County: WILLIAMSON Highway: FM 1466 Date: 09/07/2023 (1 year ago) Engineer's Estimate: $3,834,661 Control Number: 1200-04-016
Project: BR 2024(026) District: AUSTIN Time: 154 WORKING DAYS Type: BRIDGE REPLACEMENT
HCS
Pay Estimates: 1 | 2 | 3 | 4
Plans: Plans | Proposal

Bidders

Name Total Amount Place Over/Under Est Amt Left From Low Bid Delta Between Bidders
Engineer's Estimate $3,834,660.84
JOE BLAND CONSTRUCTION, L.P.   $5,546,235.00 1
44.63% | $1,711,574.16
AUSTIN ENGINEERING CO., INC.   $6,263,294.18 2
63.33% | $2,428,633.34
12.93% | $717,059.18
CAPITAL EXCAVATION COMPANY   $6,563,207.20 3
71.15% | $2,728,546.36
18.34% | $1,016,972.20
4.79% | $299,913.02
AARON CONCRETE CONTRACTORS, LLC   $7,117,045.20 4
85.6% | $3,282,384.36
28.32% | $1,570,810.20
8.44% | $553,838.00
Subcontractor Percentage Amount
LONE STAR PAVING COMPANY 26.49% $1,469,197.65
TRP CONSTRUCTION GROUP, LLC 6.16% $341,648.08
TEXAS HIGHWAY WALLS 4.95% $274,538.63
D. I. J. CONSTRUCTION, INC. 3.17% $175,815.65
WYLIE DRILLING & DRAINAGE, INC. 1.59% $88,185.14
BUYERS BARRICADES AUSTIN, LLC 1.29% $71,546.43
Total: 43.65% $2,420,931.58

Bid Items

Items: 115, 0 filtered
WILLIAMSON FM 1466  |  AUSTIN  |  1200-04-016  |  09/07/2023  |  $3,834,661  |  BR 2024(026)  |  BRIDGE REPL  |  154 WORKING DAYS
Item code Description Unit Quantity Engineer's Estimate JOE BLAND CONSTRUCTION, L.P. AUSTIN ENGINEERING CO., INC. CAPITAL EXCAVATION COMPANY AARON CONCRETE CONTRACTORS, LLC
100 6002 PREPARING ROW STA 38.000 $1,000.000 $1,500.000 $2,000.000 $1,550.000 $3,000.000
104 6010 REMOVING CONC (RIPRAP) CY 42.000 $50.000 $60.000 $50.000 $150.000 $260.000
110 6001 EXCAVATION (ROADWAY) CY 1,699.000 $15.000 $42.000 $26.000 $42.300 $35.000
132 6005 EMBANKMENT (FINAL)(ORD COMP)(TY C) CY 3,835.000 $15.000 $50.000 $23.000 $120.000 $75.000
134 6001 BACKFILL (TY A) STA 320.000 $200.000 $200.000 $85.000 $132.000 $180.000
160 6003 FURNISHING AND PLACING TOPSOIL (4") SY 9,831.000 $1.500 $4.000 $1.000 $5.500 $4.000
164 6023 CELL FBR MLCH SEED(PERM)(RURAL)(CLAY) SY 9,831.000 $0.500 $0.510 $1.000 $0.850 $0.500
164 6035 DRILL SEEDING (PERM) (RURAL) (CLAY) SY 9,831.000 $0.200 $0.290 $0.500 $0.650 $0.300
164 6071 BROADCAST SEED (TEMP)(WARM OR COOL) SY 9,831.000 $0.200 $0.310 $0.500 $0.550 $0.300
168 6001 VEGETATIVE WATERING MG 165.000 $20.000 $62.000 $84.000 $40.400 $35.000
169 6001 SOIL RETENTION BLANKETS (CL 1) (TY A) SY 527.000 $1.000 $1.600 $2.000 $2.250 $1.600
