Job Info for 0015-07-087

County: BELL Highway: IH 35 Date: 08/02/2024 (3 months ago) Engineer's Estimate: $12,215,676 Control Number: 0015-07-087
Project: STP 2024(924)TP District: WACO Time: 150 WORKING DAYS Type: INFRASTRUCTURE IMPROVEMENTS
Bidder's List
Informational:

Bidders

Name Total Amount Place Over/Under Est Amt Left From Low Bid Delta Between Bidders
Engineer's Estimate $12,215,675.58
TEXAS MATERIALS GROUP, INC.   $12,103,561.02 1
-0.92% | -$112,114.56
JORDAN FOSTER CONSTRUCTION, LLC   $12,505,548.74 2
2.37% | $289,873.16
3.32% | $401,987.72
JAMES CONSTRUCTION GROUP, LLC   $12,859,999.99 3
5.27% | $644,324.41
6.25% | $756,438.97
2.83% | $354,451.25
C. E. BARKER, LTD.   $13,630,201.32 4
11.58% | $1,414,525.74
12.61% | $1,526,640.30
5.99% | $770,201.33
CAPITAL EXCAVATION COMPANY   $13,798,155.69 5
12.95% | $1,582,480.11
14% | $1,694,594.67
1.23% | $167,954.37
AUSTIN ENGINEERING CO., INC.   $13,850,107.90 6
13.38% | $1,634,432.32
14.43% | $1,746,546.88
0.38% | $51,952.21
Subcontractor Percentage Amount
JORDAN FOSTER CONSTRUCTION, LLC 38.17% $4,619,929.24
AUSTIN TRAFFIC SIGNAL CONSTRUCTION CO., INC. 22.64% $2,740,246.21
JR WEST TEXAS CONCRETE LLC 4.06% $491,404.58
ENVIRONMENTAL SAFETY SERVICES, INC. 2.58% $312,271.87
LINEAR TRAFFIC MARKINGS LLC 0.68% $82,304.21
HIGHWAY TRAFFIC CONTROL & SERVICES, LLC 0.15% $18,155.34
Total: 68.28% $8,264,311.45

Bid Items

Items: 76, 0 filtered
BELL IH 35  |  WACO  |  0015-07-087  |  08/02/2024  |  $12,215,676  |  STP 2024(924)TP  |  INFRASTRUCT IMPRVS  |  150 WORKING DAYS
Item code Description Unit Quantity Engineer's Estimate TEXAS MATERIALS GROUP, INC. JORDAN FOSTER CONSTRUCTION, LLC JAMES CONSTRUCTION GROUP, LLC C. E. BARKER, LTD. CAPITAL EXCAVATION COMPANY AUSTIN ENGINEERING CO., INC.
100 6001 PREPARING ROW AC 8.410 $5,000.000 $4,500.000 $43,000.000 $21,983.000 $75,000.000 $2,200.000 $15,000.000
104 6001 REMOVING CONC (PAV) SY 8,435.000 $25.000 $28.000 $16.000 $8.040 $20.590 $21.800 $18.000
104 6015 REMOVING CONC (SIDEWALKS) SY 400.000 $10.000 $47.000 $100.000 $21.160 $34.720 $25.100 $72.000
104 6022 REMOVING CONC (CURB AND GUTTER) LF 2,738.000 $60.000 $10.800 $6.500 $9.230 $4.710 $21.600 $9.000
110 6001 EXCAVATION (ROADWAY) CY 46,365.000 $25.000 $5.500 $17.000 $16.440 $15.540 $11.000 $9.000
132 6025 EMBANKMENT (FINAL) (DENS CONT) (TY C1) CY 35,964.000 $25.000 $5.200 $22.000 $27.610 $27.270 $24.000 $13.000
160 6005 FURNISHING AND PLACING TOPSOIL CY 185.000 $55.000 $51.800 $225.000 $20.130 $5.720 $78.900 $31.000
162 6008 ROLL SODDING SY 2,296.000 $5.750 $12.320 $7.000 $11.620 $13.260 $12.550 $13.000
