Show Job Controls
Bid Cobra

WOOD SH 37 (0190-03-087)

Items: 80

County: WOOD
Length: N/A
Highway: SH 37
District: TYLER
Control Number: 0190-03-087
DBE Goal: N/A
Project: F 2021(820)
Guaranty: N/A
Time: 83 WORKING DAYS
Engineer's Estimate: $4,596,702.33
Date: 08/04/2021 (4 years ago)
Contract Number: N/A
Type: ROADWAY REHABILITATION/RECONSTRUCTION WITH NO ADDE
Mail/Deliver Bids To: N/A
SEE PLANS OR PROPOSAL BOOK
Actions:
Notice HCS Excel Tabs Print Print Notice
Documents:
Bidders (3)
E
Engineer's Estimate
$4,596,702.33
$4,577,457.44
Over/Under Est: -0.42% -$19,244.89
Over/Under Est: 1.62% $74,600.21
Amt Left: 2.05% $93,845.10
Over/Under Est: 2.66% $122,062.79
Amt Left: 3.09% $141,307.68
Delta: -1.02% -$47,462.58
Subcontractor Percentage Amount
MORRIS COUNTY CONTRACTORS, L.L.C. 2.56% $213,941.98
ISAACS CONSTRUCTION SERVICES LLC 0.94% $78,556.82
STRIPING TECHNOLOGY, L.P. 0.75% $62,678.31
SOUTHWEST ENVIRONMENT SERVICES LLC 0.58% $48,471.23
PINNACLE GRINDING AND GROOVING LLC 0.14% $11,699.95
PANOLA SIGN & BARRICADE, INC. 0.12% $10,028.53
Total: 5.09% $425,376.82