169 6006 SOIL RETENTION BLANKETS (CL 2) (TY F) SY 9,304.000 $1.500 $5.550 $2.000 $2.300 $5.700
247 6366 FL BS (CMP IN PLC)(TY A GR 5)(FNAL POS) CY 1,490.000 $60.000 $75.000 $158.000 $191.000 $85.000
247 6391 FL BS (RDWY DEL)(TY A GR 5) TON 458.000 $32.000 $30.000 $75.000 $52.100 $85.000
251 6025 REWORK BS MTL (TY B) (6") (ORD COMP) SY 1,153.000 $10.000 $32.000 $34.000 $14.750 $6.000
275 6001 CEMENT TON 23.000 $225.000 $445.000 $297.000 $340.000 $250.000
275 6003 CEMENT TREAT (NEW BASE) (6") SY 986.000 $2.750 $35.000 $27.000 $53.300 $8.000
275 6004 CEMENT TREAT (MX EXST MTL & NW BS) (6") SY 1,153.000 $2.500 $35.000 $26.000 $45.600 $7.000
310 6001 PRIME COAT (MULTI OPTION) GAL 1,462.000 $4.150 $5.750 $5.000 $7.050 $8.800
316 6004 ASPH (TIER I) GAL 34,141.000 $3.750 $5.450 $5.000 $5.150 $6.500
316 6029 ASPH (RC-250) GAL 316.000 $5.000 $5.750 $5.000 $76.500 $95.000
316 6193 AGGR(TY-D GR-5 SAC-B) CY 6.000 $150.000 $155.290 $160.000 $1,240.000 $1,550.000
316 6240 AGGR(TY-PD GR-4 SAC-B) CY 751.000 $160.000 $220.000 $243.000 $197.000 $245.000
351 6002 FLEXIBLE PAVEMENT STRUCTURE REPAIR(6") SY 2,500.000 $48.340 $79.000 $136.000 $70.800 $88.000
400 6005 CEM STABIL BKFL CY 252.000 $85.000 $200.000 $185.000 $280.000 $350.000
400 6006 CUT & RESTORING PAV SY 17.000 $115.000 $442.000 $204.000 $670.000 $664.000
402 6001 TRENCH EXCAVATION PROTECTION LF 50.000 $5.000 $183.190 $30.000 $20.400 $13.000
403 6001 TEMPORARY SPL SHORING SF 3,278.000 $25.000 $36.000 $24.000 $49.300 $13.000
416 6002 DRILL SHAFT (24 IN) LF 270.000 $400.000 $247.500 $237.380 $192.000 $220.000
416 6004 DRILL SHAFT (36 IN) LF 320.000 $280.000 $304.000 $350.180 $280.000 $325.000
420 6013 CL C CONC (ABUT) CY 67.000 $1,200.000 $1,301.000 $1,319.390 $1,220.000 $1,600.000
422 6001 REINF CONC SLAB SF 2,800.000 $20.000 $21.000 $40.000 $32.050 $44.000
422 6007 REINF CONC SLAB (SLAB BEAM) SF 1,808.000 $22.000 $35.000 $31.000 $26.150 $33.000
422 6015 APPROACH SLAB CY 115.900 $600.000 $743.000 $853.000 $780.000 $880.000
423 6001 RETAINING WALL (MSE) SF 3,005.000 $55.000 $132.000 $74.000 $131.000 $106.000
425 6011 PRESTR CONC SLAB BEAM (4SB15) LF 445.500 $200.000 $265.000 $302.000 $217.000 $245.000
425 6035 PRESTR CONC GIRDER (TX28) LF 347.500 $200.000 $263.000 $376.000 $250.000 $308.000
432 6002 RIPRAP (CONC)(5 IN) CY 120.000 $490.000 $790.000 $834.000 $670.000 $1,000.000
432 6025 RIRRAP (STONE COMMON)(DRY)(15 IN) CY 8.000 $160.000 $519.590 $541.000 $580.000 $535.000
