ANGELINA BU 59-G (0176-02-124)

Items: 54

County: ANGELINA
Length: N/A
Highway: BU 59-G
District: LUFKIN
Control Number: 0176-02-124
DBE Goal: N/A
Project: F 2021(825)
Guaranty: N/A
Time: 104 WORKING DAYS
Engineer's Estimate: $979,564.00
Date: 08/04/2021 (4 years ago)
Contract Number: N/A
Type: CONSTRUCT PEDESTRIAN INFRASTRUCTURE
Mail/Deliver Bids To: N/A
SEE PLANS OR PROPOSAL BOOK
Actions:
Notice HCS Excel Tabs Print Print Notice
Pay Estimates:
Documents:
Bidders (6)
E
Engineer's Estimate
$979,564.00
$934,763.00
Over/Under Est: -4.57% -$44,801.00
$1,091,840.00
Over/Under Est: 11.46% $112,276.00
Amt Left: 16.8% $157,077.00
Over/Under Est: 21.28% $208,486.92
Amt Left: 27.1% $253,287.92
Delta: -8.81% -$96,210.92
Over/Under Est: 22.07% $216,234.32
Amt Left: 27.93% $261,035.32
Delta: -0.65% -$7,747.40
$1,230,667.00
Over/Under Est: 25.63% $251,103.00
Amt Left: 31.66% $295,904.00
Delta: -2.92% -$34,868.68
$1,237,585.00
Over/Under Est: 26.34% $258,021.00
Amt Left: 32.4% $302,822.00
Delta: -0.56% -$6,918.00

