Show Job Controls
Bid Cobra

WILLIAMSON US 183 (0273-04-048)

Items: 113

County: WILLIAMSON
Length: N/A
Highway: US 183
District: AUSTIN
Control Number: 0273-04-048
DBE Goal: N/A
Project: F 2021(949)
Guaranty: N/A
Time: 234 WORKING DAYS
Engineer's Estimate: $5,039,982.58
Date: 08/04/2021 (4 years ago)
Contract Number: N/A
Type: REHABILITATION OF EXISTING ROAD
Mail/Deliver Bids To: N/A
SEE PLANS OR PROPOSAL BOOK
Actions:
Notice HCS Excel Tabs Print Print Notice
Documents:
Bidders (8)
E
Engineer's Estimate
$5,039,982.58
$5,760,579.27
Over/Under Est: 14.3% $720,596.69
Over/Under Est: 17.01% $857,330.48
Amt Left: 2.37% $136,733.79
$6,041,968.71
Over/Under Est: 19.88% $1,001,986.13
Amt Left: 4.88% $281,389.44
Delta: -2.45% -$144,655.65
$6,116,242.46
Over/Under Est: 21.35% $1,076,259.88
Amt Left: 6.17% $355,663.19
Delta: -1.23% -$74,273.75
Over/Under Est: 27.54% $1,387,969.29
Amt Left: 11.59% $667,372.60
Delta: -5.10% -$311,709.41
Over/Under Est: 28.35% $1,428,825.67
Amt Left: 12.29% $708,228.98
Delta: -0.64% -$40,856.38
Over/Under Est: 30.53% $1,538,534.67
Amt Left: 14.2% $817,937.98
Delta: -1.70% -$109,709.00
Over/Under Est: 34.76% $1,751,879.33
Amt Left: 17.9% $1,031,282.64
Delta: -3.24% -$213,344.66

Bid Items & Bid Tabulations

113 Total 0 of 113
WILLIAMSON  |  US 183  |  AUSTIN  |  0273-04-048  |  08/04/2021  |  $5,039,982.58  |  F 2021(949)  |  REHAB OF EXIST ROAD  |  234 WORKING DAYS
Item Code
Description
Unit
Quantity
Engineer's Estimate
TEXAS MATERIALS GROUP, INC.
CAPITAL EXCAVATION COMPANY
DAN WILLIAMS COMPANY
PRODIRT SERVICES, LLC
AUSTIN UNDERGROUND INCORPORATED
DIAMOND X CONTRACTING, INC
AARON CONCRETE CONTRACTORS, L.P.
LONE STAR SITEWORK, LLC
PREPARING ROW
STA 121.700 $2,000.000 $600.000 $1,250.000 $1,650.000 $1,000.000 $2,600.000 $1,500.000 $500.000 $250.000
REMOVING CONC (DRIVEWAYS)
SY 322.000 $15.000 $12.000 $15.700 $9.000 $25.000 $25.000 $17.000 $37.000 $11.500
REMOVING CONC (CURB AND GUTTER)
LF 37.000 $5.100 $10.000 $9.250 $8.000 $100.000 $19.000 $12.000 $24.000 $29.000
REMOVING CONC (MISC)
SY 377.000 $40.000 $12.000 $7.600 $9.000 $25.000 $30.000 $20.000 $36.000 $13.750
REMOVING CONCRETE(MOW STRIP)
LF 428.000 $16.000 $12.000 $10.250 $5.000 $65.000 $12.000 $11.000 $8.000 $8.500
REMOVING STAB BASE & ASPH PAV(16")
SY 5,584.000 $4.000 $16.000 $6.500 $6.000 $10.000 $10.000 $9.000 $11.000 $10.000
EXCAVATION (ROADWAY)
CY 19,270.000 $8.000 $11.000 $17.000 $20.000 $16.000 $17.000 $23.000 $13.000 $18.300
EMBANKMENT (FINAL)(ORD COMP)(TY B)