164 6010 BROADCAST SEED (TEMP) (WARM) AC 1.000 $2,000.000 $1,484.000 $3,200.000 $2,650.000 $2,676.500 $1,510.000 $1,600.000
164 6012 BROADCAST SEED (TEMP) (COOL) AC 8.000 $1,000.000 $1,484.000 $3,200.000 $2,650.000 $2,676.500 $1,510.000 $1,600.000
168 6001 VEGETATIVE WATERING MG 436.560 $35.000 $40.000 $50.000 $36.850 $22.730 $44.900 $35.000
247 6055 FL BS (CMP IN PLC)(TY D GR 3)(FNAL POS) CY 6,790.000 $86.000 $61.000 $57.000 $50.450 $70.700 $65.600 $82.000
260 6016 LIME (HYD, COM, OR QK(SLURRY)) TON 550.000 $400.000 $342.000 $0.010 $326.370 $294.920 $318.000 $386.000
260 6079 LIME TRT (SUBGRADE)(6") SY 40,728.000 $5.000 $5.200 $0.010 $3.550 $6.240 $11.900 $6.500
276 6107 CM TRT(PT MX)(CL N)(TY D)(GR 3)(FN POS) CY 755.000 $250.000 $0.010 $0.010 $92.760 $17.840 $222.000 $150.000
310 6027 PRIME COAT(MC-30 OR AE-P) GAL 8,146.000 $5.500 $4.500 $4.500 $4.500 $4.550 $4.400 $4.500
360 6004 CONC PVMT (CONT REINF - CRCP) (10") SY 40,728.000 $100.000 $107.500 $102.500 $100.500 $106.050 $122.190 $130.000
432 6006 RIPRAP (CONC)(CL B) CY 10.000 $637.500 $550.000 $615.000 $1,190.710 $656.500 $1,070.000 $1,600.000
438 6005 CLEANING AND SEALING JOINTS LF 28.000 $100.000 $100.000 $30.000 $50.000 $55.550 $141.000 $41.000
446 6029 CLEAN AND PAINT EXIST STR (REF NO.1) LS 1.000 $10,000.000 $7,500.000 $8,000.000 $7,254.000 $7,326.540 $7,600.000 $23,000.000
459 6007 GABION MATTRESSES (GALV)(12 IN) SY 802.000 $160.000 $150.000 $73.500 $131.400 $74.350 $183.000 $190.000
500 6001 MOBILIZATION LS 1.000 $1,096,132.330 $1,200,000.000 $1,000,000.000 $1,280,061.350 $1,291,000.000 $1,300,000.000 $1,052,000.000
502 6001 BARRICADES, SIGNS AND TRAFFIC HANDLING MO 10.000 $5,000.000 $1,200.000 $3,800.000 $60,000.000 $505.000 $3,240.000 $6,000.000
506 6003 ROCK FILTER DAMS (INSTALL) (TY 3) LF 256.000 $75.000 $106.530 $81.000 $85.000 $85.850 $91.300 $119.000
506 6011 ROCK FILTER DAMS (REMOVE) LF 256.000 $15.000 $37.100 $29.000 $27.500 $27.780 $29.550 $41.000
506 6020 CONSTRUCTION EXITS (INSTALL) (TY 1) SY 673.000 $35.000 $60.580 $20.000 $17.500 $17.680 $18.800 $68.000
506 6024 CONSTRUCTION EXITS (REMOVE) SY 673.000 $10.000 $19.080 $11.500 $11.500 $11.620 $12.350 $21.000
506 6034 CONSTRUCTION PERIMETER FENCE LF 2,000.000 $8.000 $3.980 $4.000 $6.000 $12.120 $4.300 $5.000
506 6038 TEMP SEDMT CONT FENCE (INSTALL) LF 8,297.000 $4.250 $4.240 $3.600 $3.550 $3.590 $3.800 $5.000
506 6039 TEMP SEDMT CONT FENCE (REMOVE) LF 8,297.000 $1.000 $0.800 $1.150 $0.550 $0.560 $0.600 $0.500
506 6041 BIODEG EROSN CONT LOGS (INSTL) (12") LF 2,170.000 $6.000 $4.240 $6.000 $6.500 $6.570 $7.000 $5.000