432 6033 RIPRAP (STONE PROTECTION)(18 IN) CY 220.000 $300.000 $210.000 $219.000 $350.000 $220.000
432 6034 RIPRAP (STONE PROTECTION)(21 IN) CY 615.000 $180.000 $235.000 $262.000 $350.000 $1,300.000
432 6045 RIPRAP (MOW STRIP)(4 IN) CY 114.000 $550.000 $629.000 $655.000 $800.000 $650.000
450 6006 RAIL (TY T223) LF 296.000 $150.000 $240.000 $388.000 $145.000 $260.000
454 6004 ARMOR JOINT (SEALED) LF 137.000 $150.000 $166.000 $160.000 $143.000 $180.000
462 6001 CONC BOX CULV (3 FT X 2 FT) LF 94.000 $280.000 $630.000 $475.000 $570.000 $1,100.000
464 6003 RC PIPE (CL III)(18 IN) LF 40.000 $95.000 $158.000 $155.000 $109.000 $145.000
464 6005 RC PIPE (CL III)(24 IN) LF 308.000 $100.000 $151.000 $152.000 $121.000 $138.000
464 6007 RC PIPE (CL III)(30 IN) LF 100.000 $150.000 $227.000 $174.000 $161.000 $162.000
466 6179 WINGWALL (PW - 1) (HW=4 FT) EA 1.000 $12,000.000 $20,500.000 $14,000.000 $12,400.000 $20,000.000
467 6110 SET (TY I)(S=3 FT)(HW= 3 FT)(6:1)(P) EA 1.000 $9,000.000 $13,463.000 $16,000.000 $14,400.000 $21,000.000
467 6363 SET (TY II) (18 IN) (RCP) (6: 1) (P) EA 2.000 $1,200.000 $2,207.000 $4,500.000 $2,730.000 $2,200.000
467 6395 SET (TY II) (24 IN) (RCP) (6: 1) (P) EA 12.000 $1,500.000 $1,912.000 $5,400.000 $3,030.000 $2,900.000
467 6423 SET (TY II) (30 IN) (RCP) (6: 1) (P) EA 4.000 $2,700.000 $3,611.000 $8,000.000 $4,520.000 $4,100.000
479 6001 ADJUSTING MANHOLES EA 1.000 $1,000.000 $1,500.000 $1,500.000 $2,590.000 $2,100.000
496 6006 REMOV STR (HEADWALL) EA 1.000 $1,400.000 $1,936.000 $2,500.000 $1,340.000 $8,800.000
496 6008 REMOV STR (BOX CULVERT) LF 92.000 $75.000 $112.000 $327.000 $92.300 $310.000
496 6009 REMOV STR (BRIDGE 0 - 99 FT LENGTH) EA 2.000 $25,000.000 $54,000.000 $38,000.000 $23,200.000 $20,000.000
500 6001 MOBILIZATION LS 1.000 $327,075.000 $300,000.400 $300,000.000 $590,000.000 $700,000.000
502 6001 BARRICADES, SIGNS AND TRAFFIC HANDLING MO 20.000 $5,000.000 $6,000.000 $15,000.000 $9,000.000 $2,500.000
506 6002 ROCK FILTER DAMS (INSTALL) (TY 2) LF 195.000 $35.000 $49.170 $44.000 $43.050 $50.000
506 6003 ROCK FILTER DAMS (INSTALL) (TY 3) LF 325.000 $75.000 $118.900 $90.000 $86.100 $120.000
506 6011 ROCK FILTER DAMS (REMOVE) LF 520.000 $10.000 $43.220 $32.000 $31.550 $44.000
506 6020 CONSTRUCTION EXITS (INSTALL) (TY 1) SY 444.000 $25.000 $43.090 $31.000 $20.100 $44.000
506 6024 CONSTRUCTION EXITS (REMOVE) SY 444.000 $8.000 $28.550 $2.000 $13.200 $30.000
