WILSON US 87 (0143-03-044)

Items: 99

County: WILSON
Length: N/A
Highway: US 87
District: SAN ANTONIO
Control Number: 0143-03-044
DBE Goal: N/A
Project: NH 2018(530)
Guaranty: N/A
Time: 103 WORKING DAYS
Engineer's Estimate: $4,005,996.90
Date: 02/02/2018 (8 years ago)
Contract Number: N/A
Type: REHABITITATE EXISTING ROADWAY
Mail/Deliver Bids To: N/A
SEE PLANS OR PROPOSAL BOOK
Actions:
Notice HCS Excel Tabs Print Print Notice
Pay Estimates:
Bidders (9)
E
Engineer's Estimate
$4,005,996.90
$2,913,595.42
Over/Under Est: -27.27% -$1,092,401.48
Over/Under Est: -18.35% -$735,254.76
Amt Left: 12.26% $357,146.72
Over/Under Est: -15.48% -$620,028.82
Amt Left: 16.21% $472,372.66
Delta: -3.52% -$115,225.94
$3,675,843.18
Over/Under Est: -8.24% -$330,153.72
Amt Left: 26.16% $762,247.76
Delta: -8.56% -$289,875.10
Over/Under Est: -6.4% -$256,227.20
Amt Left: 28.7% $836,174.28
Delta: -2.01% -$73,926.52
$3,911,115.65
Over/Under Est: -2.37% -$94,881.25
Amt Left: 34.24% $997,520.23
Delta: -4.30% -$161,345.95
Over/Under Est: 1.33% $53,181.59
Amt Left: 39.32% $1,145,583.07
Delta: -3.79% -$148,062.84
Over/Under Est: 9.97% $399,576.79
Amt Left: 51.21% $1,491,978.27
Delta: -8.53% -$346,395.20
Over/Under Est: 10.68% $427,918.96
Amt Left: 52.18% $1,520,320.44
Delta: -0.64% -$28,342.17

Bid Items & Bid Tabulations

99 Total 0 of 99
WILSON  |  US 87  |  SAN ANTONIO  |  0143-03-044  |  02/02/2018  |  $4,005,996.90  |  NH 2018(530)  |  REHABITITATE EXIST ROADWAY  |  103 WORKING DAYS
Item Code
Description
Unit
Quantity
Engineer's Estimate
HUNTER INDUSTRIES, LTD.
ANGEL BROTHERS HOLDINGS CORP.
DEAN WORD COMPANY, LTD.
AUSTIN MATERIALS, LLC
CURRAN CONTRACTING COMPANY
RAY FARIS, INC.
REIM CONSTRUCTION, INC.
SALINAS CONSTRUCTION TECHNOLOGIES, LTD.
ANDERSON COLUMBIA CO., INC.
PREPARING ROW
STA 134.000 $800.000 $241.950 $425.000 $121.000 $240.000 $232.500 $739.380 $335.000 $162.300 $400.000
REMOVING STAB BASE AND ASPH PAV (6")
SY 72,009.000 $3.500 $1.280 $3.000 $2.578 $5.030 $2.750 $2.100 $2.750 $2.010 $6.600
EXCAVATION (ROADWAY)
CY 1,306.000 $15.000 $14.550 $20.000 $11.836 $16.000 $18.750 $14.980 $12.250 $16.120 $17.000
EXCAVATION (CHANNEL)
CY 10.000 $50.000 $14.550 $85.000 $51.238 $50.000 $101.450 $42.800 $23.750 $35.800 $50.000
EMBANKMENT (FINAL)(ORD COMP)(TY B)
CY 246.000 $15.000 $14.550 $25.000 $20.394 $16.000 $101.600 $32.100 $6.500 $20.150 $7.000
FURNISHING AND PLACING TOPSOIL (4")
