Job Info for 0320-04-027

County: WILLIAMSON Highway: US 79 Date: 06/05/2019 (5 years ago) Engineer's Estimate: $1,284,714 Control Number: 0320-04-027
Project: NH 2019(993) District: AUSTIN Time: 119 WORKING DAYS Type: LANDSCAPE DEVELOPMENT

Bidders

Name Total Amount Place Over/Under Est Amt Left From Low Bid Delta Between Bidders
Engineer's Estimate $1,284,713.75
APEX LANDSCAPE & IRRIGATION, LLC   $1,038,568.89 1
-19.16% | -$246,144.86
TIGHT LINE CONSTRUCTION, LLC   $1,206,745.65 2
-6.07% | -$77,968.10
16.19% | $168,176.76
ENCINO LANDSCAPE, INC.   $1,382,980.90 3
7.65% | $98,267.15
33.16% | $344,412.01
14.60% | $176,235.25
CENTRAL NORTH CONSTRUCTION, LLC   $1,498,213.35 4
16.62% | $213,499.60
44.26% | $459,644.46
8.33% | $115,232.45
CROSS PLUS CONSTRUCTION, LLC   $1,881,603.00 5
46.46% | $596,889.25
81.17% | $843,034.11
25.59% | $383,389.65

Bid Items

Items: 28, 0 filtered
WILLIAMSON US 79  |  AUSTIN  |  0320-04-027  |  06/05/2019  |  $1,284,714  |  NH 2019(993)  |  LANDSCAPE DEVELOPMENT  |  119 WORKING DAYS
Item code Description Unit Quantity Engineer's Estimate APEX LANDSCAPE & IRRIGATION, LLC TIGHT LINE CONSTRUCTION, LLC ENCINO LANDSCAPE, INC. CENTRAL NORTH CONSTRUCTION, LLC CROSS PLUS CONSTRUCTION, LLC
161 6022 GENERAL USE COMPOST (4") SY 20,153.000 $4.000 $1.780 $3.000 $2.000 $5.150 $5.000
170 6001 IRRIGATION SYSTEM LS 1.000 $132,725.000 $100,000.000 $125,000.000 $300,000.000 $438,000.000 $250,000.000
180 6001 WILDFLOWER SEEDING AC 31.100 $1,800.000 $500.000 $2,100.000 $2,000.000 $2,475.000 $500.000
192 6004 PLANT MATERIAL (5-GAL) EA 4,124.000 $25.000 $23.900 $30.000 $30.000 $15.000 $35.000
192 6005 PLANT MATERIAL (15-GAL) EA 1,449.000 $130.000 $128.000 $110.000 $125.000 $80.000 $178.000
192 6006 PLANT MATERIAL (30-GAL) EA 872.000 $240.000 $231.000 $225.000 $225.000 $170.000 $345.000
192 6013 MULCH SY 20,153.000 $3.500 $3.510 $3.000 $3.000 $2.800 $3.000
192 6014 PLANT SOIL MIX CY 68.000 $45.000 $40.000 $50.000 $50.000 $100.000 $56.000
192 6016 PLANT BED PREPARATION SY 20,153.000 $3.000 $1.940 $1.000 $1.000 $1.500 $2.000
193 6001 PLANT MAINTENANCE MO 24.000 $250.000 $2,950.000 $1,500.000 $2,000.000 $3,600.000 $4,000.000
193 6005 PLANT REPLACEMENT (5-GAL) EA 200.000 $25.000 $0.100 $0.010 $0.010 $15.000 $40.000
193 6007 IRRIGATION SYSTEM OPER AND MAINT MO 24.000 $150.000 $1,000.000 $1,500.000 $3,000.000 $1,320.000 $4,000.000
193 6009 PLANT REPLACEMENT (15 GAL) EA 100.000 $130.000 $0.100 $0.010 $0.010 $80.000 $178.000
193 6010 PLANT REPLACEMENT (30 GAL) EA 50.000 $240.000 $0.100 $0.010 $0.010 $170.000 $199.000
402 6001 TRENCH EXCAVATION PROTECTION LF 50.000 $10.000 $0.100 $0.010 $0.010 $35.000 $56.000
403 6001 TEMPORARY SPL SHORING SF 50.000 $10.000 $0.100 $0.010 $0.010 $50.000 $56.000
420 6012 CL B CONC (MISC) CY 50.000 $1,500.000 $325.000 $700.000 $500.000 $1,000.000 $500.000
423 6015 RETAINING WALL (SPECIAL) SF 608.000 $90.000 $65.000 $50.000 $40.000 $95.000 $56.000
432 6002 RIPRAP (CONC)(5 IN) CY 1.000 $550.000 $0.100 $500.000 $1,000.000 $1,500.000 $1,000.000
500 6001 MOBILIZATION LS 1.000 $118,522.250 $110,000.000 $150,000.000 $120,000.000 $150,000.000 $120,000.000
502 6001 BARRICADES, SIGNS AND TRAFFIC HANDLING MO 10.000 $1,500.000 $1,500.000 $3,000.000 $4,000.000 $3,300.000 $5,000.000
506 6035 SANDBAGS FOR EROSION CONTROL EA 50.000 $5.000 $0.100 $10.000 $1.000 $25.000 $9.000
506 6038 TEMP SEDMT CONT FENCE (INSTALL) LF 200.000 $2.500 $0.100 $2.000 $1.000 $2.500 $9.000
506 6039 TEMP SEDMT CONT FENCE (REMOVE) LF 200.000 $1.000 $0.100 $1.000 $1.000 $0.100 $9.000
506 6041 BIODEG EROSN CONT LOGS (INSTL) (12") LF 11,825.000 $4.000 $0.100 $5.000 $5.000 $0.100 $9.000
506 6043 BIODEG EROSN CONT LOGS (REMOVE) LF 11,825.000 $1.000 $0.100 $1.000 $0.010 $0.100 $9.000
1004 6001 TREE PROTECTION EA 27.000 $500.000 $300.000 $100.000 $200.000 $500.000 $345.000
6185 6002 TMA (STATIONARY) DAY 15.000 $175.000 $200.000 $0.010 $0.010 $550.000 $1,200.000
Totals: $1,284,713.75 $1,038,568.89 $1,206,745.65 $1,382,980.90 $1,498,213.35 $1,881,603.00