Job Info for 0013-06-047

County: WISE Highway: US 81 Date: 04/08/2021 (3 years ago) Engineer's Estimate: $3,078,934 Control Number: 0013-06-047
Project: STP 2021(494)HES District: FORT WORTH Time: 171 WORKING DAYS Type: INSTALL TRAFFIC SIGNAL

Bidders

Name Total Amount Place Over/Under Est Amt Left From Low Bid Delta Between Bidders
Engineer's Estimate $3,078,934.05
AUSTIN BRIDGE & ROAD SERVICES, LP   $2,749,994.21 1
-10.68% | -$328,939.84
FOUTSCO PAVING COMPANY, LLC   $2,764,218.05 2
-10.22% | -$314,716.00
0.52% | $14,223.84
JAGOE-PUBLIC COMPANY   $2,821,436.65 3
-8.36% | -$257,497.40
2.6% | $71,442.44
2.07% | $57,218.60
PEACHTREE CONSTRUCTION, LTD.   $2,984,980.67 4
-3.05% | -$93,953.38
8.54% | $234,986.46
5.80% | $163,544.02
O. TREVINO CONSTRUCTION, LLC   $3,052,897.20 5
-0.85% | -$26,036.85
11.01% | $302,902.99
2.28% | $67,916.53
ED BELL CONSTRUCTION COMPANY   $3,177,802.39 6
3.21% | $98,868.34
15.56% | $427,808.18
4.09% | $124,905.19