SY 14,644.000 $1.750 $1.100 $2.000 $1.276 $3.550 $3.750 $0.860 $2.750 $2.060 $2.600
DRILL SEEDING (PERM)(WARM OR COOL)
SY 14,644.000 $0.500 $0.230 $0.210 $0.229 $0.200 $0.200 $0.200 $0.300 $0.230 $0.140
VEGETATIVE WATERING
MG 234.300 $20.000 $16.650 $5.000 $23.925 $25.000 $38.100 $26.840 $24.750 $44.080 $32.000
SOIL RETENTION BLANKETS (CL 1) (TY A)
SY 881.000 $4.000 $1.320 $1.450 $1.300 $1.350 $1.450 $1.350 $1.550 $1.750 $1.400
PRIME COAT (MULTI OPTION)
GAL 14,669.000 $3.500 $2.550 $3.650 $2.926 $3.750 $3.650 $4.070 $3.100 $3.250 $4.500
ASPH(AC-15P,AC-20-5TR,AC-20XP,AC10-2TR)
GAL 22,253.000 $3.000 $2.560 $2.850 $3.025 $2.850 $4.550 $3.250 $3.750 $3.780 $3.700
AGGR (TY-PD GR-4 OR GR-4S SAC-B)
CY 741.000 $80.000 $49.530 $90.000 $76.142 $67.000 $127.700 $85.960 $81.000 $98.380 $144.000
D-GR HMA TY-B PG70-22
TON 23,503.000 $65.000 $49.200 $51.500 $52.298 $58.500 $60.550 $66.980 $76.000 $78.530 $69.000
D-GR HMA TY-B PG70-22 (LEVEL - UP)
TON 985.000 $80.000 $54.630 $63.000 $63.383 $61.000 $72.050 $85.960 $77.500 $80.580 $104.000
SUPERPAVE MIXTURES SP-D SAC-A PG76-22
TON 8,085.000 $75.000 $60.750 $67.500 $78.571 $73.000 $70.300 $73.770 $88.500 $89.910 $86.000
FLEX PAVEMENT STRUCTURE REPAIR (5"-10")
SY 400.000 $80.000 $38.430 $94.000 $37.315 $73.000 $43.350 $56.600 $52.500 $66.830 $140.000
PLANE ASPH CONC PAV(0" TO 2")
SY 1,608.000 $6.000 $1.280 $3.260 $3.059 $4.900 $2.250 $4.980 $2.200 $7.150 $8.000
PLANE ASPH CONC PAV(0" TO 4")
SY 503.000 $8.000 $1.280 $10.000 $8.567 $14.000 $6.400 $11.700 $2.800 $22.850 $8.000
CEM STABIL BKFL
CY 54.000 $100.000 $120.750 $105.000 $107.800 $115.000 $142.900 $115.000 $53.500 $140.370 $100.000
TRENCH EXCAVATION PROTECTION
LF 134.000 $20.000 $12.070 $5.500 $7.700 $11.500 $1.250 $11.500 $2.000 $25.150 $5.000
TEMPORARY SPL SHORING
SF 464.000 $50.000 $18.900 $5.500 $5.500 $18.000 $15.700 $18.000 $16.000 $65.930 $5.000
DRILL SHAFT (TRF SIG POLE) (36 IN)
LF 26.400 $336.000 $186.520 $340.000 $296.400 $26.400 $330.000 $175.000 $321.000 $272.950 $175.000
RIPRAP (CONC)(4 IN)
CY 20.000 $450.000 $461.980 $450.000 $451.000 $388.470 $446.000 $440.000 $414.000 $684.990 $425.000
RIPRAP (STONE PROTECTION)(15 IN)
CY 64.000 $180.000 $230.040 $240.000 $135.300 $202.020 $141.600 $219.090 $149.000 $281.800 $225.000
RIPRAP (MOW STRIP)(4 IN)
CY 38.000 $400.000 $467.230 $425.000 $484.000 $160.860 $759.700 $445.000 $414.000 $540.700 $400.000