506 6038 TEMP SEDMT CONT FENCE (INSTALL) LF 2,709.000 $3.500 $4.570 $4.000 $4.000 $4.700
506 6039 TEMP SEDMT CONT FENCE (REMOVE) LF 2,709.000 $0.750 $1.140 $0.600 $0.550 $1.000
506 6041 BIODEG EROSN CONT LOGS (INSTL) (12") LF 2,709.000 $4.500 $4.570 $6.000 $6.300 $4.700
506 6043 BIODEG EROSN CONT LOGS (REMOVE) LF 2,709.000 $1.800 $1.140 $1.000 $1.150 $1.000
508 6001 CONSTRUCTING DETOURS SY 1,030.000 $65.000 $38.000 $234.000 $330.000 $350.000
529 6002 CONC CURB (TY II) LF 200.000 $25.000 $115.000 $48.000 $44.700 $45.000
530 6004 DRIVEWAYS (CONC) SY 89.000 $90.000 $330.000 $189.000 $175.000 $120.000
530 6005 DRIVEWAYS (ACP) SY 1,319.000 $85.000 $69.020 $131.000 $97.100 $58.000
530 6006 DRIVEWAYS (SURF TREAT) SY 1,319.000 $35.000 $18.410 $19.000 $14.050 $18.000
540 6001 MTL W-BEAM GD FEN (TIM POST) LF 1,436.000 $28.000 $31.350 $32.000 $30.000 $32.000
540 6002 MTL W-BEAM GD FEN (STEEL POST) LF 75.000 $36.000 $98.870 $103.000 $105.000 $102.000
540 6006 MTL BEAM GD FEN TRANS (THRIE-BEAM) EA 8.000 $2,300.000 $2,715.020 $3,000.000 $2,890.000 $2,800.000
540 6014 SHORT RADIUS LF 100.000 $75.000 $95.280 $98.000 $101.000 $98.000
540 6015 DRIVEWAY TERMINAL ANCHOR SECTION EA 4.000 $1,125.000 $2,014.680 $1,191.000 $1,200.000 $1,100.000
542 6001 REMOVE METAL BEAM GUARD FENCE LF 470.000 $3.000 $7.950 $8.000 $8.450 $8.000
544 6001 GUARDRAIL END TREATMENT (INSTALL) EA 10.000 $3,500.000 $4,285.050 $4,400.000 $4,560.000 $4,400.000
556 6006 PIPE UNDERDRAINS (TY 6) (6") LF 389.000 $30.000 $100.010 $44.000 $60.450 $35.000
560 6007 MAILBOX INSTALL-S (WC-POST) TY 3 EA 5.000 $200.000 $388.850 $595.000 $171.000 $350.000
644 6001 IN SM RD SN SUP&AM TY10BWG(1)SA(P) EA 24.000 $500.000 $800.570 $841.000 $710.000 $835.000
644 6004 IN SM RD SN SUP&AM TY10BWG(1)SA(T) EA 2.000 $750.000 $888.630 $2,423.000 $860.000 $1,200.000
644 6007 IN SM RD SN SUP&AM TY10BWG(1)SA(U) EA 1.000 $950.000 $1,212.290 $1,208.000 $910.000 $1,200.000
644 6030 IN SM RD SN SUP&AM TYS80(1)SA(T) EA 1.000 $1,200.000 $888.630 $1,300.000 $1,030.000 $1,310.000
644 6076 REMOVE SM RD SN SUP&AM EA 22.000 $85.000 $131.520 $113.000 $114.000 $112.000
658 6047 INSTL OM ASSM (OM-2Y)(WC)GND EA 18.000 $70.000 $124.880 $297.000 $133.000 $130.000
658 6062 INSTL DEL ASSM (D-SW)SZ 1(BRF)GF2(BI) EA 16.000 $35.000 $49.960 $129.000 $53.100 $52.000
662 6063 WK ZN PAV MRK REMOV (W)4"(SLD) LF 6,200.000 $0.850 $0.760 $0.770 $1.050 $0.750