Bid Items & Bid Tabulations

54 Total 0 of 54
ANGELINA  |  BU 59-G  |  LUFKIN  |  0176-02-124  |  08/04/2021  |  $979,564.00  |  F 2021(825)  |  CONSTRUCT PEDESTRIAN INFRASTRUCT  |  104 WORKING DAYS
Item Code
Description
Unit
Quantity
Engineer's Estimate
DBI SERVICES, LLC
ENCINO LANDSCAPE, INC.
HIGHWAY 19 CONSTRUCTION LLC
HIGHWAY INTELLIGENT TRAFFIC SOLUTIONS, INC.
FNH CONSTRUCTION, LLC
TI-ZACK CONCRETE, INC.
PREPARING ROW
STA 135.000 $500.000 $225.000 $500.000 $1,000.000 $27.380 $750.000 $600.000
REMOVING CONC (DRIVEWAYS)
SY 2,734.000 $20.000 $16.000 $20.000 $25.000 $13.690 $20.000 $35.000
REMOVING CONC (CURB)
LF 45.000 $30.000 $8.000 $10.000 $10.000 $21.900 $20.000 $17.000
REMOVING CONC (CURB AND GUTTER)
LF 700.000 $20.000 $16.000 $10.000 $10.000 $15.330 $20.000 $12.000
REMOVING CONC (HEADWALL)
CY 0.400 $5,000.000 $400.000 $1,000.000 $100.000 $766.500 $5,000.000 $2,000.000
REMOVING CONC (SIDEWALK OR RAMP)
SY 112.000 $30.000 $16.000 $20.000 $25.000 $13.690 $20.000 $25.000
REMOVING CONC (PAVERS)
SY 358.000 $15.000 $8.000 $20.000 $30.000 $9.310 $30.000 $22.000
REMOVING STAB BASE & ASPH PAV (0"-10")
SY 1,002.000 $10.000 $10.000 $20.000 $10.000 $30.110 $20.000 $16.000
SPEC EXCAV WORK (HYD EXCAVATOR)
HR 8.000 $105.000 $500.000 $500.000 $50.000 $112.250 $200.000 $60.000
FURNISHING AND PLACING TOPSOIL (4")
SY 1,501.000 $5.000 $5.000 $3.000 $5.000 $17.000 $8.000 $8.000
BLOCK SODDING
SY 1,501.000 $4.500 $6.000 $6.000 $5.000 $18.780 $6.000 $5.000
BROADCAST SEED (TEMP)(WARM OR COOL)
SY 1,501.000 $0.500 $4.000 $1.000 $1.000 $0.780 $3.000 $1.000
VEGETATIVE WATERING
MG 68.000 $20.000 $100.000 $20.000 $100.000 $55.900 $50.000 $1.000
FLEXIBLE PAVEMENT STRUCTURE REPAIR(6")
SY 50.000 $100.000 $60.000 $100.000 $85.000 $165.310 $200.000 $65.000
CL C CONC (COLLAR)
EA 1.000 $600.000 $800.000 $1,000.000 $1,000.000 $716.750 $2,500.000 $2,000.000
RIPRAP (CONC)(4 IN)
CY 41.200 $500.000 $300.000 $800.000 $500.000 $458.340 $550.000 $600.000
RC PIPE (CL III)(18 IN)
LF 10.000 $120.000 $120.000 $50.000 $100.000 $141.700 $150.000 $120.000
INLET (COMP) (TY SIDEWALK BRIDGE)
EA 1.000 $6,000.000 $8,000.000 $10,000.000 $5,000.000 $7,988.900 $6,500.000 $9,000.000
SET (TY II) (18 IN) (RCP) (6: 1) (P)
EA 1.000 $750.000 $2,000.000 $2,000.000 $1,000.000 $1,220.500 $1,850.000 $1,500.000
ADJUSTING MANHOLES (WATER VALVE BOX)
EA 1.000 $820.000 $500.000 $150.000 $500.000 $621.100 $550.000 $750.000
ADJUSTING MANHOLES (WATER METER)
EA 2.000 $750.000 $400.000 $50.000 $250.000 $824.000 $550.000 $500.000
ADJUSTING MANHOLES (ELECTRIC BOX)
EA 3.000 $750.000 $500.000 $50.000 $350.000 $933.500 $550.000 $250.000
MOBILIZATION
LS 1.000 $88,000.000 $60,000.000 $100,000.000 $100,000.000 $156,243.000 $120,000.000 $100,000.000
BARRICADES, SIGNS AND TRAFFIC HANDLING
MO 10.000 $2,000.000 $4,000.000 $300.000 $5,000.000 $12,504.460 $7,500.000 $1,000.000
TEMP SEDMT CONT FENCE (INSTALL)
LF 1,390.000 $2.500 $3.000 $3.000 $1.000 $3.760 $4.000 $0.100
TEMP SEDMT CONT FENCE (REMOVE)
LF 1,390.000 $1.000 $1.000 $1.000 $1.000 $1.100 $2.000 $0.100
BIODEG EROSN CONT LOGS (INSTL) (8")
LF 470.000 $4.000 $4.000 $6.000 $1.000 $2.270 $18.000 $0.100
BIODEG EROSN CONT LOGS (REMOVE)
LF 470.000 $1.000 $2.000 $1.000 $1.000 $1.100 $9.000 $0.100
COLORED TEXTURED CONC (4")
SY 82.000 $80.000 $80.000 $150.000 $150.000 $127.540 $150.000 $185.000
CONC CURB (TY II)
LF 672.000 $25.000 $20.000 $20.000 $20.000 $30.040 $35.000 $35.000
CONC CURB & GUTTER (TY II)
LF 426.000 $35.000 $38.000 $35.000 $35.000 $34.610 $45.000 $35.000
DRIVEWAYS (CONC)
SY 4,077.000 $75.000 $80.000 $80.000 $85.000 $79.970 $80.000 $95.000
CONC SIDEWALKS (4")
SY 3,839.000 $60.000 $60.000 $70.000 $71.000 $65.100 $55.000 $90.000
CURB RAMPS (TY 7)
EA 9.000 $1,500.000 $1,720.000 $1,500.000 $1,100.000 $1,994.400 $2,500.000 $1,500.000
CURB RAMPS (TY 21)
EA 1.000 $2,400.000 $1,350.000 $2,000.000 $2,500.000 $2,170.350 $2,850.000 $1,500.000
CONDT (PVC) (SCH 40) (2")
LF 65.000 $10.000 $12.000 $20.000 $30.000 $22.350 $15.000 $200.000
IN SM RD SN SUP&AM TY10BWG(1)SB(P)
EA 5.000 $600.000 $870.000 $800.000 $800.000 $674.560 $850.000 $500.000
IN SM RD SN SUP&AM TYS80(1)SA(P)
EA 1.000 $700.000 $700.000 $1,250.000 $1,000.000 $856.800 $850.000 $500.000
IN SM RD SN SUP&AM TYS80(1)SA(U-1EXT)
EA 2.000 $700.000 $1,200.000 $2,000.000 $750.000 $1,175.040 $850.000 $500.000
IN SM RD SN SUP&AM TYTWT(1)WS(P)
EA 5.000 $350.000 $400.000 $600.000 $850.000 $472.400 $850.000 $500.000
RELOCATE SM RD SN SUP&AM TY 10BWG
EA 8.000 $350.000 $600.000 $900.000 $300.000 $566.950 $650.000 $400.000
REMOVE SM RD SN SUP&AM
EA 13.000 $90.000 $125.000 $100.000 $100.000 $219.000 $50.000 $30.000
PREFAB PAV MRK TY C (W) (24") (SLD)
LF 364.000 $12.000 $10.000 $25.000 $15.000 $31.490 $20.000 $16.000
ELIM EXT PAV MRK & MRKS (24")
LF 334.000 $3.000 $3.000 $10.000 $15.000 $7.610 $10.000 $5.000
PAV SURF PREP FOR MRK (24")
LF 364.000 $1.000 $1.000 $15.000 $8.000 $1.750 $10.000 $8.000
PED SIG SEC (LED)(COUNTDOWN)
EA 4.000 $700.000 $600.000 $1,000.000 $471.000 $708.250 $2,850.000 $700.000
TRF SIG CBL (TY A)(12 AWG)(2 CONDR)
LF 472.000 $2.000 $2.000 $5.000 $1.610 $3.270 $3.000 $2.000
TRF SIG CBL (TY A)(12 AWG)(4 CONDR)
LF 888.000 $2.000 $2.500 $5.000 $2.000 $3.180 $3.000 $2.500
PED POLE ASSEMBLY
EA 3.000 $2,750.000 $1,500.000 $2,000.000 $1,640.000 $2,200.000 $2,850.000 $900.000
PED DETECT PUSH BUTTON (APS)
EA 2.000 $780.000 $700.000 $500.000 $767.000 $915.250 $1,850.000 $1,000.000
PED DETECT PUSH BUTTON (STANDARD)
EA 2.000 $650.000 $500.000 $500.000 $400.000 $541.250 $950.000 $650.000
PED DETECTOR CONTROLLER UNIT
EA 1.000 $3,200.000 $3,000.000 $3,000.000 $1,500.000 $2,847.500 $8,500.000 $1,200.000
PORTABLE CHANGEABLE MESSAGE SIGN
EA 2.000 $8,000.000 $4,000.000 $10,000.000 $10,000.000 $7,447.500 $12,500.000 $1.000
TMA (MOBILE OPERATION)
DAY 31.000 $220.000 $250.000 $500.000 $200.000 $210.000 $550.000 $1.000
Totals: $979,564.000 $934,763.000 $1,091,840.000 $1,188,050.920 $1,195,798.328 $1,230,667.000 $1,237,585.000