RAIL (TY T631)
LF 42.000 $100.000 $73.500 $75.000 $67.600 $70.000 $74.250 $140.000 $95.000 $353.300 $65.000
CONC BOX CULV (3 FT X 3 FT)
LF 4.000 $250.000 $677.540 $800.000 $1,485.000 $645.000 $1,377.350 $645.000 $1,370.000 $1,233.160 $750.000
CONC BOX CULV (4 FT X 4 FT)
LF 2.000 $500.000 $1,057.560 $1,100.000 $1,485.000 $1,007.240 $2,040.950 $1,007.240 $1,400.000 $2,216.310 $1,000.000
RC PIPE (CL III)(24 IN)
LF 134.000 $70.000 $93.370 $66.000 $101.200 $88.930 $75.000 $88.930 $65.000 $74.130 $62.000
SET (TY I)(S=3 FT)(HW= 4 FT)(4:1)(C)
EA 2.000 $4,800.000 $3,674.860 $6,000.000 $5,885.000 $3,500.000 $6,254.550 $3,500.000 $7,990.000 $6,010.760 $6,500.000
SET (TY I)(S= 4 FT)(HW= 5 FT)(4:1) (C)
EA 1.000 $6,500.000 $8,924.660 $10,000.000 $12,540.000 $8,500.000 $15,673.550 $8,500.000 $11,200.000 $8,896.520 $9,500.000
SET (TY II) (24 IN) (RCP) (4: 1) (P)
EA 5.000 $1,500.000 $1,072.160 $1,350.000 $1,776.500 $1,021.140 $1,292.250 $1,021.140 $1,400.000 $1,248.260 $1,250.000
SET (TY II) (24 IN) (RCP) (6: 1) (P)
EA 5.000 $1,600.000 $1,096.540 $1,650.000 $2,134.000 $1,044.360 $1,693.800 $1,044.360 $1,540.000 $1,533.260 $1,550.000
CLEAN EXIST CULVERTS
EA 4.000 $1,500.000 $1,889.930 $1,600.000 $1,045.000 $1,800.000 $848.350 $1,800.000 $2,830.000 $2,857.180 $1,500.000
REMOV STR (SET)
EA 10.000 $400.000 $180.020 $275.000 $605.000 $171.450 $1,971.100 $171.450 $391.000 $2,052.970 $250.000
REMOV STR (PIPE)
LF 175.000 $25.000 $16.160 $12.500 $35.200 $15.390 $20.200 $15.390 $11.500 $17.940 $12.000
MOBILIZATION
LS 1.000 $364,175.000 $237,346.590 $230,000.000 $310,351.375 $200,000.000 $285,000.000 $430,000.000 $175,000.000 $236,320.510 $284,000.000
BARRICADES, SIGNS AND TRAFFIC HANDLING
MO 6.000 $12,000.000 $4,352.370 $4,500.000 $5,432.500 $22,500.000 $8,991.600 $5,371.000 $7,000.000 $13,059.010 $4,100.000
ROCK FILTER DAMS (INSTALL) (TY 2)
LF 399.000 $25.000 $23.220 $28.000 $22.880 $22.550 $29.200 $25.500 $25.750 $30.530 $24.000
ROCK FILTER DAMS (REMOVE)
LF 399.000 $10.000 $7.390 $15.000 $7.280 $6.600 $7.000 $6.000 $7.150 $7.490 $8.000
TEMP SEDMT CONT FENCE (INSTALL)
LF 23,946.000 $1.600 $1.850 $2.250 $1.820 $1.900 $2.000 $2.250 $2.000 $2.170 $1.800
TEMP SEDMT CONT FENCE (REMOVE)
LF 23,946.000 $0.300 $0.630 $0.750 $0.624 $0.250 $0.250 $0.250 $1.000 $0.310 $0.300
ONE-WAY TRAF CONT (FLAGGER CONT)
HR 800.000 $50.000 $62.700 $30.000 $58.300 $112.500 $103.200 $96.300 $58.500 $45.890 $102.000
