WILLIAMSON CR (0914-05-174)

Items: 48

County: WILLIAMSON
Length: N/A
Highway: CR
District: AUSTIN
Control Number: 0914-05-174
DBE Goal: N/A
Project: BR 2020(731)
Guaranty: N/A
Time: 85 WORKING DAYS
Engineer's Estimate: $667,325.43
Date: 03/07/2023 (3 years ago)
Contract Number: N/A
Type: BRIDGE REPLACEMENT
Mail/Deliver Bids To: N/A
JASON HUDSON
JOHN PETERS
Actions:
Notice HCS Excel Tabs Print Print Notice
Pay Estimates:
Bidders (3)
E
Engineer's Estimate
$667,325.43
$769,807.30
Over/Under Est: 15.36% $102,481.87
Over/Under Est: 25.06% $167,254.92
Amt Left: 8.41% $64,773.05
$844,848.00
Over/Under Est: 26.6% $177,522.57
Amt Left: 9.75% $75,040.70
Delta: -1.23% -$10,267.65

Bid Items & Bid Tabulations

48 Total 0 of 48
WILLIAMSON  |  CR  |  AUSTIN  |  0914-05-174  |  03/07/2023  |  $667,325.43  |  BR 2020(731)  |  BRIDGE REPL  |  85 WORKING DAYS
Item Code
Description
Unit
Quantity
Engineer's Estimate
KNIFE RIVER CORPORATION - SOUTH
A GREATER AUSTIN DEVELOPMENT COMPANY, LTD.
CHASCO CONSTRUCTORS
PREPARING ROW
STA 3.630 $3,000.000 $4,800.000 $5,000.000 $10,000.000
REMOVING STAB BASE & ASPH PAV (5" - 6")
SY 649.000 $2.000 $12.000 $28.000 $20.000
EXCAVATION (ROADWAY)
CY 70.000 $10.080 $130.000 $31.000 $60.000
EMBANKMENT (FINAL)(ORD COMP)(TY C)
CY 267.000 $20.000 $25.000 $79.000 $80.000
FURNISHING AND PLACING TOPSOIL (4")
SY 682.000 $1.970 $1.750 $3.000 $3.000
BROADCAST SEED (PERM) (RURAL) (CLAY)
SY 682.000 $0.500 $2.100 $1.800 $1.500
BROADCAST SEED (TEMP)(WARM OR COOL)
SY 682.000 $0.320 $2.100 $1.300 $1.500
VEGETATIVE WATERING
MG 1.200 $34.360 $350.000 $1,165.000 $100.000
SOIL RETENTION BLANKETS (CL 1) (TY C)
SY 682.000 $1.860 $2.100 $1.900 $2.000
FL BS (CMP IN PLC)(TY A GR 5)(FNAL POS)
CY 123.000 $46.580 $150.000 $118.000 $125.000
CEM STABIL BKFL
CY 81.000 $125.840 $265.000 $177.000 $250.000
DRILL SHAFT (24 IN)
LF 249.000 $407.690 $225.000 $242.350 $200.000
CL C CONC (ABUT)
CY 19.800 $1,216.170 $1,850.000 $1,315.000 $2,200.000
CL C CONC (CAP)
CY 7.600 $2,275.650 $2,000.000 $1,635.000 $1,900.000
CL C CONC (COLUMN)
CY 2.800 $2,406.050 $2,850.000 $3,560.000 $2,800.000
REINF CONC SLAB (SLAB BEAM)
SF 2,106.000 $20.000 $29.000 $30.850 $38.000
APPROACH SLAB
CY 54.000 $600.000 $740.000 $620.000 $775.000
PRESTR CONC SLAB BEAM (5SB12)
LF 414.020 $246.300 $235.000 $295.000 $250.000