CY 7,337.000 $12.000 $9.000 $27.000 $15.000 $19.000 $6.500 $15.000 $8.000 $15.400
BACKFILL (TY A)
STA 9.300 $386.000 $500.000 $560.000 $1,000.000 $2,000.000 $350.000 $400.000 $1,300.000 $4,250.000
FURNISHING AND PLACING TOPSOIL (4")
SY 54,978.000 $1.000 $1.000 $3.000 $1.000 $2.000 $4.000 $2.000 $1.300 $5.200
BROADCAST SEED (PERM) (RURAL) (CLAY)
SY 54,978.000 $0.140 $0.250 $0.180 $0.250 $0.500 $0.400 $0.300 $0.300 $0.300
BROADCAST SEED (TEMP) (WARM)
SY 27,489.000 $0.140 $0.250 $0.120 $0.250 $0.500 $0.250 $0.300 $0.300 $0.300
BROADCAST SEED (TEMP) (COOL)
SY 27,489.000 $0.110 $0.250 $0.120 $0.250 $0.500 $0.250 $0.300 $0.300 $0.300
VEGETATIVE WATERING
MG 1,004.000 $16.500 $20.000 $21.400 $5.000 $20.000 $26.000 $40.000 $35.000 $66.500
PROOF ROLLING
HR 40.000 $198.000 $60.000 $78.900 $60.000 $125.000 $54.000 $75.000 $125.000 $85.000
FL BS (CMP IN PLC)(TY A GR 5)(FNAL POS)
CY 7,924.000 $45.000 $65.000 $50.000 $40.000 $52.000 $55.000 $57.000 $74.000 $60.500
PRIME COAT (MULTI OPTION)
GAL 6,481.000 $4.000 $4.000 $4.100 $3.950 $4.250 $6.000 $4.250 $4.600 $3.500
D-GR HMA (SQ) TY-D PG64_22(LEVEL-UP)
TON 33.700 $83.000 $250.000 $171.000 $170.000 $175.000 $200.000 $170.000 $192.000 $214.500
TACK COAT
GAL 362.000 $3.620 $2.700 $4.150 $4.000 $4.150 $5.000 $4.300 $4.600 $3.000
TOM (ASPHALT) PG 76-22
TON 337.000 $105.000 $114.000 $115.000 $112.000 $115.000 $110.000 $119.000 $130.000 $143.000
TOM-C (AGGREGATE) SAC-A
TON 3,089.000 $95.000 $114.000 $120.000 $112.000 $115.000 $115.000 $119.000 $130.000 $143.000
TOM - C (AGGREGATE) SAC - B
TON 2,006.000 $100.000 $114.000 $117.000 $110.000 $113.000 $120.000 $116.000 $130.000 $143.000
FLEXIBLE PAVEMENT STRUCTURE REPAIR(8")
SY 9,610.000 $32.000 $40.000 $45.500 $45.000 $48.000 $57.000 $47.000 $52.000 $49.500
PLAN & TEXT ASPH CONC PAV(0" TO 2")
SY 34,229.000 $1.500 $2.400 $3.450 $4.000 $3.500 $3.000 $3.600 $4.000 $1.700
TEMPORARY SPL SHORING
SF 4,300.000 $27.000 $32.000 $21.950 $30.000 $45.000 $33.000 $29.290 $34.000 $29.570
RETAINING WALL (CAST - IN - PLACE)
SF 8,395.000 $78.000 $82.000 $60.000 $75.000 $65.000 $65.000 $86.000 $86.000 $103.500
RIPRAP (CONC)(5 IN)
CY 329.000 $482.000 $480.000 $515.000 $425.000 $600.000 $490.000 $490.000 $645.000 $635.000
RIPRAP (STONE COMMON)(GROUT)(12 IN)
CY 17.000 $151.000 $320.000 $350.000 $355.000 $400.000 $220.000 $322.000 $400.000 $125.000
RIPRAP (MOW STRIP)(4 IN)
CY 201.000 $425.000 $540.000 $490.000 $525.000 $700.000 $590.000 $500.000 $600.000 $667.000
CMP AR (GAL STL DES 2)
