WOOD FM 14 (0492-03-040)
Items: 52
County: WOOD
Length: N/A
Highway: FM 14
District: TYLER
Control Number: 0492-03-040
DBE Goal: N/A
Project: STP 2023(452)HES
Guaranty: N/A
Time: 72 WORKING DAYS
Engineer's Estimate: $2,407,434.60
Date: 02/02/2023 (3 years ago)
Contract Number: N/A
Type: HAZARD ELIMINATION & SAFETY
Mail/Deliver Bids To: N/A
LANCE POMYKAL
Bidders (2)
| Bidder | Total Amount | Over/Under Est | Amt Left From Low Bid | Delta Between Bidders |
|---|---|---|---|---|
|
E
Engineer's Estimate
|
$2,407,434.60 | |||
| $2,614,763.55 |
8.61%
$207,328.95
|
|||
| $3,278,125.75 |
36.17%
$870,691.15
|
25.37%
$663,362.20
|
E
Engineer's Estimate
$2,407,434.60
1
Awarded
$2,614,763.55
Over/Under Est:
8.61%
$207,328.95
$3,278,125.75
Over/Under Est:
36.17%
$870,691.15
Amt Left:
25.37%
$663,362.20
Bid Items & Bid Tabulations
52
Total
0 of 52