506 6043 BIODEG EROSN CONT LOGS (REMOVE) LF 2,170.000 $2.000 $0.800 $2.300 $1.000 $1.010 $1.050 $1.000
508 6001 CONSTRUCTING DETOURS SY 1,465.000 $120.000 $122.000 $135.000 $131.750 $102.010 $135.000 $160.000
512 6013 PORT CTB (DES SOURCE)(SGL SLP)(TY 1) LF 432.000 $20.000 $138.000 $170.000 $8.970 $47.980 $142.000 $41.000
512 6021 PORT CTB (DES SOURCE)(LOW PROF)(TY 1) LF 600.000 $15.000 $10.900 $15.000 $14.120 $20.200 $28.050 $17.000
512 6022 PORT CTB (DES SOURCE)(LOW PROF)(TY 2) LF 40.000 $20.000 $50.300 $80.000 $17.780 $20.200 $42.500 $28.000
512 6045 PORT CTB (STKPL)(LOW PROF)(TY 1) LF 600.000 $15.000 $9.500 $17.000 $14.120 $20.200 $28.050 $15.000
512 6046 PORT CTB (STKPL)(LOW PROF)(TY 2) LF 40.000 $20.000 $47.600 $28.000 $17.780 $20.200 $42.500 $29.000
529 6005 CONC CURB (MONO) (TY II) LF 3,524.000 $15.000 $11.000 $13.200 $22.240 $32.320 $19.300 $18.000
529 6008 CONC CURB & GUTTER (TY II) LF 342.000 $48.000 $44.000 $38.000 $38.510 $36.360 $76.300 $66.000
529 6021 CONC CURB & GUTTER (SLOTTED) LF 115.000 $50.000 $58.000 $79.000 $51.480 $75.750 $92.000 $61.000
529 6037 CONC CURB & GUTTER TY II (MOD) LF 3,630.000 $50.000 $42.000 $38.000 $46.700 $36.360 $80.110 $77.000
531 6002 CONC SIDEWALKS (5") SY 1,388.000 $100.000 $75.000 $98.000 $65.050 $83.330 $99.000 $105.000
531 6005 CURB RAMPS (TY 2) EA 2.000 $2,900.000 $2,500.000 $3,000.000 $2,746.540 $3,030.000 $2,510.000 $2,400.000
531 6013 CURB RAMPS (TY 10) EA 4.000 $3,100.000 $2,500.000 $3,000.000 $2,743.220 $3,535.000 $4,360.000 $2,200.000
536 6003 CONC DIRECTIONAL ISLAND LF 1,406.000 $45.000 $46.000 $87.000 $121.960 $90.900 $102.000 $66.000
545 6007 CRASH CUSH ATTEN (INSTL)(L)(N)(TL3) EA 2.000 $28,000.000 $30,000.000 $31,000.000 $24,506.750 $24,751.820 $34,400.000 $40,000.000
550 6036 CHAIN LINK FENCE (INSTALL) SF 1,685.000 $7.000 $15.000 $9.300 $15.000 $12.120 $35.700 $36.000
552 6009 GATE (SPECIAL) EA 2.000 $5,000.000 $3,500.000 $1,400.000 $3,500.000 $1,010.000 $1,180.000 $1,500.000
644 6004 IN SM RD SN SUP&AM TY10BWG(1)SA(T) EA 12.000 $820.000 $1,144.800 $1,150.000 $1,125.000 $772.650 $930.000 $1,300.000
644 6030 IN SM RD SN SUP&AM TYS80(1)SA(T) EA 2.000 $1,100.000 $1,459.620 $1,500.000 $1,250.000 $868.600 $1,100.000 $1,600.000
644 6050 IN SM RD SN SUP&AM TYS80(2)SA(P) EA 2.000 $1,875.000 $2,326.440 $2,300.000 $1,600.000 $2,065.450 $2,050.000 $2,600.000
644 6060 IN SM RD SN SUP&AM TYTWT(1)WS(P) EA 8.000 $550.000 $706.440 $710.000 $750.000 $540.350 $430.000 $800.000
644 6076 REMOVE SM RD SN SUP&AM EA 22.000 $145.000 $100.700 $100.000 $100.000 $116.150 $85.900 $113.000