LF 320.000 $65.000 $63.000 $72.500 $90.000 $60.000 $64.000 $98.000 $130.000 $64.000
CONC BOX CULV (4 FT X 4 FT)
LF 4.000 $303.000 $1,200.000 $2,300.000 $2,000.000 $1,800.000 $2,700.000 $2,700.000 $1,000.000 $980.000
CONC BOX CULV (7 FT X 6 FT)
LF 21.000 $508.000 $1,600.000 $1,160.000 $1,500.000 $2,000.000 $1,500.000 $2,000.000 $1,600.000 $1,975.000
RC PIPE (CL III)(18 IN)
LF 537.000 $60.000 $65.000 $73.700 $65.000 $45.000 $73.000 $93.000 $115.000 $60.500
RC PIPE (CL III)(24 IN)
LF 602.000 $83.000 $70.000 $81.380 $85.000 $65.000 $90.000 $109.000 $124.000 $84.500
WINGWALL (FW - S) (HW=9 FT)
EA 1.000 $25,900.000 $30,000.000 $26,500.000 $30,000.000 $30,000.000 $34,000.000 $40,000.000 $33,000.000 $58,320.000
SET (TY II) (15 IN) (CMP) (6: 1) (P)
EA 10.000 $804.000 $1,200.000 $1,200.000 $1,250.000 $1,500.000 $1,600.000 $1,600.000 $2,000.000 $1,975.000
SET (TY II) (18 IN) (RCP) (6: 1) (P)
EA 20.000 $1,300.000 $1,900.000 $1,330.000 $1,250.000 $1,600.000 $1,800.000 $1,710.000 $2,200.000 $2,230.000
SET (TY II) (24 IN) (RCP) (6: 1) (P)
EA 22.000 $1,600.000 $1,800.000 $1,820.000 $1,600.000 $1,900.000 $1,900.000 $1,900.000 $2,500.000 $2,530.000
REMOV STR (SET)
EA 20.000 $460.000 $430.000 $214.000 $250.000 $1,100.000 $430.000 $500.000 $660.000 $350.000
REMOV STR (WINGWALL)
EA 2.000 $1,500.000 $2,900.000 $3,550.000 $1,000.000 $2,500.000 $1,700.000 $1,500.000 $3,000.000 $3,500.000
REMOV STR (PIPE)
LF 361.000 $15.000 $15.000 $7.900 $20.000 $40.000 $20.000 $25.000 $43.000 $20.000
MOBILIZATION
LS 1.000 $349,000.000 $555,000.000 $425,000.000 $600,000.000 $250,000.000 $320,000.000 $500,000.000 $500,000.000 $220,000.000
BARRICADES, SIGNS AND TRAFFIC HANDLING
MO 15.000 $8,000.000 $2,700.000 $1,810.000 $14,250.000 $4,500.000 $5,500.000 $3,000.000 $1,400.000 $1,500.000
ROCK FILTER DAMS (INSTALL) (TY 2)
LF 50.000 $25.000 $28.000 $28.200 $35.000 $40.000 $47.000 $37.000 $40.000 $40.000
ROCK FILTER DAMS (REMOVE)
LF 50.000 $8.200 $20.000 $20.500 $30.000 $30.000 $4.000 $33.000 $34.000 $35.000
TEMP SEDMT CONT FENCE (INSTALL)
LF 10,306.000 $2.750 $2.500 $2.550 $4.000 $5.000 $2.500 $4.000 $4.500 $4.600
TEMP SEDMT CONT FENCE (REMOVE)
LF 10,306.000 $0.750 $0.250 $0.250 $1.000 $1.000 $0.300 $1.000 $1.100 $1.200
CONC CURB & GUTTER (TY II)
LF 37.000 $17.600 $60.000 $91.400 $40.000 $40.000 $34.000 $70.000 $32.000 $50.000
DRIVEWAYS (CONC)
SY 286.000 $80.000 $75.000 $104.000 $65.000 $90.000 $90.000 $113.000 $100.000 $89.500
DRIVEWAYS (ACP)
SY 1,360.000 $40.000 $50.000 $86.200 $60.000 $65.000 $59.000 $58.000 $82.000 $68.500