Bid Items

Items: 66, 0 filtered
WISE US 81  |  FORT WORTH  |  0013-06-047  |  04/08/2021  |  $3,078,934  |  STP 2021(494)HES  |  INSTL TRAF SIGNAL  |  171 WORKING DAYS
Item code Description Unit Quantity Engineer's Estimate AUSTIN BRIDGE & ROAD SERVICES, LP FOUTSCO PAVING COMPANY, LLC JAGOE-PUBLIC COMPANY PEACHTREE CONSTRUCTION, LTD. O. TREVINO CONSTRUCTION, LLC ED BELL CONSTRUCTION COMPANY
100 6002 PREPARING ROW STA 15.380 $3,900.000 $7,961.750 $250.000 $130.000 $1,500.000 $6,148.000 $4,200.000
104 6064 REMOVING CONC (MISC) CY 19.970 $35.000 $295.120 $100.000 $130.000 $550.000 $67.000 $367.500
110 6001 EXCAVATION (ROADWAY) CY 3,332.000 $6.500 $12.240 $15.000 $13.500 $19.500 $12.500 $13.500
132 6004 EMBANKMENT (FINAL)(DENS CONT)(TY B) CY 72.080 $9.000 $40.120 $50.000 $22.000 $110.000 $72.000 $52.500
161 6028 COMPOST MANUF TOPSOIL (2") SY 4,733.720 $5.000 $3.660 $3.500 $4.680 $2.400 $2.550 $2.500
164 6021 CELL FBR MLCH SEED(PERM)(RURAL)(SANDY) SY 4,733.720 $0.380 $1.350 $0.900 $0.470 $0.840 $1.000 $1.000
168 6001 VEGETATIVE WATERING MG 165.650 $20.000 $55.000 $40.000 $35.000 $75.000 $175.000 $165.650
260 6002 LIME (HYDRATED LIME (SLURRY)) TON 54.000 $175.000 $190.560 $165.000 $190.000 $210.000 $200.000 $200.000
260 6027 LIME TRT (EXST MATL)(8") SY 3,419.060 $3.450 $12.240 $5.000 $6.000 $7.500 $6.500 $3.150
305 6060 SALV,HAUL & STKPL RCL APH PV (2" TO 3") SY 120,521.620 $1.460 $0.790 $0.500 $1.000 $1.100 $1.040 $1.500
310 6009 PRIME COAT (MC-30) GAL 637.990 $5.000 $4.590 $4.000 $4.000 $6.000 $5.500 $6.300
360 6002 CONC PVMT (CONT REINF - CRCP) (8") SY 3,077.160 $50.000 $64.290 $60.000 $58.000 $120.000 $65.000 $69.000
432 6016 RIPRAP (STONE TY R)(DRY)(12 IN) CY 2.670 $200.000 $1,005.620 $300.000 $1,900.000 $430.000 $685.000 $735.000
432 6045 RIPRAP (MOW STRIP)(4 IN) CY 415.950 $450.000 $563.400 $500.000 $710.000 $580.000 $685.000 $525.000
467 6390 SET (TY II) (24 IN) (RCP) (4: 1) (C) EA 2.000 $1,000.000 $1,719.920 $1,000.000 $1,200.000 $1,625.000 $1,400.000 $2,100.000
500 6001 MOBILIZATION LS 1.000 $281,266.740 $274,174.430 $206,000.000 $74,000.000 $175,000.000 $300,000.000 $285,000.000
502 6001 BARRICADES, SIGNS AND TRAFFIC HANDLING MO 8.000 $9,000.000 $8,111.080 $2,000.000 $2,500.000 $7,500.000 $2,500.000 $13,650.000
506 6038 TEMP SEDMT CONT FENCE (INSTALL) LF 580.000 $2.500 $2.350 $3.000 $2.500 $5.000 $5.250 $5.180
506 6039 TEMP SEDMT CONT FENCE (REMOVE) LF 580.000 $0.600 $1.000 $1.000 $1.050 $1.000 $1.000 $0.870
533 6001 RUMBLE STRIPS (SHOULDER) LF 42,363.810 $0.160 $0.100 $0.100 $0.280 $0.250 $0.110 $0.110
540 6001 MTL W-BEAM GD FEN (TIM POST) LF 5,500.000 $21.000 $17.500 $17.500 $18.500 $19.000 $19.000 $18.550
540 6006 MTL BEAM GD FEN TRANS (THRIE-BEAM) EA 20.000 $1,850.000 $1,420.000 $1,420.000 $2,700.000 $1,520.000 $2,100.000 $2,970.970
540 6016 DOWNSTREAM ANCHOR TERMINAL SECTION EA 8.000 $1,350.000 $900.000 $900.000 $1,000.000 $950.000 $1,000.000 $954.000
540 6018 MTL BM GD FEN TRANS (NON - SYM) EA 12.000 $1,035.000 $500.000 $500.000 $525.000 $530.000 $550.000 $530.000
542 6001 REMOVE METAL BEAM GUARD FENCE LF 5,375.000 $3.250 $2.000 $2.000 $2.150 $2.200 $2.250 $2.120
542 6002 REMOVE TERMINAL ANCHOR SECTION EA 6.000 $235.000 $125.000 $125.000 $135.000 $135.000 $135.000 $132.500
542 6004 RM MTL BM GD FENCE TRANS (THRIE-BEAM) EA 12.000 $325.000 $175.000 $175.000 $190.000 $185.000 $190.000 $185.500
544 6001 GUARDRAIL END TREATMENT (INSTALL) EA 20.000 $2,600.000 $2,200.000 $2,200.000 $2,300.000 $2,350.000 $2,400.000 $2,332.000
544 6003 GUARDRAIL END TREATMENT (REMOVE) EA 14.000 $230.000 $230.000 $230.000 $245.000 $245.000 $250.000 $243.800
644 6001 IN SM RD SN SUP&AM TY10BWG(1)SA(P) EA 24.000 $520.000 $475.000 $475.000 $400.000 $405.000 $514.000 $503.500
644 6004 IN SM RD SN SUP&AM TY10BWG(1)SA(T) EA 11.000 $600.000 $530.000 $530.000 $610.000 $630.000 $575.000 $561.800