ONE-WAY TRAF CONT (PILOT CAR)
HR 800.000 $65.000 $87.780 $45.000 $89.650 $6.000 $139.550 $96.300 $76.500 $82.280 $140.000
PORT CTB (FUR & INST)(SGL SLOPE)(TY 1)
LF 900.000 $32.000 $15.820 $20.000 $10.175 $15.100 $31.550 $15.070 $22.500 $86.260 $39.000
PORT CTB (MOVE)(SGL SLP)(TY 1)
LF 600.000 $10.000 $5.710 $5.000 $6.600 $5.440 $14.600 $5.440 $9.800 $16.910 $10.500
PORT CTB (REMOVE)(SGL SLP)(TY 1)
LF 900.000 $7.000 $11.980 $10.000 $9.900 $11.410 $18.100 $11.410 $22.500 $81.260 $12.000
DRIVEWAYS (CONC)
SY 225.000 $80.000 $122.380 $70.000 $71.610 $116.660 $69.950 $123.010 $50.500 $102.120 $77.000
DRIVEWAYS (ACP)
SY 973.000 $40.000 $32.280 $24.500 $31.713 $36.400 $38.150 $36.400 $42.500 $50.060 $44.000
MTL W-BEAM GD FEN (STEEL POST)
LF 862.500 $45.000 $19.700 $21.000 $24.461 $19.700 $20.900 $19.700 $27.000 $26.430 $24.000
SHORT RADIUS
LF 20.000 $35.000 $30.250 $32.000 $39.780 $30.250 $32.100 $30.250 $43.500 $49.430 $40.000
DRIVEWAY TERMINAL ANCHOR SECTION
EA 1.000 $1,000.000 $575.000 $600.000 $806.000 $575.000 $609.750 $575.000 $904.000 $1,042.570 $790.000
DOWNSTREAM ANCHOR TERMINAL SECTION
EA 4.000 $1,000.000 $1,054.000 $1,100.000 $942.240 $1,054.000 $1,117.700 $1,054.000 $1,030.000 $1,091.970 $920.000
REMOVE METAL BEAM GUARD FENCE
LF 1,131.500 $2.000 $1.000 $1.050 $1.310 $1.000 $1.050 $1.000 $2.250 $1.680 $1.300
REMOVE TERMINAL ANCHOR SECTION
EA 4.000 $150.000 $125.000 $135.000 $98.800 $125.000 $132.550 $125.000 $296.000 $143.770 $97.000
GUARDRAIL END TREATMENT (INSTALL)
EA 4.000 $2,800.000 $2,346.000 $2,500.000 $2,185.040 $2,346.000 $2,487.750 $2,346.000 $2,430.000 $2,371.270 $2,140.000
GUARDRAIL END TREATMENT (REMOVE)
EA 4.000 $300.000 $125.000 $135.000 $79.040 $125.000 $132.550 $125.000 $246.000 $143.770 $78.000
CRASH CUSH ATTEN (INSTL)
EA 6.000 $10,000.000 $6,000.000 $13,000.000 $14,300.000 $12,000.000 $1,532.750 $6,000.000 $14,800.000 $18,566.780 $16,300.000
CRASH CUSH ATTEN (MOVE & RESET)
EA 4.000 $1,500.000 $391.500 $1,400.000 $1,540.000 $1,300.000 $789.200 $391.500 $1,010.000 $2,277.770 $1,960.000
CRASH CUSH ATTEN (REMOVE)
EA 6.000 $650.000 $180.060 $800.000 $330.000 $750.000 $389.900 $180.060 $523.000 $455.180 $330.000
TRAY CABLE (4 CONDR) (12 AWG)
LF 240.000 $3.500 $4.600 $4.300 $2.080 $4.050 $2.300 $4.320 $2.250 $3.130 $4.400
ZINC-COAT STL WIRE STRAND (3/16")