TURNOUTS (ACP)
SY 82.000 $70.000 $190.000 $106.000 $73.000 $70.000 $62.000 $61.000 $79.000 $85.000
MTL W-BEAM GD FEN (TIM POST)
LF 3,225.000 $21.400 $30.000 $21.050 $23.000 $34.000 $30.000 $31.000 $32.000 $32.600
SHORT RADIUS
LF 75.000 $39.000 $40.000 $42.550 $42.000 $40.000 $590.000 $38.000 $41.000 $41.000
DRIVEWAY TERMINAL ANCHOR SECTION
EA 2.000 $850.000 $900.000 $920.000 $1,000.000 $1,500.000 $1,400.000 $945.000 $1,000.000 $1,009.000
DOWNSTREAM ANCHOR TERMINAL SECTION
EA 12.000 $1,600.000 $1,300.000 $1,180.000 $1,250.000 $1,800.000 $1,500.000 $1,305.000 $1,400.000 $1,395.000
MTL BM GD FEN (LONG SPAN SYSTEM)
LF 150.000 $24.000 $30.000 $23.100 $25.000 $35.000 $30.000 $32.000 $34.000 $33.500
REMOVE METAL BEAM GUARD FENCE
LF 1,425.000 $2.000 $2.500 $2.050 $2.500 $4.000 $1.500 $3.000 $3.000 $2.900
REMOVE TERMINAL ANCHOR SECTION
EA 1.000 $182.000 $160.000 $154.000 $200.000 $400.000 $270.000 $162.000 $171.000 $172.000
REMOVE DOWNSTREAM ANCHOR TERMINAL
EA 5.000 $160.000 $160.000 $154.000 $200.000 $400.000 $180.000 $162.000 $171.000 $172.000
GUARDRAIL END TREATMENT (INSTALL)
EA 9.000 $2,650.000 $3,500.000 $2,720.000 $3,000.000 $4,500.000 $3,700.000 $3,500.000 $3,600.000 $3,666.000
GUARDRAIL END TREATMENT (REMOVE)
EA 3.000 $216.000 $270.000 $205.000 $225.000 $400.000 $250.000 $270.000 $285.000 $288.000
MAILBOX INSTALL-S (TWG-POST) TY 1
EA 7.000 $180.000 $220.000 $226.000 $250.000 $500.000 $240.000 $271.000 $290.000 $290.000
MAILBOX INSTALL-D (TWG-POST) TY 1
EA 3.000 $205.000 $310.000 $270.000 $275.000 $550.000 $340.000 $296.000 $315.000 $316.000
MAILBOX INSTALL-M (TWG-POST) TY 1
EA 2.000 $345.000 $440.000 $350.000 $350.000 $600.000 $490.000 $460.000 $485.000 $489.000
IN SM RD SN SUP&AM TY10BWG(1)SA(P)
EA 41.000 $550.000 $630.000 $500.000 $500.000 $750.000 $700.000 $714.000 $755.000 $762.000
IN SM RD SN SUP&AM TY10BWG(1)SA(T)
EA 5.000 $550.000 $680.000 $580.000 $580.000 $1,000.000 $810.000 $870.000 $920.000 $928.000
IN SM RD SN SUP&AM TY10BWG(1)SA(U)
EA 2.000 $675.000 $700.000 $700.000 $690.000 $1,200.000 $840.000 $920.000 $973.000 $982.000
IN SM RD SN SUP&AM TYS80(1)SA(P)
EA 1.000 $668.000 $900.000 $770.000 $755.000 $1,500.000 $1,100.000 $1,030.000 $1,100.000 $1,097.000
REMOVE SM RD SN SUP&AM
EA 39.000 $90.000 $94.000 $20.500 $130.000 $400.000 $100.000 $140.000 $142.000 $144.000
INSTL DEL ASSM (D-SW)SZ (BRF)GF1
EA 17.000 $21.500 $22.000 $20.500 $20.000 $25.000 $25.000 $18.000 $18.000 $18.400
INSTL OM ASSM (OM-2Y)(WC)GND
