Job Info for 0015-17-028

County: WILLIAMSON Highway: SS 158 Date: 08/08/2018 (6 years ago) Engineer's Estimate: $951,493 Control Number: 0015-17-028
Project: STP 1802(542)HES District: AUSTIN Time: 50 WORKING DAYS Type: IMPROVE GUARDRAIL TO DESIGN STANDARDS

Bidders

Name Total Amount Place Over/Under Est Amt Left From Low Bid Delta Between Bidders
Engineer's Estimate $951,492.50
CHAMPION INFRASTRUCTURE, LLC   $1,181,685.00 1
24.19% | $230,192.50
DBI SERVICES, LLC   $1,267,363.75 2
33.2% | $315,871.25
7.25% | $85,678.75
3LW CIVIL LLC   $1,587,270.00 3
66.82% | $635,777.50
34.32% | $405,585.00
25.24% | $319,906.25

Bid Items

Items: 18, 0 filtered
WILLIAMSON SS 158  |  AUSTIN  |  0015-17-028  |  08/08/2018  |  $951,493  |  STP 1802(542)HES  |  IMPROVE GUARDRAIL TO DESIGN STANDARDS  |  50 WORKING DAYS
Item code Description Unit Quantity Engineer's Estimate CHAMPION INFRASTRUCTURE, LLC DBI SERVICES, LLC 3LW CIVIL LLC
134 6001 BACKFILL (TY A) STA 191.000 $135.000 $250.000 $410.000 $1,000.000
500 6001 MOBILIZATION LS 1.000 $74,600.000 $125,000.000 $105,000.000 $100,000.000
502 6001 BARRICADES, SIGNS AND TRAFFIC HANDLING MO 3.000 $7,500.000 $4,000.000 $2,200.000 $20,000.000
506 6038 TEMP SEDMT CONT FENCE (INSTALL) LF 500.000 $3.000 $5.000 $10.000 $3.750
506 6039 TEMP SEDMT CONT FENCE (REMOVE) LF 500.000 $1.000 $2.000 $5.000 $2.000
540 6001 MTL W-BEAM GD FEN (TIM POST) LF 17,675.000 $19.000 $21.000 $21.000 $30.000
540 6006 MTL BEAM GD FEN TRANS (THRIE-BEAM) EA 69.000 $1,300.000 $1,800.000 $2,150.000 $1,750.000
540 6009 MTL BEAM GD FEN TRANS (T6) EA 12.000 $700.000 $950.000 $810.000 $750.000
540 6014 SHORT RADIUS LF 300.000 $30.000 $32.000 $46.000 $40.000
540 6016 DOWNSTREAM ANCHOR TERMINAL SECTION EA 85.000 $1,100.000 $1,100.000 $1,250.000 $1,100.000
540 6020 MTL W - BEAM GD FEN (LOW FILL CULVERT) LF 137.500 $60.000 $240.000 $56.000 $100.000
542 6001 REMOVE METAL BEAM GUARD FENCE LF 17,175.000 $1.500 $2.000 $3.250 $5.000
542 6002 REMOVE TERMINAL ANCHOR SECTION EA 122.000 $105.000 $250.000 $225.000 $250.000
542 6004 RM MTL BM GD FENCE TRANS (THRIE-BEAM) EA 81.000 $200.000 $300.000 $450.000 $270.000
544 6001 GUARDRAIL END TREATMENT (INSTALL) EA 85.000 $2,300.000 $2,700.000 $2,750.000 $3,000.000
544 6003 GUARDRAIL END TREATMENT (REMOVE) EA 47.000 $200.000 $250.000 $450.000 $300.000
6001 6001 PORTABLE CHANGEABLE MESSAGE SIGN DAY 96.000 $85.000 $85.000 $265.000 $300.000
6185 6002 TMA (STATIONARY) DAY 60.000 $235.000 $200.000 $215.000 $300.000
Totals: $951,492.50 $1,181,685.00 $1,267,363.75 $1,587,270.00