Bid Items & Bid Tabulations

80 Total 0 of 80
WOOD  |  SH 37  |  TYLER  |  0190-03-087  |  08/04/2021  |  $4,596,702.33  |  F 2021(820)  |  ROADWAY REHAB/RECON WITH NO ADDE  |  83 WORKING DAYS
Item Code
Description
Unit
Quantity
Engineer's Estimate
EAST TEXAS BRIDGE, INC.
LONGVIEW BRIDGE AND ROAD, LTD.
TEXAS MATERIALS GROUP, INC.
PREPARING ROW
STA 2.000 $800.000 $10,000.000 $2,800.000 $1,400.000
REMOVING CONC (DRIVEWAYS)
SY 213.000 $20.000 $20.000 $25.000 $18.000
REMOVING CONC (FLUME)
SY 40.000 $15.000 $20.000 $35.000 $18.000
SUBGRADE WIDENING (ORD COMP)
STA 211.640 $300.000 $450.000 $235.000 $220.000
EMBANKMENT (VEHICLE)(ORD COMP)(TY C)
CY 6,997.000 $35.000 $20.000 $18.000 $24.000
BACKFILL (TY A)
STA 271.140 $250.000 $150.000 $275.000 $246.000
BLADING
STA 210.000 $300.000 $150.000 $205.000 $0.010
FURNISHING AND PLACING TOPSOIL (4")
SY 36,434.000 $1.500 $1.350 $2.250 $1.050
BROADCAST SEED (PERM) (RURAL) (SANDY)
SY 18,076.000 $0.200 $0.160 $0.170 $0.100
BOND FBR MTRX SEED (PERM)(RURAL)(SAND)
SY 36,152.000 $0.850 $0.700 $0.700 $0.790
BONDED FBR MTRX SEED (TEMP)(WARM)
SY 18,076.000 $0.650 $0.680 $0.700 $0.690
BONDED FBR MTRX SEED (TEMP)(COOL)
SY 18,076.000 $0.650 $0.680 $0.700 $0.690
VEGETATIVE WATERING
MG 994.000 $11.500 $7.000 $1.000 $25.000
TBPFC (MEMBRANE)
GAL 27,118.000 $3.050 $3.000 $3.500 $3.000
TBPFC (ASPHALT)(PG 76-22)
TON 611.000 $185.000 $175.000 $185.000 $166.000
TBPFC (AGGREGATE) (SAC-A)
TON 9,559.000 $185.000 $175.000 $185.000 $166.000
FLEXIBLE PAVEMENT STRUCTURE REPAIR(6")
SY 3,500.000 $55.000 $55.000 $55.000 $52.000
PLANE ASPH CONC PAV (0" TO 1 1/2")
SY 4,265.000 $3.000 $6.000 $3.000 $3.450
CL C CONC (COLLAR)
EA 5.000 $800.000 $1,200.000 $1,200.000 $900.000
RIPRAP (MOW STRIP)(4 IN)
CY 143.000 $460.000 $450.000 $510.000 $620.000
RETROFIT RAIL (TY T631)
LF 1,625.000 $110.000 $82.000 $82.000 $90.000
RC PIPE (CL III)(18 IN)
LF 1,652.000 $40.000 $45.000 $53.500 $55.000
RC PIPE (CL III)(24 IN)
LF 666.000 $55.000 $60.000 $70.000 $75.000
RC PIPE (CL III)(48 IN)
LF 4.000 $175.000 $400.000 $255.000 $475.000
INLET(COMPL)(PAZD)(FG)(3FTX3FT-3FTX3FT)
EA 1.000 $3,600.000 $6,000.000 $6,000.000 $5,700.000
SET (TY II) (18 IN) (RCP) (6: 1) (P)
EA 120.000 $600.000 $625.000 $660.000 $1,350.000
SET (TY II) (24 IN) (RCP) (4: 1) (C)
EA 4.000 $800.000 $800.000 $825.000 $1,430.000
SET (TY II) (24 IN) (RCP) (6: 1) (P)
EA 42.000 $875.000 $1,000.000 $1,050.000 $1,725.000
SET (TY II) (48 IN) (RCP) (4: 1) (C)
EA 1.000 $4,500.000 $7,000.000 $4,300.000 $8,250.000
REMOV STR (PIPE)
EA 68.000 $312.000 $500.000 $475.000 $335.000
MOBILIZATION
LS 1.000 $312,000.000 $400,000.000 $420,000.000 $455,835.000
BARRICADES, SIGNS AND TRAFFIC HANDLING
MO 7.000 $5,000.000 $20,000.000 $5,000.000 $39,000.000
ROCK FILTER DAMS (INSTALL) (TY 1)
LF 1,000.000 $30.000 $28.000 $27.500 $29.000
ROCK FILTER DAMS (INSTALL) (TY 2)
LF 1,095.000 $31.000 $30.000 $31.000 $31.000
ROCK FILTER DAMS (REMOVE)
LF 2,095.000 $9.000 $7.000 $7.700 $8.250
EARTHWORK (EROSN & SEDMT CONT, IN VEH)
CY 150.000 $23.000 $30.000 $35.000 $12.000
BACKHOE WORK (EROSION & SEDMT CONT)
HR 50.000 $75.000 $75.000 $275.000 $86.000
TEMP SEDMT CONT FENCE (INSTALL)
LF 6,610.000 $3.250 $3.000 $3.050 $2.350
