Show Job Controls
Bid Cobra

WISE SH 114 (0353-01-027)

Items: 15

County: WISE
Length: N/A
Highway: SH 114
District: FORT WORTH
Control Number: 0353-01-027
DBE Goal: N/A
Project: STP 2022(868)HES
Guaranty: N/A
Time: 106 WORKING DAYS
Engineer's Estimate: $894,818.19
Date: 08/04/2022 (3 years ago)
Contract Number: N/A
Type: HAZARD ELIMINATION & SAFETY
Mail/Deliver Bids To: N/A
SEE PLANS OR PROPOSAL BOOK
Actions:
Notice HCS Excel Tabs Print Print Notice
Documents:
Bidders (4)
E
Engineer's Estimate
$894,818.19
$919,578.95
Over/Under Est: 2.77% $24,760.76
Over/Under Est: 18.35% $164,176.00
Amt Left: 15.16% $139,415.24
Over/Under Est: 28.57% $255,674.95
Amt Left: 25.11% $230,914.19
Delta: -8.64% -$91,498.95
Over/Under Est: 32.18% $287,952.50
Amt Left: 28.62% $263,191.74
Delta: -2.81% -$32,277.55

Bid Items & Bid Tabulations

15 Total 0 of 15
WISE  |  SH 114  |  FORT WORTH  |  0353-01-027  |  08/04/2022  |  $894,818.19  |  STP 2022(868)HES  |  HAZARD ELIM & SAFETY  |  106 WORKING DAYS
Item Code
Description
Unit
Quantity
Engineer's Estimate
GRATIOT CONSTRUCTION, LTD.
MASSANA CONSTRUCTION INC.
ROADWAY SPECIALTIES, INC.
SCR CIVIL CONSTRUCTION, LLC
PREPARING ROW
AC 1.210 $2,500.000 $4,000.000 $6,150.000 $22,388.860 $15,200.000
CELL FBR MLCH SEED(PERM)(RURAL)(SANDY)
SY 12,189.710 $1.500 $0.750 $0.580 $1.580 $1.350
VEGETATIVE WATERING
MG 426.610 $30.000 $8.000 $61.500 $115.150 $90.000
RIPRAP (MOW STRIP)(5 IN)
CY 846.480 $420.000 $380.000 $450.000 $485.330 $564.000
MOBILIZATION
LS 1.000 $81,347.100 $88,000.000 $140,872.500 $150,000.000 $85,000.000
BARRICADES, SIGNS AND TRAFFIC HANDLING
MO 7.000 $9,000.000 $8,000.000 $8,500.000 $1,972.500 $7,425.000
BIODEG EROSN CONT LOGS (INSTL) (12")
LF 1,155.000 $4.000 $6.000 $2.750 $3.830 $12.000
BIODEG EROSN CONT LOGS (REMOVE)
LF 1,155.000 $1.250 $1.000 $1.000 $1.320 $2.000
CABLE BARRIER SYSTEM (TL-4)
LF 18,284.630 $12.500 $16.500 $17.150 $19.430 $19.000
CABLE BARRIER TERMINAL SECTION (TL-4)
EA 22.000 $4,500.000 $5,150.000 $4,500.000 $3,807.710 $4,100.000
POST AND CABLE FENCE (REMOVAL)
LF 450.000 $3.000 $5.000 $3.500 $5.680 $12.000
POST AND CABLE FENCE (REMV CONC ANCHOR)
EA 4.000 $300.000 $200.000 $300.000 $255.470 $600.000
PORTABLE CHANGEABLE MESSAGE SIGN
DAY 106.000 $75.000 $15.000 $50.000 $92.050 $60.000
TMA (STATIONARY)
DAY 106.000 $120.000 $50.000 $95.000 $170.950 $200.000
TMA (MOBILE OPERATION)
DAY 20.000 $200.000 $175.000 $95.000 $197.250 $300.000
Totals: $894,818.190 $919,578.958 $1,058,994.201 $1,150,493.153 $1,182,770.698