PROOF ROLLING
|
HR
|
16.000
|
$100.000
|
$120.000
|
|
|
FLEXIBLE PAVEMENT STRUCTURE REPAIR(6")
|
SY
|
2,227.000
|
$60.000
|
$84.000
|
|
|
FLEXIBLE PAVEMENT STRUCTURE REPAIR(3")
|
SY
|
1,114.000
|
$30.000
|
$50.000
|
|
|
PLANE ASPH CONC PAV(2" TO 4")
|
SY
|
112,410.000
|
$6.000
|
$4.000
|
|
|
ADJUSTING MANHOLES
|
EA
|
5.000
|
$2,000.000
|
$2,500.000
|
|
|
ADJUSTING MANHOLES (WATER METER)
|
EA
|
5.000
|
$1,000.000
|
$1,000.000
|
|
|
MOBILIZATION
|
LS
|
1.000
|
$370,000.000
|
$580,000.000
|
|
|
BARRICADES, SIGNS AND TRAFFIC HANDLING
|
MO
|
4.000
|
$15,000.000
|
$65,000.000
|
|
|
INTERSECTIONS (ACP)
|
SY
|
7,503.000
|
$40.000
|
$58.000
|
|
|
WK ZN PAV MRK NON-REMOV (W)6"(BRK)
|
LF
|
8,980.000
|
$0.400
|
$0.950
|
|
|
WK ZN PAV MRK NON-REMOV (W)6"(SLD)
|
LF
|
2,290.000
|
$0.400
|
$0.950
|
|
|
WK ZN PAV MRK NON-REMOV (W)8"(SLD)
|
LF
|
746.000
|
$0.800
|
$1.100
|
|
|
WK ZN PAV MRK NON-REMOV (W)18"(SLD)
|
LF
|
320.000
|
$1.200
|
$6.050
|
|
|
WK ZN PAV MRK NON-REMOV (W)24"(SLD)
|
LF
|
903.000
|
$1.500
|
$8.250
|
|
|
WK ZN PAV MRK NON-REMOV (W)(ARROW)
|
EA
|
21.000
|
$50.000
|
$138.000
|
|
|
WK ZN PAV MRK NON-REMOV (Y)6"(BRK)
|
LF
|
6,060.000
|
$0.400
|
$0.950
|
|
|
WK ZN PAV MRK NON-REMOV (Y)6"(SLD)
|
LF
|
33,566.000
|
$0.400
|
$0.950
|
|
WK ZN PAV MRK SHT TERM (TAB)TY W
|
EA
|
1,704.000
|
$2.000
|
$1.250
|
|
WK ZN PAV MRK SHT TERM (TAB)TY Y-2
|
EA
|
3,408.000
|
$2.000
|
$1.200
|
|
REFL PAV MRK TY I (W)8"(SLD)(100MIL)
|
LF
|
661.000
|
$0.700
|
$2.200
|
|
RE PM W/RET REQ TY I (W)6"(BRK)(100MIL)
|
LF
|
8,980.000
|
$0.700
|
$1.100
|
|
RE PM W/RET REQ TY I (W)6"(SLD)(100MIL)
|
LF
|
2,290.000
|
$0.700
|
$1.100
|
|
RE PM W/RET REQ TY I (Y)6"(BRK)(100MIL)
|
LF
|
6,060.000
|
$0.700
|
$1.100
|
|
RE PM W/RET REQ TY I (Y)6"(SLD)(100MIL)
|
LF
|
33,566.000
|
$0.700
|
$1.100
|
|
PREFAB PAV MRK TY B (W)(6")(BRK)
|
LF
|
60.000
|
$3.000
|
$16.500
|
|
PREFAB PAV MRK TY B (W)(6")(DOT)
|
LF
|
42.000
|
$3.000
|
$16.500
|
|
PREFAB PAV MRK TY B (W)(8")(SLD)
|
LF
|
425.000
|
$4.000
|
$22.000
|
|
PREFAB PAV MRK TY B (W)(24")(SLD)
|
LF
|
345.000
|
$15.000
|
$44.000
|
|
PREFAB PAV MRK TY B (W)(ARROW)
|
EA
|
12.000
|
$350.000
|
$775.000
|
|
PREFAB PAV MRK TY C (W) (18") (SLD)
|
LF
|
320.000
|
$12.000
|
$14.850
|
|
PREFAB PAV MRK TY C (W) (24") (SLD)
|
LF
|
264.000
|
$15.000
|
$18.000
|
|
PREFAB PAV MRK TY C (W) (ARROW)
|
EA
|
9.000
|
$350.000
|
$300.000
|
|
REFL PAV MRKR TY I-C
|
EA
|
452.000
|
$3.000
|
$5.500
|
|
REFL PAV MRKR TY II-A-A
|
EA
|
954.000
|
$3.000
|
$5.500
|
|
|
ELIM EXT PAV MRK & MRKS (6")
|
LF
|
278.000
|
$1.000
|
$5.500
|
|
|
ELIM EXT PAV MRK & MRKS (8")
|
LF
|
300.000
|
$1.500
|
$5.500
|
|
|
ELIM EXT PAV MRK & MRKS (12")
|
LF
|
607.000
|
$2.000
|
$5.500
|
|
|
ELIM EXT PAV MRK & MRKS (24")
|
LF
|
330.000
|
$4.000
|
$5.500
|
|
|
ELIM EXT PAV MRK & MRKS (ARROW)
|
EA
|
8.000
|
$20.000
|
$110.000
|
|
|
LITTER REMOVAL
|
CYC
|
3.000
|
$2,100.000
|
$5,000.000
|
|
|
CLEANING / SWEEPING (OUTSIDE MAIN LANE)
|
CYC
|
3.000
|
$2,000.000
|
$10,000.000
|
|
|
REINFORCED FAB FOR ASPH PVMNT OVERLAYS
|
SY
|
112,410.000
|
$6.500
|
$6.850
|
|
|
ASPH FOR REINF FAB (PG76-28)
|
GAL
|
16,857.000
|
$5.750
|
$6.900
|
|
|
TACK COAT
|
GAL
|
24.000
|
$10.000
|
$13.750
|
|
|
D-GR HMA TY-F SAC-B PG76-28
|
TON
|
345.000
|
$300.000
|
$205.000
|
|
|
STONE-MTRX-ASPH SMA-D SAC-A PG76-28
|
TON
|
13,264.000
|
$170.000
|
$205.000
|
|
|
TACK COAT
|
GAL
|
193.000
|
$10.000
|
$13.750
|
|
|
PORTABLE CHANGEABLE MESSAGE SIGN
|
DAY
|
120.000
|
$80.000
|
$100.000
|
|
|
TMA (STATIONARY)
|
DAY
|
240.000
|
$250.000
|
$350.000
|
|
|
TMA (MOBILE OPERATION)
|
DAY
|
36.000
|
$800.000
|
$900.000
|
|
|
TEMP SPEED MONITOR SYS
|
EA
|
1.000
|
$12,500.000
|
$12,000.000
|
|
Totals: |
$4,999,591.350
|
$6,041,330.000
|