WILLIAMSON FM 734 (3417-02-039)
Items: 23
County: WILLIAMSON
Length: 0.0000 MILES (0.6903 MILES)
Highway: FM 734
District: AUSTIN
Control Number: 3417-02-039
DBE Goal: 0.0%
Project: STP 2026(793)HES
Guaranty: $9,000.00
Time: 61 WORKING DAYS
Engineer's Estimate: $432,477.50
Date: 07/02/2026 1:00 PM CDT (16 days ago)
Contract Number: 7263229
Type: HAZARD ELIMINATION & SAFETY
Project ID: A00206732
Contract Type: FEDERAL
Project Description: SAFETY LIGHTING
Mail/Deliver Bids To:
TEXAS DEPARTMENT OF TRANSPORTATION
ATTN: CONSTRUCTION DIVISION - RM M1C3.02
6230 E STASSNEY LN, AUSTIN, TX 78744
MAHENDRAN THIVAKARAN
YETNAYET BOGALE
KYLE RUSSELL
JEREMY MIKES
CORY JUCIUS
SRIDHAR RAMAIYENGAR
WILLIAMSON FM 734 (3417-02-039)
Project Name: N/A
Project: STP 2026(793)HES
Engineer's Estimate: $432,477.50
Length: 0.0000 MILES (0.6903 MILES)
Project Class: SAFETY IMPROVEMENT PROJECTS
Limits From: SH 45
Limits To: 0.66 MI S OF SH45
Project Description: SAFETY LIGHTING
Bidders (7)
| Bidder | Total Amount | Over/Under Est | Amt Left From Low Bid | Delta Between Bidders |
|---|---|---|---|---|
|
E
Engineer's Estimate
|
$432,477.50 | |||
| $342,220.25 |
-20.87%
-$90,257.25
|
|||
| $373,340.63 |
-13.67%
-$59,136.87
|
9.09%
$31,120.38
|
||
| $386,823.00 |
-10.56%
-$45,654.50
|
13.03%
$44,602.75
|
-3.61%
-$13,482.37
|
|
| $398,341.50 |
-7.89%
-$34,136.00
|
16.4%
$56,121.25
|
-2.98%
-$11,518.50
|
|
| $415,803.17 |
-3.86%
-$16,674.33
|
21.5%
$73,582.92
|
-4.38%
-$17,461.67
|
|
| $488,488.00 |
12.95%
$56,010.50
|
42.74%
$146,267.75
|
-17.48%
-$72,684.83
|
|
| $547,400.00 |
26.57%
$114,922.50
|
59.96%
$205,179.75
|
-12.06%
-$58,912.00
|
E
Engineer's Estimate
$432,477.50
$342,220.25
Over/Under Est:
-20.87%
-$90,257.25
$373,340.63
Over/Under Est:
-13.67%
-$59,136.87
Amt Left:
9.09%
$31,120.38
$386,823.00
Over/Under Est:
-10.56%
-$45,654.50
Amt Left:
13.03%
$44,602.75
Delta:
-3.61%
-$13,482.37
$398,341.50
Over/Under Est:
-7.89%
-$34,136.00
Amt Left:
16.4%
$56,121.25
Delta:
-2.98%
-$11,518.50
$415,803.17
Over/Under Est:
-3.86%
-$16,674.33
Amt Left:
21.5%
$73,582.92
Delta:
-4.38%
-$17,461.67
$488,488.00
Over/Under Est:
12.95%
$56,010.50
Amt Left:
42.74%
$146,267.75
Delta:
-17.48%
-$72,684.83
$547,400.00
Over/Under Est:
26.57%
$114,922.50
Amt Left:
59.96%
$205,179.75
Delta:
-12.06%
-$58,912.00
Bid Items & Bid Tabulations
23
Total
0 of 23
INCLUDES FORCE ACCOUNT WORK AMOUNTS AS FOLLOWS:
| Description | Amount |
|---|---|
| PUBLIC UTILITY FORCE ACCT WORK (PART) | $125,000.00 |
| EROSION CONTROL MAINTENANCE: CONTRACTOR FORCE ACCOUNT WORK (PART) | $5,000.00 |
| LAW ENFORCEMENT: CONTRACTOR FORCE ACCOUNT WORK (PART) | $10,000.00 |
| SAFETY CONTINGENCY: CONTRACTOR FORCE ACCOUNT WORK (PART) | $5,000.00 |
| Total: | $145,000.00 |