EA 20.000 $75.000 $70.000 $40.000 $20.000 $75.000 $80.000 $57.000 $60.000 $60.400
WK ZN PAV MRK NON-REMOV (W)4"(BRK)
LF 170.000 $0.100 $0.250 $0.250 $0.220 $0.400 $0.300 $0.250 $0.600 $0.600
WK ZN PAV MRK NON-REMOV (W)4"(SLD)
LF 22,463.000 $0.200 $0.240 $0.250 $0.200 $0.380 $0.200 $0.250 $0.300 $0.300
WK ZN PAV MRK NON-REMOV (Y)4"(BRK)
LF 5,660.000 $0.200 $0.260 $0.250 $0.220 $0.400 $0.300 $0.250 $0.300 $0.300
WK ZN PAV MRK NON-REMOV (Y)4"(SLD)
LF 22,531.000 $0.200 $0.240 $0.250 $0.200 $0.380 $0.200 $0.250 $0.300 $0.300
WK ZN PAV MRK NON-REMOV (Y)8"(SLD)
LF 27.000 $3.000 $2.380 $0.500 $2.000 $2.500 $2.500 $2.000 $11.400 $11.500
WK ZN PAV MRK REMOV (TRAF BTN) TY W
EA 170.000 $3.000 $1.780 $2.550 $1.500 $1.750 $2.000 $1.600 $5.700 $5.300
WK ZN PAV MRK SHT TERM (TAB)TY W
EA 652.000 $1.000 $1.050 $3.150 $2.000 $2.000 $0.600 $1.000 $1.000 $1.000
WK ZN PAV MRK SHT TERM (TAB)TY Y-2
EA 709.000 $1.000 $1.050 $3.150 $2.000 $2.000 $0.600 $1.000 $2.000 $1.000
REFL PAV MRK TY I (W)8"(SLD)(100MIL)
LF 2,278.000 $0.840 $0.750 $0.700 $0.650 $0.750 $0.700 $0.700 $0.800 $0.800
REFL PAV MRK TY I (W)24"(SLD)(100MIL)
LF 119.000 $7.750 $5.500 $6.150 $5.000 $5.250 $5.500 $5.400 $8.000 $8.000
REFL PAV MRK TY I (W)(ARROW)(100MIL)
EA 33.000 $150.000 $100.000 $169.000 $90.000 $120.000 $95.000 $96.000 $171.000 $172.000
REFL PAV MRK TY I (W)(WORD)(100MIL)
EA 11.000 $145.000 $110.000 $190.000 $95.000 $110.000 $100.000 $102.000 $171.000 $172.000
REFL PAV MRK TY II (W) 4" (BRK)
LF 5,940.000 $0.180 $0.170 $0.150 $0.140 $0.250 $0.170 $0.150 $0.200 $0.190
REFL PAV MRK TY II (W) 4" (SLD)
LF 23,520.000 $0.150 $0.150 $0.150 $0.130 $0.220 $0.170 $0.140 $0.200 $0.190
REFL PAV MRK TY II (W) 8" (SLD)
LF 2,278.000 $0.540 $0.400 $0.300 $0.350 $0.500 $0.400 $0.380 $0.600 $0.600
REFL PAV MRK TY II (W) 24" (SLD)
LF 119.000 $2.750 $1.600 $3.100 $1.450 $1.750 $1.500 $1.600 $5.700 $5.700
REFL PAV MRK TY II (W) (ARROW)
EA 33.000 $60.000 $53.000 $41.050 $45.000 $65.000 $50.000 $48.000 $75.000 $75.000
REFL PAV MRK TY II (W) (WORD)
EA 11.000 $75.000 $59.000 $41.050 $50.000 $70.000 $55.000 $54.000 $75.000 $75.000
REFL PAV MRK TY II (Y) 4" (BRK)
LF 5,270.000 $0.190 $0.160 $0.150 $0.140 $0.250 $0.170 $0.150 $0.200 $0.180
REFL PAV MRK TY II (Y) 4" (SLD)
LF 24,187.000 $0.160 $0.150 $0.150 $0.130 $0.220 $0.160 $0.150 $0.200 $0.180
RE PM W/RET REQ TY I (W)4"(BRK)(100MIL)
LF 5,940.000 $0.400 $0.440 $0.350 $0.370 $0.500 $0.400 $0.400 $0.500 $0.500
RE PM W/RET REQ TY I (Y)4"(BRK)(100MIL)