RIPRAP (STONE PROTECTION)(12 IN)
CY 588.000 $115.000 $130.000 $117.000 $160.000
RIPRAP (MOW STRIP)(4 IN)
CY 19.300 $505.170 $785.000 $975.000 $610.000
RAIL (TY T223)
LF 164.000 $149.560 $140.000 $175.000 $200.000
ARMOR JOINT (SEALED)
LF 59.000 $140.000 $135.000 $165.000 $150.000
REMOV STR (BRIDGE 0 - 99 FT LENGTH)
EA 1.000 $18,332.670 $35,000.000 $34,200.000 $40,000.000
REMOV STR (SMALL FENCE)
LF 55.000 $3.510 $10.000 $18.000 $5.000
MOBILIZATION
LS 1.000 $60,665.950 $76,000.000 $83,200.000 $81,106.000
BARRICADES, SIGNS AND TRAFFIC HANDLING
MO 6.000 $6,000.000 $2,000.000 $5,000.000 $1,600.000
ROCK FILTER DAMS (INSTALL) (TY 2)
LF 100.000 $34.670 $43.000 $37.450 $35.000
ROCK FILTER DAMS (INSTALL) (TY 3)
LF 68.000 $93.090 $126.000 $62.400 $55.000
ROCK FILTER DAMS (INSTALL) (TY 4)
LF 100.000 $34.100 $76.000 $43.700 $40.000
ROCK FILTER DAMS (REMOVE)
LF 368.000 $16.110 $28.000 $25.000 $20.000
TEMP SEDMT CONT FENCE (INSTALL)
LF 592.000 $3.840 $8.500 $5.000 $5.000
TEMP SEDMT CONT FENCE (REMOVE)
LF 592.000 $0.400 $1.000 $1.250 $1.000
BIODEG EROSN CONT LOGS (INSTL) (12")
LF 100.000 $4.680 $7.000 $5.000 $5.000
BIODEG EROSN CONT LOGS (REMOVE)
LF 100.000 $4.080 $1.000 $1.250 $1.000
ROCK FILTER DAMS (INSTALL) (TY 2) (6:1)
LF 100.000 $42.500 $66.000 $50.000 $45.000
MTL W-BEAM GD FEN (TIM POST)
LF 150.000 $27.300 $28.000 $34.150 $29.000
MTL BEAM GD FEN TRANS (THRIE-BEAM)
EA 4.000 $2,224.330 $2,750.000 $3,100.000 $2,000.000
GUARDRAIL END TREATMENT (INSTALL)
EA 4.000 $3,824.510 $3,300.000 $2,875.000 $2,400.000
WIRE FENCE (WATER GAP)
LF 55.000 $40.000 $110.000 $180.000 $110.000
IN SM RD SN SUP&AM TY10BWG(1)SA(P)
EA 1.000 $568.240 $1,100.000 $1,155.000 $975.000
REMOVE SM RD SN SUP&AM
EA 4.000 $104.630 $75.000 $175.000 $160.000
INSTL DEL ASSM (D-SW)SZ (BRF)CTB (BI)
EA 6.000 $25.400 $25.000 $25.000 $20.000
REMOVE DELIN & OBJECT MARKER ASSMS
EA 4.000 $11.760 $40.000 $25.000 $25.000
INSTL DEL ASSM (D-SW)SZ 1(BRF)GF2(BI)
EA 12.000 $29.000 $60.000 $66.000 $55.000
REF PROF PAV MRK TY I(Y)4"(SLD)(100MIL)
LF 363.000 $0.600 $25.000 $33.000 $28.000
REFL PAV MRKR TY II-A-A
EA 9.000 $3.910 $35.000 $12.000 $11.000
D-GR HMA TY-D PG 76-22 (EXEMPT)
TON 122.000 $135.110 $225.000 $375.000 $320.000
PORTABLE CHANGEABLE MESSAGE SIGN
DAY 30.000 $98.500 $175.000 $165.000 $75.000
Totals: $667,325.435 $769,807.300 $834,580.350 $844,848.000