LF 430.000 $3.500 $4.520 $6.350 $4.160 $6.000 $4.650 $4.240 $4.500 $7.970 $4.400
ZINC-COAT STL WIRE STRAND (5/16")
LF 430.000 $4.100 $4.520 $6.350 $4.160 $6.000 $4.650 $4.240 $4.500 $7.970 $4.400
IN SM RD SN SUP&AM TY10BWG(1)SA(P)
EA 28.000 $500.000 $400.000 $475.000 $416.000 $437.340 $463.750 $437.340 $435.000 $499.260 $400.000
IN SM RD SN SUP&AM TY10BWG(1)SA(U)
EA 4.000 $650.000 $640.000 $825.000 $665.600 $714.100 $757.250 $714.100 $435.000 $844.010 $770.000
IN SM RD SN SUP&AM TYS80(1)SA(P)
EA 2.000 $700.000 $570.000 $660.000 $592.800 $583.420 $618.650 $583.420 $392.000 $688.910 $630.000
IN SM RD SN SUP&AM TYS80(1)SA(T)
EA 3.000 $750.000 $620.000 $660.000 $644.800 $592.980 $628.800 $592.980 $585.000 $784.610 $720.000
REMOVE SM RD SN SUP&AM
EA 35.000 $85.000 $45.000 $45.000 $46.800 $65.000 $68.950 $65.000 $77.500 $109.410 $92.000
INSTL DEL ASSM (D-SW)SZ 1(FLX)GND
EA 5.000 $75.000 $50.000 $40.000 $52.000 $37.290 $39.550 $37.290 $50.000 $78.410 $65.000
INSTL DEL ASSM (D-SW)SZ 1(FLX)GND(BI)
EA 11.000 $70.000 $50.000 $40.000 $52.000 $37.530 $39.800 $37.530 $50.000 $77.580 $65.000
INSTL OM ASSM (OM-2Z)(FLX)GND
EA 19.000 $45.000 $52.000 $45.000 $54.080 $40.390 $42.850 $40.390 $50.000 $78.890 $65.000
REMOVE DELIN & OBJECT MARKER ASSMS
EA 38.000 $20.000 $5.000 $10.000 $5.200 $25.000 $26.500 $25.000 $26.250 $12.690 $5.000
WK ZN PAV MRK REMOV (REFL) TY I-C
EA 409.000 $5.000 $2.750 $3.000 $2.860 $2.750 $2.900 $2.750 $4.000 $3.250 $3.000
WK ZN PAV MRK REMOV (REFL) TY II-A-A
EA 753.000 $4.000 $2.750 $3.000 $2.860 $2.750 $2.900 $2.750 $4.000 $3.150 $3.000
WK ZN PAV MRK REMOV (TRAF BTN) TY W
EA 2,401.000 $4.000 $2.350 $2.500 $2.444 $2.350 $2.500 $2.350 $4.000 $2.620 $2.400
WK ZN PAV MRK REMOV (TRAF BTN) TY Y
EA 4,540.000 $3.000 $2.350 $2.500 $2.444 $2.350 $2.500 $2.350 $4.000 $2.610 $2.400
WK ZN PAV MRK SHT TERM (TAB)TY W
EA 1,779.000 $2.000 $1.760 $0.900 $1.375 $1.000 $2.450 $1.240 $1.500 $1.010 $1.330
WK ZN PAV MRK SHT TERM (TAB)TY Y
EA 1,351.000 $2.500 $1.760 $0.900 $1.375 $1.000 $1.250 $1.240 $1.500 $1.130 $1.330
REFL PAV MRK TY I (W)24"(SLD)(100MIL)
LF 154.000 $10.000 $6.440 $7.000 $6.698 $6.440 $6.850 $6.440 $4.500 $7.680 $7.000
REFL PAV MRK TY I(W)(LNDP ARW)(100MIL)
EA 2.000 $300.000 $644.000 $680.000 $669.760 $644.000 $682.900 $644.000 $170.000 $753.930 $660.000
PAVEMENT SEALER 4"
LF 42,670.000 $0.180 $0.150 $0.160 $0.156 $0.150 $0.150 $0.150 $0.300 $0.170 $0.150
PAVEMENT SEALER 24"
