County: WILSON Highway: CS Date: 05/02/2024 (6 months ago) Engineer's Estimate: $743,922 Control Number: 0915-14-050
Project: STP 2023(123)TAPS District: SAN ANTONIO Time: 98 WORKING DAYS Type: CONSTRUCT PEDESTRIAN INFRASTRUCTURE
Bidder's List
Informational:
Email All | Notice | Questions
HCS
Pay Estimates: 1 | 2 | 3 | 4
Plans: Plans | Proposal

Bidders

Name Total Amount Place Over/Under Est Amt Left From Low Bid Delta Between Bidders
Engineer's Estimate $743,921.82
DIAMOND R CONTRACTING, LLC   $624,919.00 1
-16% | -$119,002.82
J3 COMPANY, LLC   $685,875.00 2
-7.8% | -$58,046.82
9.75% | $60,956.00
STX CIVIL   $764,405.60 3
2.75% | $20,483.78
22.32% | $139,486.60
11.45% | $78,530.60
DEAN WORD COMPANY, LTD.   $792,217.76 4
6.49% | $48,295.94
26.77% | $167,298.76
3.64% | $27,812.16
ENCINO LANDSCAPE, INC.   $869,750.00 5
16.91% | $125,828.18
39.18% | $244,831.00
9.79% | $77,532.24
DELGADO'S CONTRACTORS, LLC   $894,904.00 6
20.3% | $150,982.18
43.2% | $269,985.00
2.89% | $25,154.00
SALINAS CONSTRUCTION TECHNOLOGIES, LTD.   $912,871.13 7
22.71% | $168,949.31
46.08% | $287,952.13
2.01% | $17,967.13
TI-ZACK CONCRETE, LLC   $930,875.94 8
25.13% | $186,954.12
48.96% | $305,956.94
1.97% | $18,004.81
LUCANIA CONTRACTORS LLC   $1,284,057.30 9
72.61% | $540,135.48
105.48% | $659,138.30
37.94% | $353,181.36
Subcontractor Percentage Amount
ALL-PRO PAVING, LLC 33.05% $206,535.73
A K FUQUAY CONSTRUCTION 6.36% $39,744.85
HIGHWAY INFRASTRUCTURE SAFETY SERVICES, INC. 3.83% $23,934.40
Total: 43.24% $270,214.98

Bid Items

Items: 41, 0 filtered
WILSON CS  |  SAN ANTONIO  |  0915-14-050  |  05/02/2024  |  $743,922  |  STP 2023(123)TAPS  |  CONSTRUCT PEDESTRIAN INFRASTRUCT  |  98 WORKING DAYS
Item code Description Unit Quantity Engineer's Estimate DIAMOND R CONTRACTING, LLC J3 COMPANY, LLC STX CIVIL DEAN WORD COMPANY, LTD. ENCINO LANDSCAPE, INC. DELGADO'S CONTRACTORS, LLC SALINAS CONSTRUCTION TECHNOLOGIES, LTD. TI-ZACK CONCRETE, LLC LUCANIA CONTRACTORS LLC
104 6015 REMOVING CONC (SIDEWALKS) SY 133.000 $13.500 $50.000 $15.000 $14.500 $56.790 $30.000 $20.000 $25.720 $36.000 $50.000
104 6017 REMOVING CONC (DRIVEWAYS) SY 1,170.000 $20.000 $50.000 $15.000 $17.500 $24.430 $30.000 $30.000 $23.680 $24.550 $50.000
104 6028 REMOVING CONC (MISC) SY 12.000 $13.000 $500.000 $90.000 $15.000 $91.940 $30.000 $25.000 $39.540 $79.800 $100.000
104 6029 REMOVING CONC (CURB OR CURB & GUTTER) LF 126.000 $12.000 $100.000 $10.000 $12.000 $24.330 $20.000 $12.000 $7.040 $15.200 $30.000