TEMP SEDMT CONT FENCE (REMOVE)
LF 6,610.000 $1.100 $0.500 $0.550 $0.550
TRACKHOE WORK (EROSION & SEDMT CONT)
HR 50.000 $102.000 $125.000 $275.000 $0.010
INTERSECTIONS (ACP)
SY 3,920.000 $55.000 $40.000 $46.000 $35.000
DRIVEWAYS (ACP)
SY 3,025.000 $35.000 $30.000 $40.000 $40.000
DRIVEWAYS (CONC) (HES)
SY 213.000 $100.000 $100.000 $125.000 $100.000
RUMBLE STRIPS (SHOULDER)
LF 54,204.000 $0.200 $0.250 $0.180 $0.080
RUMBLE STRIPS (CENTERLINE)
LF 27,102.000 $0.200 $0.400 $0.140 $0.080
MTL W-BEAM GD FEN (STEEL POST)
LF 2,275.000 $30.000 $30.000 $30.000 $32.000
REMOVE METAL BEAM GUARD FENCE
LF 2,250.000 $4.000 $3.000 $2.200 $3.050
GUARDRAIL END TREATMENT (INSTALL)
EA 8.000 $2,215.000 $3,200.000 $3,025.000 $2,850.000
GUARDRAIL END TREATMENT (REMOVE)
EA 8.000 $220.000 $300.000 $220.000 $265.000
MAILBOX INSTALL-S (TWG-POST) TY 2
EA 38.000 $275.000 $300.000 $415.000 $300.000
MAILBOX INSTALL-D (TWG-POST) TY 2
EA 6.000 $300.000 $400.000 $565.000 $325.000
INSTL DEL ASSM (D-SW)SZ 1(BRF)GF2
EA 36.000 $27.000 $35.000 $27.500 $47.000
INSTL DEL ASSM (D-SW)SZ 1(BRF)GF2(BI)
EA 18.000 $21.000 $35.000 $27.500 $47.000
INSTL OM ASSM (OM-2Z)(WFLX)GND
EA 30.000 $48.000 $55.000 $44.000 $67.000
WK ZN PAV MRK NON-REMOV (W)4"(SLD)
LF 54,226.000 $0.200 $0.140 $0.140 $0.140
WK ZN PAV MRK NON-REMOV (W)8"(SLD)
LF 868.000 $0.200 $0.550 $0.550 $0.520
WK ZN PAV MRK NON-REMOV (W)24"(SLD)
LF 40.000 $1.600 $5.000 $4.400 $4.200
WK ZN PAV MRK NON-REMOV (Y)4"(BRK)
LF 11,176.000 $0.200 $0.140 $0.140 $0.140
WK ZN PAV MRK NON-REMOV (Y)4"(SLD)
LF 41,720.000 $0.200 $0.140 $0.140 $0.140
WK ZN PAV MRK SHT TERM RMV (W)(4")
LF 195.000 $1.500 $2.000 $1.200 $1.090
WK ZN PAV MRK SHT TERM RMV (Y)(4")
LF 6,293.000 $1.250 $2.000 $1.400 $1.090
REFL PAV MRK TY I (W)8"(SLD)(100MIL)
LF 868.000 $0.850 $1.100 $1.100 $1.050
REFL PAV MRK TY I (W)24"(SLD)(100MIL)
LF 300.000 $3.450 $7.000 $6.600 $6.250
REFL PAV MRK TY II (W) 4" (SLD)
LF 1,624.000 $0.120 $0.550 $0.550 $0.540
REFL PAV MRK TY II (Y) 4" (BRK)
LF 203.000 $0.120 $0.550 $0.550 $0.540
RE PM W/RET REQ TY I (W)4"(SLD)(100MIL)
LF 57,706.000 $0.450 $0.440 $0.440 $0.420
RE PM W/RET REQ TY I (Y)4"(BRK)(100MIL)
LF 5,385.000 $0.450 $0.550 $0.550 $0.540
RE PM W/RET REQ TY I (Y)4"(SLD)(100MIL)
LF 26,790.000 $0.450 $0.440 $0.440 $0.420
PREFAB PAV MRK TY C (W) (ARROW)
EA 5.000 $180.000 $220.000 $220.000 $215.000
PREFAB PAV MRK TY C (W) (WORD)
EA 5.000 $250.000 $270.000 $275.000 $260.000
REFL PAV MRKR TY I-A
EA 66.000 $3.150 $6.000 $5.500 $5.300
REFL PAV MRKR TY I-C
EA 44.000 $3.000 $6.000 $5.500 $5.300
REFL PAV MRKR TY II-A-A
EA 1,048.000 $3.500 $4.000 $3.850 $3.750
ELIM EXT PAV MRK & MRKS (4")
LF 1,827.000 $0.450 $1.100 $1.100 $1.070
SP MIXES SP-B PG64-22
TON 2,131.000 $110.000 $120.000 $130.000 $135.000
SP MIXES SP-D PG64-22 (LEVEL-UP)
TON 484.000 $112.000 $130.000 $148.000 $120.000
TACK COAT
GAL 939.000 $3.160 $5.000 $3.900 $0.010
PORTABLE CHANGEABLE MESSAGE SIGN
EA 2.000 $13,500.000 $40,000.000 $18,000.000 $6,400.000
TMA (STATIONARY)
DAY 40.000 $350.000 $300.000 $200.000 $285.000
TMA (MOBILE OPERATION)
DAY 20.000 $550.000 $300.000 $200.000 $0.010
Totals: $4,596,702.330 $4,577,457.440 $4,671,302.540 $4,718,765.120