LF 154.000 $3.000 $7.000 $7.400 $7.280 $7.000 $7.400 $7.000 $1.700 $8.290 $7.000
PAVEMENT SEALER (LNDP ARROW)
EA 2.000 $125.000 $366.000 $400.000 $380.640 $366.000 $388.100 $366.000 $125.000 $411.710 $375.000
RE PM W/RET REQ TY I (W)4"(BRK)(100MIL)
LF 1,145.000 $1.500 $0.500 $0.550 $0.520 $0.500 $0.550 $0.500 $0.500 $0.630 $0.510
RE PM W/RET REQ TY I (W)4"(SLD)(100MIL)
LF 2,841.000 $2.500 $0.450 $0.500 $0.468 $0.450 $0.500 $0.450 $0.500 $0.530 $0.460
RE PM W/RET REQ TY I (Y)4"(SLD)(100MIL)
LF 2,736.000 $2.500 $0.450 $0.500 $0.468 $0.450 $0.500 $0.450 $0.500 $0.530 $0.460
REF PROF PAV MRK TY I(W)4"(SLD)(100MIL)
LF 23,566.000 $1.000 $0.700 $0.750 $0.728 $0.700 $0.750 $0.700 $0.750 $0.780 $0.710
REF PROF PAV MRK TY I(Y)4"(BRK)(100MIL)
LF 2,286.000 $1.000 $1.000 $1.100 $1.040 $1.000 $1.050 $1.000 $1.250 $1.140 $1.000
REF PROF PAV MRK TY I(Y)4"(SLD)(100MIL)
LF 10,096.000 $1.500 $0.800 $0.850 $0.832 $0.800 $0.850 $0.800 $0.750 $0.890 $0.820
REFL PAV MRKR TY I-C
EA 62.000 $5.000 $4.000 $4.250 $4.160 $4.000 $4.250 $4.000 $5.250 $5.870 $4.000
REFL PAV MRKR TY II-A-A
EA 301.000 $3.500 $4.000 $4.250 $4.160 $4.000 $4.250 $4.000 $5.750 $4.700 $4.000
ELIM EXT PAV MRK & MRKS (4")
LF 10,312.000 $0.500 $0.670 $0.700 $0.697 $0.670 $0.700 $0.670 $1.000 $0.750 $0.700
INSTALL HWY TRF SIG (FLASH BEACON)
EA 1.000 $4,000.000 $3,306.180 $2,650.000 $2,600.000 $2,500.000 $2,894.950 $3,102.000 $2,820.000 $2,841.070 $3,200.000
REMOVING TRAFFIC SIGNALS
EA 1.000 $6,000.000 $860.120 $1,150.000 $884.000 $1,050.000 $984.300 $807.000 $959.000 $1,246.070 $820.000
VEH SIG SEC (12")LED(YEL)
EA 8.000 $250.000 $448.710 $380.000 $364.000 $360.000 $405.300 $421.000 $395.000 $407.380 $430.000
VEH SIG SEC (12")LED(RED)
EA 8.000 $250.000 $448.710 $380.000 $364.000 $360.000 $405.300 $421.000 $395.000 $407.380 $430.000
TRF SIG CBL (TY A)(12 AWG)(4 CONDR)
LF 564.000 $2.000 $5.680 $4.250 $2.080 $4.000 $2.300 $5.330 $2.250 $4.560 $5.400
INS TRF SIG PL AM (S)STR(TY B)
EA 2.000 $3,500.000 $3,959.530 $4,000.000 $5,200.000 $3,800.000 $5,789.850 $3,715.000 $5,640.000 $4,189.110 $3,800.000
PORTABLE CHANGEABLE MESSAGE SIGN
EA 4.000 $8,000.000 $7,755.400 $7,500.000 $6,050.000 $9,900.000 $3,549.100 $7,500.000 $7,000.000 $7,203.200 $6,100.000
Totals: $4,005,996.900 $2,913,595.433 $3,270,742.145 $3,385,968.209 $3,675,843.180 $3,749,769.705 $3,911,115.652 $4,059,178.500 $4,405,573.699 $4,433,915.860