662 6008 WK ZN PAV MRK NON-REMOV (W)6"(SLD) LF 495.000 $0.500 $1.120 $2.700 $2.500 $2.530 $5.850 $2.000
662 6037 WK ZN PAV MRK NON-REMOV (Y)6"(SLD) LF 495.000 $0.500 $1.150 $2.700 $2.500 $2.530 $5.850 $2.000
666 6170 REFL PAV MRK TY II (W) 4" (SLD) LF 13,688.000 $0.850 $1.400 $0.750 $0.700 $0.710 $0.900 $2.000
666 6180 REFL PAV MRK TY II (W) 12" (SLD) LF 234.000 $1.000 $1.850 $1.700 $1.600 $1.620 $2.650 $10.000
666 6225 PAVEMENT SEALER 6" LF 1,500.000 $0.600 $0.780 $0.750 $0.700 $0.710 $0.900 $2.000
666 6303 RE PM W/RET REQ TY I (W)4"(SLD)(100MIL) LF 13,688.000 $2.500 $0.830 $2.700 $2.500 $2.530 $1.450 $6.000
666 6356 REFL PAV MRK TY II (R&W)6"(FIRE LANE) LF 3,000.000 $4.000 $5.000 $1.100 $1.060 $1.070 $1.450 $4.000
666 6357 REFL PAV MRK TY II(RED)(SYMBOL)(100MIL) EA 96.000 $100.000 $138.000 $26.000 $25.000 $25.250 $5.850 $13.000
666 6363 REFL PAV MRK TY I (W)12"(SLD)(100MIL)1X LF 234.000 $5.000 $3.000 $7.350 $7.000 $7.070 $7.050 $23.000
668 6077 PREFAB PAV MRK TY C (W) (ARROW) EA 6.000 $400.000 $380.000 $290.000 $275.000 $277.750 $350.000 $571.000
668 6078 PREFAB PAV MRK TY C (W) (DBL ARROW) EA 12.000 $400.000 $235.000 $395.000 $374.000 $377.740 $530.000 $618.000
668 6085 PREFAB PAV MRK TY C (W) (WORD) EA 6.000 $375.000 $285.000 $550.000 $520.000 $525.200 $530.000 $648.000
668 6092 PREFAB PAV MRK TY C (W) (36")(YLD TRI) EA 12.000 $65.000 $60.000 $55.000 $52.000 $52.520 $88.000 $238.000
677 6001 ELIM EXT PAV MRK & MRKS (4") LF 10,974.000 $1.000 $0.600 $1.150 $1.060 $1.070 $0.850 $2.000
677 6008 ELIM EXT PAV MRK & MRKS (ARROW) EA 4.000 $125.000 $55.000 $56.000 $52.000 $52.520 $75.800 $160.000
677 6012 ELIM EXT PAV MRK & MRKS (WORD) EA 6.000 $115.000 $65.000 $56.000 $52.000 $52.520 $89.600 $178.000
678 6001 PAV SURF PREP FOR MRK (4") LF 10,878.000 $0.200 $0.360 $0.570 $0.520 $0.530 $0.500 $0.600
678 6021 PAV SURF PREP FOR MRK (SYMBOL) EA 96.000 $50.000 $1.250 $6.000 $5.200 $5.250 $1.700 $1.000
772 6003 POST AND CABLE FENCE (NEW INSTALLATION) LF 1,000.000 $25.000 $25.860 $26.000 $24.400 $35.350 $22.550 $29.000
3076 6037 D-GR HMA TY-D SAC-B PG64-22 TON 4,481.000 $150.000 $170.000 $117.000 $110.000 $111.100 $113.000 $127.000
6001 6002 PORTABLE CHANGEABLE MESSAGE SIGN EA 8.000 $12,000.000 $20,000.000 $10,000.000 $17,291.230 $8,080.000 $11,900.000 $20,000.000
7204 6001 MEP AND WASTEWATER SYSTEM UPGRADE EA 1.000 $1,275,000.000 $2,741,000.000 $2,831,000.000 $2,157,000.000 $2,768,410.000 $2,327,837.280 $2,600,000.000
Totals: $12,215,675.58 $12,103,561.02 $12,505,548.74 $12,860,000.00 $13,630,201.33 $13,798,155.69 $13,850,107.90