644 6027 IN SM RD SN SUP&AM TYS80(1)SA(P) EA 14.000 $605.000 $675.000 $675.000 $700.000 $710.000 $730.000 $715.500
644 6030 IN SM RD SN SUP&AM TYS80(1)SA(T) EA 1.000 $1,000.000 $705.000 $705.000 $780.000 $810.000 $763.000 $747.300
644 6076 REMOVE SM RD SN SUP&AM EA 2.000 $110.000 $150.000 $150.000 $130.000 $135.000 $162.000 $159.000
658 6013 INSTL DEL ASSM (D-SW)SZ (BRF)CTB EA 26.000 $22.500 $15.000 $60.000 $19.000 $19.000 $19.500 $19.080
658 6026 INSTL DEL ASSM (D-SY)SZ (BRF)CTB EA 20.000 $24.000 $15.000 $15.000 $19.000 $19.000 $19.500 $19.080
658 6061 INSTL DEL ASSM (D-SW)SZ 1(BRF)GF2 EA 38.000 $58.000 $30.000 $60.000 $26.000 $26.500 $27.000 $26.500
658 6064 INSTL DEL ASSM (D-SY)SZ 1(BRF)GF2 EA 9.000 $28.000 $30.000 $15.000 $26.000 $26.500 $27.000 $26.500
658 6080 INSTL DEL ASSM (D-SW)SZ 1(WFLX)GND EA 32.000 $45.000 $60.000 $30.000 $26.000 $43.000 $44.000 $42.400
658 6086 INSTL DEL ASSM (D-SY)SZ 1(YFLX)GND EA 51.000 $60.000 $60.000 $30.000 $42.000 $43.000 $44.000 $42.400
662 6001 WK ZN PAV MRK NON-REMOV (W)4"(BRK) LF 6,836.000 $0.500 $0.300 $0.300 $0.320 $1.100 $0.400 $1.060
662 6009 WK ZN PAV MRK NON-REMOV (W)8"(BRK) LF 413.000 $1.000 $0.600 $0.600 $0.630 $1.100 $0.800 $1.060
662 6012 WK ZN PAV MRK NON-REMOV (W)8"(SLD) LF 4,869.690 $0.750 $0.600 $0.600 $0.630 $1.100 $0.800 $1.060
662 6047 WK ZN PAV MRK REMOV (REFL) TY I-A LF 6,148.020 $3.000 $0.850 $0.850 $0.900 $1.000 $1.100 $0.950
662 6049 WK ZN PAV MRK REMOV (REFL) TY I-C LF 8,353.380 $1.460 $0.850 $0.850 $0.900 $1.000 $1.100 $0.950
662 6057 WK ZN PAV MRK REMOV (TRAF BTN) TY W LF 8,353.380 $1.770 $0.850 $0.850 $0.900 $1.000 $1.100 $0.950
662 6059 WK ZN PAV MRK REMOV (TRAF BTN) TY Y LF 6,148.020 $0.970 $0.850 $0.850 $0.900 $1.000 $1.100 $0.950
662 6109 WK ZN PAV MRK SHT TERM (TAB)TY W EA 2,675.000 $1.290 $1.510 $1.000 $1.250 $2.000 $1.100 $2.490
666 6027 REFL PAV MRK TY I (W)8"(BRK)(100MIL) LF 413.000 $1.250 $0.680 $0.680 $0.720 $1.100 $0.900 $1.060
666 6036 REFL PAV MRK TY I (W)8"(SLD)(100MIL) LF 4,869.690 $0.800 $0.680 $0.680 $0.720 $1.100 $0.900 $1.060
666 6300 RE PM W/RET REQ TY I (W)4"(BRK)(100MIL) LF 6,836.000 $0.450 $0.340 $0.340 $0.360 $0.580 $0.450 $0.580
666 6303 RE PM W/RET REQ TY I (W)4"(SLD)(100MIL) LF 27,244.000 $0.400 $0.340 $0.340 $0.360 $0.480 $0.450 $0.480
666 6315 RE PM W/RET REQ TY I (Y)4"(SLD)(100MIL) LF 27,244.000 $0.400 $0.340 $0.340 $0.360 $0.480 $0.450 $0.480
668 6076 PREFAB PAV MRK TY C (W) (24") (SLD) LF 179.000 $12.000 $16.000 $16.000 $17.000 $13.750 $21.000 $13.780
668 6077 PREFAB PAV MRK TY C (W) (ARROW) EA 22.000 $270.000 $225.000 $225.000 $235.000 $195.000 $293.000 $190.800
668 6085 PREFAB PAV MRK TY C (W) (WORD) EA 22.000 $360.000 $300.000 $300.000 $315.000 $235.000 $390.000 $233.200
672 6010 REFL PAV MRKR TY II-C-R EA 592.000 $3.600 $3.500 $3.500 $3.700 $3.800 $4.750 $3.710
677 6001 ELIM EXT PAV MRK & MRKS (4") LF 12,368.040 $0.320 $0.750 $0.750 $0.750 $0.260 $1.000 $0.260
677 6003 ELIM EXT PAV MRK & MRKS (8") LF 1,084.380 $0.850 $1.000 $1.000 $1.000 $0.540 $1.290 $0.530
3076 6002 D-GR HMA TY-B SAC-B PG64-22 TON 733.960 $92.000 $89.010 $100.000 $75.000 $72.500 $102.000 $75.000
3077 6027 SP MIXES SP-C SAC-A PG70-28 TON 14,480.980 $102.000 $81.100 $105.000 $100.000 $92.300 $92.000 $99.950
3077 6075 TACK COAT GAL 27,818.520 $2.000 $0.100 $0.010 $3.150 $0.750 $1.150 $0.750
6001 6001 PORTABLE CHANGEABLE MESSAGE SIGN DAY 60.000 $60.000 $73.180 $200.000 $75.000 $75.000 $175.000 $210.000
6185 6002 TMA (STATIONARY) DAY 116.000 $200.000 $191.320 $200.000 $175.000 $150.000 $250.000 $210.000
6185 6003 TMA (MOBILE OPERATION) HR 224.000 $50.000 $20.910 $1.000 $25.000 $35.000 $56.000 $52.500
6227 6002 SOLAR POWERED LED ROADSIDE SIGN EA 6.000 $3,000.000 $3,150.000 $3,000.000 $3,500.000 $3,900.000 $3,400.000 $3,339.000
Totals: $3,078,934.05 $2,749,994.32 $2,764,218.10 $2,821,436.71 $2,984,980.71 $3,052,897.26 $3,177,802.45