104 6032 REMOVING CONC (WHEELCHAIR RAMP) SY 47.000 $25.000 $100.000 $30.000 $14.500 $44.380 $30.000 $30.000 $10.100 $20.370 $70.000
104 6044 REMOVING CONC (FLUME) SY 6.000 $26.000 $500.000 $55.000 $12.500 $115.240 $30.000 $100.000 $79.080 $159.600 $200.000
105 6045 REMOVING STAB BASE AND ASPH PAV (2"-8") SY 29.000 $10.000 $400.000 $20.000 $13.500 $47.810 $30.000 $5.000 $72.530 $33.020 $130.000
110 6002 EXCAVATION (CHANNEL) CY 11.300 $15.000 $1,000.000 $80.000 $17.000 $168.380 $50.000 $50.000 $73.720 $84.740 $90.000
110 6003 EXCAVATION (SPECIAL) CY 314.000 $16.000 $35.000 $40.000 $16.500 $72.720 $40.000 $35.000 $52.650 $91.490 $16.000
132 6003 EMBANKMENT (FINAL)(ORD COMP)(TY B) CY 562.000 $25.000 $25.000 $40.000 $25.500 $54.210 $50.000 $80.000 $45.560 $40.090 $80.000
160 6003 FURNISHING AND PLACING TOPSOIL (4") SY 2,842.000 $2.300 $10.000 $2.000 $6.500 $2.600 $5.000 $6.000 $6.600 $6.530 $8.500
164 6005 BROADCAST SEED (PERM) (URBAN) (SANDY) SY 2,842.000 $0.750 $1.000 $0.500 $0.500 $0.200 $0.500 $0.500 $0.340 $3.300 $0.400
168 6001 VEGETATIVE WATERING MG 56.000 $25.000 $50.000 $40.000 $69.500 $27.220 $100.000 $200.000 $75.980 $1.100 $120.000
169 6002 SOIL RETENTION BLANKETS (CL 1) (TY B) SY 634.000 $1.200 $1.000 $2.000 $3.000 $4.170 $5.000 $3.000 $1.970 $3.300 $2.000
169 6004 SOIL RETENTION BLANKETS (CL 1) (TY D) SY 2,122.000 $2.210 $1.000 $1.500 $3.000 $5.220 $6.000 $3.000 $1.100 $3.300 $1.250
351 6002 FLEXIBLE PAVEMENT STRUCTURE REPAIR(6") SY 17.200 $45.000 $300.000 $300.000 $55.000 $225.050 $100.000 $150.000 $944.210 $137.500 $2,000.000
432 6001 RIPRAP (CONC)(4 IN) CY 5.000 $320.000 $1,000.000 $1,000.000 $703.500 $1,775.010 $800.000 $700.000 $1,335.710 $824.100 $2,000.000
465 6233 INLET (COMP) (TY SIDEWALK BRIDGE) EA 4.000 $13,400.000 $5,000.000 $12,500.000 $13,533.000 $20,252.120 $17,000.000 $15,000.000 $15,157.090 $9,477.150 $17,000.000
465 6389 INLET (COMPL)(TY SIDEWALK BRIDGE)(MOD) EA 1.000 $12,000.000 $5,000.000 $12,500.000 $15,749.000 $20,317.030 $15,000.000 $12,500.000 $20,780.440 $9,477.150 $18,000.000
500 6001 MOBILIZATION LS 1.000 $80,000.000 $50,000.000 $61,500.000 $52,000.000 $75,000.000 $75,000.000 $70,000.000 $140,686.160 $88,105.800 $130,000.000
502 6001 BARRICADES, SIGNS AND TRAFFIC HANDLING MO 7.000 $6,000.000 $4,500.000 $5,500.000 $2,246.500 $1,963.710 $2,000.000 $3,000.000 $1,399.770 $1,650.000 $17,000.000
506 6002 ROCK FILTER DAMS (INSTALL) (TY 2) LF 100.000 $35.000 $50.000 $30.000 $57.000 $61.260 $10.000 $45.000 $32.380 $1.100 $35.000
506 6011 ROCK FILTER DAMS (REMOVE) LF 100.000 $13.000 $6.000 $12.000 $12.000 $15.660 $5.000 $10.000 $12.590 $1.100 $15.000
