County: WOOD Highway: SL 564 Date: 01/09/2019 (5 years ago) Engineer's Estimate: $5,870,280 Control Number: 3240-01-019
Project: STP 2019(323) District: TYLER Time: 101 WORKING DAYS Type: PLANING,PVMT RPR,ACP,OCST,PFS,MBGF,PV MK

Bidders

Name Total Amount Place Over/Under Est Amt Left From Low Bid Delta Between Bidders
Engineer's Estimate $5,870,279.89
REYNOLDS & KAY, LTD.   $5,773,806.79 1
-1.64% | -$96,473.10
LONGVIEW BRIDGE AND ROAD, LTD.   $5,844,679.33 2
-0.44% | -$25,600.56
1.23% | $70,872.54
EAST TEXAS BRIDGE, INC.   $5,865,375.76 3
-0.08% | -$4,904.13
1.59% | $91,568.97
0.35% | $20,696.43
HERITAGE ASPHALT COMPANY LLC   $6,250,538.20 4
6.48% | $380,258.31
8.26% | $476,731.41
6.57% | $385,162.44

Bid Items

Items: 75, 0 filtered
WOOD SL 564  |  TYLER  |  3240-01-019  |  01/09/2019  |  $5,870,280  |  STP 2019(323)  |  PLANING,PVMT RPR,ACP,OCST,PFS,MBGF,PV MK  |  101 WORKING DAYS
Item code Description Unit Quantity Engineer's Estimate REYNOLDS & KAY, LTD. LONGVIEW BRIDGE AND ROAD, LTD. EAST TEXAS BRIDGE, INC. HERITAGE ASPHALT COMPANY LLC
104 6017 REMOVING CONC (DRIVEWAYS) SY 368.000 $12.000 $15.000 $20.000 $20.000 $10.000
104 6054 REMOVING CONCRETE(MOW STRIP) LF 448.000 $10.000 $15.000 $11.500 $9.000 $7.000
132 6021 EMBANKMENT (VEHICLE)(ORD COMP)(TY C) CY 104.000 $22.000 $30.000 $50.000 $25.000 $10.000
134 6001 BACKFILL (TY A) STA 363.580 $275.000 $220.000 $145.000 $300.000 $225.000
164 6054 BOND FBR MTRX SEED (PERM)(RURAL)(SAND) SY 50,478.000 $0.850 $0.650 $0.650 $0.850 $1.000
164 6055 BONDED FBR MTRX SEED (TEMP)(WARM) SY 25,238.000 $0.700 $0.650 $0.650 $0.700 $1.000
164 6056 BONDED FBR MTRX SEED (TEMP)(COOL) SY 25,238.000 $0.700 $0.650 $0.630 $0.700 $1.000
168 6001 VEGETATIVE WATERING MG 1,077.000 $10.000 $15.000 $1.000 $7.000 $30.000
316 6406 ASPH (AC-20XP, AC-10-2TR, OR AC-20-5TR) GAL 79,898.000 $2.800 $3.250 $3.150 $3.500 $4.000
316 6407 AGGR (TY-PD GR-3 OR TY-PL GR-3) CY 1,902.000 $120.000 $115.000 $129.000 $135.000 $175.000
340 6106 D-GR HMA(SQ) TY-D PG64-22 TON 685.000 $150.000 $197.000 $140.000 $185.000 $100.000
342 6002 PFC (ASPHALT) PG76-22 TON 388.000 $130.000 $144.000 $145.000 $140.000 $150.000
342 6014 PFC-F (AGGR) PG76-22 SAC-A TON 6,071.000 $135.000 $144.000 $145.000 $140.000 $150.000
344 6050 SUPERPAVE MIXTURES SP-C PG70-22 TON 25,667.000 $100.000 $102.000 $102.000 $100.000 $101.500
344 6122 SUPERPAVE MIXTURES SP-D PG70-22 TON 2,646.000 $110.000 $109.000 $114.000 $115.000 $100.000
351 6002 FLEXIBLE PAVEMENT STRUCTURE REPAIR(6") SY 4,000.000 $45.000 $44.000 $59.250 $55.000 $40.000
354 6002 PLAN & TEXT ASPH CONC PAV(0" TO 2") SY 20,137.000 $2.000 $2.650 $3.000 $3.000 $2.500
354 6045 PLANE ASPH CONC PAV (2") SY 3,330.000 $2.250 $3.200 $3.550 $3.000 $3.000
