTD CABINET)
EA 1.000
SYSTEM INTEGRATION
LS 1.000
ITS RVSD SYSTEM (DATA COLLECTION ONLY)
EA 9.000
REMOVE ITS RSVD (DC ONLY)
EA 1.000
ITS POLE MNT CAB (TY 2)(CONF 2)
EA 1.000
ITS POLE (60 FT)(90 MPH)
EA 9.000
ITS POLE MNT CAB (TY 3)(CONF 1)
EA 9.000
ITS POLE (20 FT) (90 MPH)
EA 13.000
GROUND BOX (PREPARE)
EA 15.000
CCTV FIELD EQUIPMENT (DIGITAL)
EA 12.000
CCTV MOUNT (POLE)
EA 11.000
REMOVE CCTV FIELD EQUIPMENT
EA 6.000
ETHERNET SWITCH (INSTALL ONLY)
EA 24.000
FIBER OPTIC CBL (SINGLE-MODE)(12 FIBER)
LF 107,170.000
FIBER OPTIC FUSION SPLICE
EA 1,406.000
FIBER OPTIC PATCH PANEL (12 POSITION)
EA 50.000
FIBER OPTIC CBL(SINGLE-MODE)(144 FIBER)
LF 57,260.000
FIBER OPTIC PATCH PANEL (144 POSITIONS)
EA 8.000
FO SPLICE ENCLOSURE (TYPE 1)
EA 8.000
INSTALL WRONG WAY DRIVER DETECTION SYS
EA 12.000
REMOVE WRONG WAY DRIVER DETECTION SYS
EA 4.000
ITS GRND MNT CAB (TY 4) (CONF 2)
EA 1.000
ITS GRND MNT CAB (TY 6)(CONF 2)
EA 1.000
REMOVE AND REPLACE DMS
EA 2.000
FURNISH AND INSTALL RWIS
EA 2.000
ALL-IN-ONE ATMOSPHERIC SENSOR
EA 1.000
NON-INTRUSIVE PAVE CONDI & TEMP SENSOR
EA 2.000
NON-INTRUSIVE WATER LEVEL FLOOD SENSOR
EA 1.000
BLUETOOTH DETECTION SYSTEM
EA 10.000
REMOVE EXISTING CABLES (POWER)
LF 2,530.000
REMOVE EXISTING CABLES (COMMUNICATION)
LF 1,540.000
REMOVE EXISTING FIBER HUB
EA 1.000
CCTV ON HIGH MAST ILLUMIN. ASSEM.
EA 1.000
INCLUDES FORCE ACCOUNT WORK AMOUNTS AS FOLLOWS:
Description Amount
STATE FORCE ACCOUNT WORK (NON-PART) $243,600.00
STATE FORCE ACCOUNT WORK (NON-PART) $669,500.00
EROSION CONTROL MAINTENANCE: CONTRACTOR FORCE ACCOUNT WORK (PART) $1,000.00
Total: $914,100.00