ANDERSON VA (0910-08-080)

Items: 13

County: ANDERSON
Length: N/A
Highway: VA
District: TYLER
Control Number: 0910-08-080
DBE Goal: N/A
Project: C 910-8-80
Guaranty: N/A
Time: 63 WORKING DAYS
Engineer's Estimate: $1,057,250.00
Date: 02/01/2023 (3 years ago)
Contract Number: N/A
Type: STATE PARK IMPROVEMENTS
Mail/Deliver Bids To: N/A
Actions:
Notice HCS Excel Tabs Print Print Notice
Bidders (6)
E
Engineer's Estimate
$1,057,250.00
Over/Under Est: -9.32% -$98,500.75
$1,241,203.00
Over/Under Est: 17.4% $183,953.00
Amt Left: 29.46% $282,453.75
Over/Under Est: 25.01% $264,378.00
Amt Left: 37.85% $362,878.75
Delta: -6.48% -$80,425.00
$1,365,930.00
Over/Under Est: 29.2% $308,680.00
Amt Left: 42.47% $407,180.75
Delta: -3.35% -$44,302.00
Over/Under Est: 32.12% $339,640.00
Amt Left: 45.7% $438,140.75
Delta: -2.27% -$30,960.00
Over/Under Est: 58.09% $614,182.00
Amt Left: 74.33% $712,682.75
Delta: -19.65% -$274,542.00

Bid Items & Bid Tabulations

13 Total 0 of 13
ANDERSON  |  VA  |  TYLER  |  0910-08-080  |  02/01/2023  |  $1,057,250.00  |  C 910-8-80  |  STATE PARK IMPRVS  |  63 WORKING DAYS
Item Code
Description
Unit
Quantity
Engineer's Estimate
BAKER & COMPANY CONSTRUCTION, LLC
CK NEWBERRY, LLC
HIGHWAY 19 CONSTRUCTION LLC
FNH CONSTRUCTION, LLC
MB WESTERN INDUSTRIAL CONTRACTING COMPANY
DREWERY CONSTRUCTION COMPANY, INCORPORATED
PREPARING ROW
STA 46.000 $100.000 $700.000 $1,000.000 $1,000.000 $2,605.000 $2,150.000 $1,000.000
FL BS (RDWY DEL) (TY B GR 1-2)
TON 15,455.000 $50.000 $41.250 $51.000 $59.000 $50.000 $45.000 $72.000
PRIME COAT (MC-30)
GAL 1,628.000 $5.000 $7.000 $6.000 $10.000 $10.000 $7.500 $16.500
ASPH (AC-20XP, AC-10-2TR, OR AC-20-5TR)
GAL 8,462.000 $5.000 $6.750 $5.000 $6.500 $10.000 $7.500 $5.000
AGGR (TY-PD GR-3 OR TY-PL GR-3)
CY 110.000 $110.000 $435.000 $225.000 $300.000 $450.000 $150.000 $315.000
RC PIPE (CL III)(18 IN)
LF 650.000 $60.000 $47.000 $120.000 $70.000 $95.000 $252.000 $125.000
RC PIPE (CL III)(24 IN)
LF 330.000 $90.000 $47.000 $145.000 $90.000 $125.000 $263.000 $145.000
RC PIPE (CL III)(36 IN)
LF 150.000 $140.000 $34.000 $200.000 $220.000 $180.000 $340.000 $215.000
REMOV STR (PIPE)
EA 23.000 $660.000 $667.000 $600.000 $1,000.000 $500.000 $1,500.000 $1,100.000
MOBILIZATION
LS 1.000 $86,000.000 $95,000.000 $115,000.000 $100,000.000 $130,000.000 $150,000.000 $175,000.000
BARRICADES, SIGNS AND TRAFFIC HANDLING
MO 4.000 $4,000.000 $725.000 $10,000.000 $5,000.000 $8,500.000 $2,650.000 $7,000.000
BACKHOE WORK (EROSION & SEDMT CONT)
HR 40.000 $120.000 $120.000 $75.000 $50.000 $200.000 $105.000 $165.000
PORTABLE CHANGEABLE MESSAGE SIGN
DAY 63.000 $90.000 $55.000 $40.000 $100.000 $150.000 $150.000 $200.000
Totals: $1,057,250.000 $958,749.250 $1,241,203.000 $1,321,628.000 $1,365,930.000 $1,396,890.000 $1,671,432.000