354 6088 PLANE ASPH CONC PAV (0" TO 5") SY 6,209.000 $7.000 $4.000 $4.200 $5.000 $3.500
354 6121 PLAN & TEXT ASPH CONC PAV (0" TO 2.75") SY 7,853.000 $2.300 $3.500 $3.450 $5.000 $3.000
354 6180 PLANE ASPH CONC PAV (2.75") SY 2,738.000 $2.500 $4.000 $3.600 $5.000 $3.000
432 6006 RIPRAP (CONC)(CL B) CY 12.000 $350.000 $650.000 $1,200.000 $500.000 $500.000
432 6045 RIPRAP (MOW STRIP)(4 IN) CY 40.000 $500.000 $650.000 $545.000 $450.000 $500.000
500 6001 MOBILIZATION LS 1.000 $530,000.000 $251,000.000 $338,000.000 $300,000.000 $600,000.000
502 6001 BARRICADES, SIGNS AND TRAFFIC HANDLING MO 7.000 $4,800.000 $5,000.000 $3,000.000 $8,000.000 $6,500.000
506 6029 EARTHWORK (EROSN & SEDMT CONT, IN VEH) CY 50.000 $22.000 $15.000 $60.000 $50.000 $100.000
506 6030 BACKHOE WORK (EROSION & SEDMT CONT) HR 50.000 $80.000 $50.000 $100.000 $125.000 $100.000
506 6038 TEMP SEDMT CONT FENCE (INSTALL) LF 1,000.000 $2.600 $3.000 $3.000 $4.000 $4.000
506 6039 TEMP SEDMT CONT FENCE (REMOVE) LF 1,000.000 $0.850 $1.000 $1.200 $1.000 $2.000
506 6046 TRACKHOE WORK (EROSION & SEDMT CONT) HR 50.000 $125.000 $85.000 $100.000 $150.000 $175.000
530 6017 DRIVEWAYS (CONC) (HES) SY 368.000 $92.000 $85.000 $110.000 $100.000 $85.000
533 6001 RUMBLE STRIPS (SHOULDER) LF 20,068.000 $0.180 $0.170 $0.250 $0.500 $0.300
533 6002 RUMBLE STRIPS (CENTERLINE) LF 10,034.000 $0.200 $0.170 $0.500 $0.800 $0.350
540 6001 MTL W-BEAM GD FEN (TIM POST) LF 450.000 $22.000 $20.000 $25.000 $21.000 $22.000
540 6006 MTL BEAM GD FEN TRANS (THRIE-BEAM) EA 4.000 $1,750.000 $1,530.000 $1,760.000 $1,800.000 $1,500.000
542 6001 REMOVE METAL BEAM GUARD FENCE LF 400.000 $3.500 $2.250 $4.400 $3.000 $3.000
542 6004 RM MTL BM GD FENCE TRANS (THRIE-BEAM) EA 4.000 $250.000 $167.000 $248.000 $200.000 $175.000
544 6001 GUARDRAIL END TREATMENT (INSTALL) EA 4.000 $2,500.000 $2,950.000 $2,900.000 $3,000.000 $3,000.000
544 6003 GUARDRAIL END TREATMENT (REMOVE) EA 4.000 $300.000 $222.000 $275.000 $220.000 $250.000
556 6008 PIPE UNDERDRAINS (TY 8) (6") LF 5,000.000 $41.000 $43.000 $30.000 $10.000 $25.000
658 6062 INSTL DEL ASSM (D-SW)SZ 1(BRF)GF2(BI) EA 26.000 $35.000 $28.000 $49.500 $35.000 $35.000
662 6001 WK ZN PAV MRK NON-REMOV (W)4"(BRK) LF 116.000 $0.230 $1.100 $1.100 $1.100 $1.000
662 6004 WK ZN PAV MRK NON-REMOV (W)4"(SLD) LF 83,804.000 $0.200 $0.110 $0.110 $0.120 $0.150
662 6012 WK ZN PAV MRK NON-REMOV (W)8"(SLD) LF 16,138.000 $0.350 $0.280 $0.280 $0.270 $0.250
662 6016 WK ZN PAV MRK NON-REMOV (W)24"(SLD) LF 791.000 $2.350 $2.750 $2.750 $3.000 $2.500
662 6032 WK ZN PAV MRK NON-REMOV (Y)4"(BRK) LF 3,683.000 $0.220 $0.110 $0.110 $0.120 $0.150
662 6034 WK ZN PAV MRK NON-REMOV (Y)4"(SLD) LF 70,824.000 $0.170 $0.110 $0.110 $0.120 $0.150