LF 5,270.000 $0.400 $0.440 $0.350 $0.370 $0.500 $0.400 $0.400 $0.500 $0.500
REF PROF PAV MRK TY I(W)4"(SLD)(100MIL)
LF 23,520.000 $0.610 $0.700 $0.700 $0.600 $0.750 $0.650 $0.650 $0.700 $0.650
REF PROF PAV MRK TY I(Y)4"(SLD)(100MIL)
LF 24,187.000 $0.560 $0.700 $0.700 $0.600 $0.750 $0.650 $0.650 $0.700 $0.650
REFL PAV MRKR TY I-C
EA 413.000 $3.500 $4.500 $3.850 $4.000 $4.500 $4.500 $4.360 $4.600 $4.600
REFL PAV MRKR TY II-A-A
EA 689.000 $3.500 $4.500 $3.850 $4.000 $4.150 $4.500 $4.250 $4.600 $4.600
ELIM EXT PAV MRK & MRKS (4")
LF 39,614.000 $0.300 $0.300 $0.450 $0.300 $0.400 $0.400 $0.270 $0.600 $0.600
ELIM EXT PAV MRK & MRKS (8")
LF 765.000 $1.850 $0.750 $1.050 $0.650 $0.750 $0.700 $0.700 $1.700 $1.700
ELIM EXT PAV MRK & MRKS (ARROW)
EA 5.000 $61.000 $80.000 $44.100 $70.000 $90.000 $80.000 $75.280 $74.000 $75.000
ELIM EXT PAV MRK & MRKS (WORD)
EA 5.000 $61.000 $80.000 $44.100 $70.000 $90.000 $84.000 $75.280 $74.000 $75.000
INSTL RDSD FLSH BCN ASSM (SOLAR PWRD)
EA 2.000 $7,000.000 $15,000.000 $7,300.000 $10,000.000 $9,000.000 $8,700.000 $8,000.000 $8,300.000 $8,300.000
REMOV RDSD FLSH BCN AM (SOLAR PWRD)
EA 2.000 $1,000.000 $1,600.000 $650.000 $700.000 $1,200.000 $1,300.000 $460.000 $740.000 $750.000
D-GR HMA TY-B PG64-22
TON 8,759.000 $68.000 $75.000 $76.000 $73.000 $72.000 $88.000 $75.000 $82.000 $93.500
D-GR HMA TY-D PG76-22
TON 3,113.000 $79.000 $90.000 $102.000 $96.000 $97.000 $120.000 $102.000 $110.000 $107.800
D-GR HMA TY-D SAC-B PG76-22
TON 113.000 $67.000 $90.000 $129.000 $135.000 $127.000 $150.000 $135.000 $145.000 $242.000
TACK COAT
GAL 5,260.000 $3.250 $2.980 $5.150 $5.000 $5.150 $5.500 $6.000 $5.800 $3.000
BONDING COURSE
GAL 407.000 $2.670 $7.400 $4.100 $3.950 $4.000 $5.000 $4.250 $4.600 $3.000
UNDERSEAL COURSE
GAL 18,671.000 $3.250 $3.200 $4.150 $4.000 $4.200 $5.000 $4.300 $4.650 $3.000
PORTABLE CHANGEABLE MESSAGE SIGN
EA 4.000 $10,000.000 $15,000.000 $10,700.000 $10,000.000 $30,000.000 $15,000.000 $22,000.000 $9,100.000 $20,250.000
TMA (STATIONARY)
DAY 270.000 $180.000 $120.000 $440.000 $175.000 $380.000 $180.000 $175.000 $170.000 $360.000
TMA (MOBILE OPERATION)
HR 150.000 $60.000 $40.000 $44.150 $60.000 $150.000 $170.000 $175.000 $97.000 $300.000
SUBSURFACE UTIL LOCATE (OUTSIDE RDBED)
EA 4.000 $2,500.000 $2,000.000 $3,150.000 $1,000.000 $4,500.000 $760.000 $2,200.000 $1,920.000 $6,000.000
Totals: $5,039,982.580 $5,760,579.270 $5,897,313.060 $6,041,968.710 $6,116,242.460 $6,427,951.870 $6,468,808.250 $6,578,517.250 $6,791,861.910