662 6095 WK ZN PAV MRK REMOV (Y)4"(SLD) LF 5,850.000 $0.750 $0.760 $0.770 $1.050 $0.750
662 6111 WK ZN PAV MRK SHT TERM (TAB)TY Y-2 EA 3,190.000 $1.300 $1.170 $4.000 $1.750 $2.000
666 6048 REFL PAV MRK TY I (W)24"(SLD)(100MIL) LF 80.000 $10.000 $35.210 $35.760 $13.750 $35.000
666 6093 REFL PAV MRK TY I (W)(RR XING)(100MIL) EA 2.000 $655.000 $880.230 $893.000 $770.000 $880.000
666 6174 REFL PAV MRK TY II (W) 6" (SLD) LF 69,850.000 $0.360 $0.260 $0.250 $0.680 $0.300
666 6182 REFL PAV MRK TY II (W) 24" (SLD) LF 80.000 $6.000 $5.870 $5.000 $5.750 $5.900
666 6196 REFL PAV MRK TY II (W) (RR XING) EA 2.000 $300.000 $352.090 $357.000 $400.000 $350.000
666 6208 REFL PAV MRK TY II (Y) 6" (BRK) LF 12,468.000 $0.160 $0.200 $0.200 $0.700 $0.200
666 6210 REFL PAV MRK TY II (Y) 6" (SLD) LF 49,039.000 $0.350 $0.420 $0.400 $0.700 $0.400
666 6343 REF PROF PAV MRK TY I(W)6"(SLD)(100MIL) LF 69,850.000 $0.650 $1.090 $1.000 $0.940 $1.100
666 6346 REF PROF PAV MRK TY I(Y)6"(BRK)(100MIL) LF 12,478.000 $0.970 $0.620 $1.000 $0.950 $0.600
666 6347 REF PROF PAV MRK TY I(Y)6"(SLD)(100MIL) LF 49,039.000 $0.650 $1.090 $1.250 $0.950 $1.100
672 6009 REFL PAV MRKR TY II-A-A EA 873.000 $4.500 $8.510 $8.000 $5.000 $8.500
3076 6003 D-GR HMA TY-B PG64-22 (EXEMPT) TON 1,106.000 $105.000 $201.000 $208.000 $169.000 $200.000
3076 6051 D-GR HMA TY-D PG76-22 (LEVEL-UP) TON 2,002.000 $135.850 $196.000 $202.000 $202.000 $230.000
3076 6072 D-GR HMA TY-D PG 76-22 (EXEMPT) TON 1,045.000 $105.000 $230.060 $238.000 $213.000 $245.000
3076 6080 D-GR HMA TY-C PG76-22 (EXEMPT) TON 156.000 $105.000 $483.130 $500.000 $280.000 $325.000
3085 6001 UNDERSEAL COURSE GAL 2,589.000 $3.500 $5.750 $5.000 $10.100 $13.000
6001 6001 PORTABLE CHANGEABLE MESSAGE SIGN DAY 180.000 $94.940 $62.000 $300.000 $36.350 $83.000
6185 6002 TMA (STATIONARY) DAY 171.000 $175.000 $171.000 $300.000 $200.000 $206.000
6185 6003 TMA (MOBILE OPERATION) HR 86.000 $125.000 $18.000 $500.000 $106.000 $95.000
6305 6001 LCS SYSTEM EA 2.000 $4,500.000 $4,500.000 $36,000.000 $100.000 $5,000.000
6305 6005 LCS SYSTEM (RELOCATE) EA 5.000 $1,100.000 $1,500.000 $6,000.000 $100.000 $2,700.000
6305 6007 LCS SYSTEM (REMOVE) EA 2.000 $4,400.000 $2,500.000 $600.000 $100.000 $560.000
7251 6001 SUBSURFACE UTIL LOCATE (OUTSIDE RDBED) EA 16.000 $2,000.000 $1,200.000 $2,800.000 $2,050.000 $1,000.000
Totals: $3,834,660.84 $5,546,235.00 $6,263,294.18 $6,563,207.20 $7,117,045.20