506 6035 SANDBAGS FOR EROSION CONTROL EA 261.000 $10.500 $40.000 $5.000 $6.500 $2.590 $5.000 $5.000 $5.320 $1.100 $6.000
506 6038 TEMP SEDMT CONT FENCE (INSTALL) LF 1,337.000 $3.700 $9.000 $3.000 $5.500 $2.270 $5.000 $5.000 $3.030 $1.100 $3.500
506 6039 TEMP SEDMT CONT FENCE (REMOVE) LF 1,337.000 $1.000 $1.000 $2.000 $1.500 $0.970 $1.000 $1.000 $1.600 $1.100 $1.750
506 6041 BIODEG EROSN CONT LOGS (INSTL) (12") LF 875.000 $5.000 $5.000 $10.000 $10.500 $5.220 $8.000 $9.000 $8.580 $1.100 $10.000
506 6043 BIODEG EROSN CONT LOGS (REMOVE) LF 875.000 $1.400 $1.000 $3.000 $1.500 $1.310 $1.000 $2.000 $3.230 $1.100 $4.000
529 6001 CONC CURB (TY I) LF 2,103.000 $15.000 $25.000 $22.000 $35.000 $25.980 $20.000 $50.000 $39.490 $58.240 $40.000
530 6004 DRIVEWAYS (CONC) SY 841.000 $115.000 $25.000 $85.000 $113.500 $96.950 $130.000 $120.000 $118.640 $123.640 $140.000
530 6021 DRIVEWAYS (ACP) (TYPE 2) SY 478.000 $80.000 $25.000 $85.000 $75.000 $85.780 $50.000 $85.000 $95.980 $82.140 $100.000
531 6001 CONC SIDEWALKS (4") SY 3,097.000 $82.000 $50.000 $65.000 $79.000 $64.200 $100.000 $80.000 $74.410 $111.280 $115.000
531 6004 CURB RAMPS (TY 1) EA 6.000 $2,200.000 $2,500.000 $1,800.000 $2,500.000 $2,274.170 $2,000.000 $3,000.000 $1,680.670 $2,497.270 $3,800.000
560 6025 RELOCATE EXISTING MAILBOX EA 1.000 $300.000 $1,000.000 $395.000 $300.000 $514.850 $500.000 $500.000 $547.530 $165.000 $300.000
644 6068 RELOCATE SM RD SN SUP&AM TY 10BWG EA 5.000 $585.000 $1,000.000 $1,050.000 $300.000 $1,368.570 $1,000.000 $1,100.000 $1,177.610 $275.000 $300.000
666 6048 REFL PAV MRK TY I (W)24"(SLD)(100MIL) LF 579.000 $9.000 $20.000 $12.000 $25.500 $15.660 $20.000 $14.000 $13.400 $13.200 $14.500
666 6230 PAVEMENT SEALER 24" LF 579.000 $3.100 $20.000 $4.000 $8.500 $5.220 $10.000 $5.000 $4.050 $4.400 $4.250
677 6007 ELIM EXT PAV MRK & MRKS (24") LF 238.000 $4.000 $20.000 $5.000 $13.000 $6.510 $10.000 $6.000 $5.970 $5.500 $7.250
752 6007 TREE REMOVAL (18" - 24" DIA) EA 3.000 $940.000 $1,000.000 $2,500.000 $1,588.000 $595.670 $2,000.000 $500.000 $3,672.330 $1,650.000 $5,000.000
6001 6002 PORTABLE CHANGEABLE MESSAGE SIGN EA 1.000 $8,000.000 $5,000.000 $6,000.000 $5,000.000 $6,656.620 $1,000.000 $11,000.000 $15,555.510 $1.100 $20,000.000
6185 6002 TMA (STATIONARY) DAY 71.000 $220.000 $1.000 $220.000 $253.000 $408.820 $300.000 $300.000 $222.690 $1.100 $500.000
Totals: $743,921.82 $624,919.00 $685,875.00 $764,405.60 $792,217.76 $869,750.00 $894,904.00 $912,871.14 $930,875.94 $1,284,057.30