662 6109 WK ZN PAV MRK SHT TERM (TAB)TY W EA 842.000 $1.000 $0.950 $1.250 $1.750 $1.000
662 6110 WK ZN PAV MRK SHT TERM (TAB)TY Y EA 5,102.000 $1.250 $0.950 $1.250 $1.750 $1.000
662 6112 WK ZN PAV MRK SHT TERM RMV (W)(4") LF 1,624.000 $1.050 $1.100 $1.450 $1.750 $1.000
662 6113 WK ZN PAV MRK SHT TERM RMV (Y)(4") LF 14,412.000 $1.100 $1.100 $1.450 $1.750 $1.000
666 6036 REFL PAV MRK TY I (W)8"(SLD)(100MIL) LF 16,136.000 $0.750 $0.900 $0.880 $0.880 $1.000
666 6048 REFL PAV MRK TY I (W)24"(SLD)(100MIL) LF 1,268.000 $5.000 $5.500 $5.500 $5.500 $5.500
666 6170 REFL PAV MRK TY II (W) 4" (SLD) LF 970.000 $0.280 $1.100 $1.100 $1.100 $1.000
666 6207 REFL PAV MRK TY II (Y) 4" (SLD) LF 970.000 $0.280 $1.100 $1.100 $1.100 $1.000
666 6300 RE PM W/RET REQ TY I (W)4"(BRK)(100MIL) LF 116.000 $0.350 $1.100 $1.100 $1.100 $1.000
666 6303 RE PM W/RET REQ TY I (W)4"(SLD)(100MIL) LF 67,454.000 $0.250 $0.450 $0.440 $0.450 $0.500
666 6312 RE PM W/RET REQ TY I (Y)4"(BRK)(100MIL) LF 2,434.000 $0.320 $0.500 $0.500 $0.500 $0.500
666 6315 RE PM W/RET REQ TY I (Y)4"(SLD)(100MIL) LF 59,698.000 $0.250 $0.450 $0.450 $0.450 $0.500
666 6342 REF PROF PAV MRK TY I(W)4"(SLD)(100MIL) LF 19,430.000 $0.820 $0.700 $0.700 $0.700 $0.750
666 6344 REF PROF PAV MRK TY I(Y)4"(BRK)(100MIL) LF 1,249.000 $1.700 $0.800 $0.800 $0.800 $0.750
666 6345 REF PROF PAV MRK TY I(Y)4"(SLD)(100MIL) LF 9,620.000 $1.000 $0.800 $0.800 $0.800 $0.750
668 6077 PREFAB PAV MRK TY C (W) (ARROW) EA 49.000 $195.000 $206.000 $200.000 $200.000 $200.000
668 6078 PREFAB PAV MRK TY C (W) (DBL ARROW) EA 5.000 $340.000 $278.000 $275.000 $300.000 $275.000
668 6085 PREFAB PAV MRK TY C (W) (WORD) EA 49.000 $260.000 $250.000 $250.000 $250.000 $275.000
668 6091 PREFAB PAV MRK TY C (W) (18")(YLD TRI) EA 128.000 $25.000 $39.000 $38.500 $45.000 $40.000
672 6007 REFL PAV MRKR TY I-C EA 608.000 $3.000 $3.750 $3.750 $4.000 $4.000
672 6009 REFL PAV MRKR TY II-A-A EA 4,634.000 $2.650 $3.500 $3.500 $4.000 $4.000
677 6001 ELIM EXT PAV MRK & MRKS (4") LF 1,940.000 $0.300 $1.100 $1.100 $1.100 $1.000
678 6001 PAV SURF PREP FOR MRK (4") LF 1,940.000 $0.150 $0.550 $0.550 $0.550 $0.500
6001 6001 PORTABLE CHANGEABLE MESSAGE SIGN DAY 28.000 $90.000 $80.000 $65.000 $200.000 $700.000
6001 6002 PORTABLE CHANGEABLE MESSAGE SIGN EA 2.000 $9,500.000 $3,500.000 $6,000.000 $15,000.000 $20,000.000
6056 6002 PREFORMED CENTERLINE RUMBLE STRIP LF 625.000 $3.500 $9.000 $8.800 $9.000 $9.000
6185 6001 TMA (STATIONARY) EA 1.000 $5,000.000 $9,200.000 $6,500.000 $30,000.000 $12,000.000
6185 6005 TMA (MOBILE OPERATION) DAY 40.000 $23.000 $105.000 $110.000 $300.000 $125.000
Totals: $5,870,279.89 $5,773,806.79 $5,844,679.33 $5,865,375.76 $6,250,538.20