PREPARING ROW
|
STA
|
170.250
|
$4,500.000
|
$800.000
|
$750.000
|
$5,000.000
|
$3,500.000
|
|
|
REMOVING CONC (DRIVEWAYS)
|
SY
|
98.000
|
$21.000
|
$20.000
|
$10.000
|
$100.000
|
$30.000
|
|
|
REMOVING STAB BASE AND ASPH PAV (0-4")
|
SY
|
1,086.000
|
$10.000
|
$2.000
|
$6.000
|
$3.000
|
$20.000
|
|
|
REMOVING STAB BASE & ASPH PAV (0-6")
|
SY
|
44,890.000
|
$20.000
|
$2.000
|
$5.000
|
$4.000
|
$8.000
|
|
|
REMOVING STAB BASE AND ASPH PAV (2"-8")
|
SY
|
1,933.000
|
$25.000
|
$2.000
|
$7.000
|
$5.000
|
$20.000
|
|
|
OBLITERATING ABANDONED ROAD
|
STA
|
21.000
|
$2,270.000
|
$250.000
|
$3,000.000
|
$3,000.000
|
$1,500.000
|
|
|
EXCAVATION (ROADWAY)
|
CY
|
29,255.000
|
$12.000
|
$4.000
|
$6.000
|
$8.000
|
$15.000
|
|
|
EXCAVATION (CHANNEL)
|
CY
|
232.000
|
$45.000
|
$12.000
|
$10.000
|
$25.000
|
$40.000
|
|
|
EMBANKMENT (FINAL)(DENS CONT)(TY C)
|
CY
|
5,296.000
|
$15.000
|
$10.000
|
$5.000
|
$12.000
|
$7.000
|
|
|
FURNISHING AND PLACING TOPSOIL (4")
|
SY
|
100,754.000
|
$5.500
|
$2.050
|
$2.000
|
$3.000
|
$0.710
|
|
|
CELL FBR MLCH SEED(PERM)(RURAL)(CLAY)
|
SY
|
98,432.000
|
$1.200
|
$0.500
|
$0.500
|
$0.750
|
$0.500
|
|
|
CELL FBR MLCH SEED(TEMP)(WARM)
|
SY
|
98,432.000
|
$1.600
|
$0.450
|
$0.500
|
$0.750
|
$0.450
|
|
|
VEGETATIVE WATERING
|
MG
|
1,637.000
|
$40.000
|
$30.000
|
$55.000
|
$20.000
|
$50.000
|
|
|
PROOF ROLLING
|
HR
|
8.000
|
$50.000
|
$80.000
|
$66.000
|
$50.000
|
$100.000
|
|
|
FL BS (RDWY DEL)(TY E GR 4)(FNAL POS)
|
CY
|
18,842.000
|
$40.000
|
$29.000
|
$40.000
|
$45.000
|
$63.000
|
|
|
LIME (HYDRATED LIME (SLURRY))
|
TON
|
1,131.000
|
$355.000
|
$236.000
|
$300.000
|
$330.000
|
$250.000
|
|
|
LIME TRT (EXST MATL) (12")
|
SY
|
64,040.000
|
$4.400
|
$2.600
|
$3.000
|
$5.000
|
$3.000
|
|
|
CEMENT
|
TON
|
688.000
|
$270.000
|
$190.000
|
$185.000
|
$230.000
|
$185.000
|
|
|
CEMENT TREAT (NEW BASE) (10")
|
SY
|
67,501.000
|
$2.800
|
$3.450
|
$3.000
|
$4.000
|
$3.250
|
|
|
PRIME COAT (MC-30)
|
GAL
|
13,252.000
|
$10.000
|
$4.750
|
$7.000
|
$6.000
|
$6.000
|
|
|
ASPH (TIER II)
|
GAL
|
19,479.000
|
$11.000
|
$6.500
|
$6.000
|
$6.000
|
$6.000
|
|
|
AGGR (TY-B GR-4P SAC-B)
|
CY
|
571.000
|
$70.000
|
$70.000
|
$149.000
|
$120.000
|
$175.000
|
|
|
STRUCT EXCAV (BOX)
|
CY
|
116.000
|
$11.000
|
$5.000
|
$66.000
|
$90.000
|
$125.000
|
|
|
CEM STABIL BKFL
|
CY
|
249.000
|
$120.000
|
$90.000
|
$64.000
|
$90.000
|
$125.000
|
|
|
STRUCT EXCAV (SPECIAL)
|
CY
|
59.000
|
$56.000
|
$70.000
|
$60.000
|
$90.000
|
$125.000
|
|
|
TRENCH EXCAVATION PROTECTION
|
LF
|
515.000
|
$10.000
|
$0.100
|
$9.000
|
$5.000
|
$5.000
|
|
|
TEMPORARY SPL SHORING
|
SF
|
6,350.000
|
$30.000
|
$0.100
|
$72.000
|
$25.000
|
$50.000
|
|
|
DRILL SHAFT (24 IN)
|
LF
|
1,250.000
|
$315.000
|
$280.000
|
$441.000
|
$500.000
|
$350.000
|
|
|
CL C CONC (ABUT)
|
CY
|
64.400
|
$1,500.000
|
$1,600.000
|
$1,019.000
|
$2,000.000
|
$2,300.000
|
|
|
CL C CONC (CAP)
|
CY
|
46.800
|
$2,000.000
|
$2,000.000
|
$2,742.000
|
$2,000.000
|
$2,900.000
|
|
|
CL C CONC (COLUMN)
|
CY
|
22.000
|
$2,450.000
|
$3,000.000
|
$2,704.000
|
$2,000.000
|
$2,900.000
|
|
|
REINF CONC SLAB (SLAB BEAM)
|
SF
|
8,970.000
|
$33.000
|
$18.000
|
$45.000
|
$45.000
|
$60.000
|
|
|
PRESTR CONC SLAB BEAM (5SB12)
|
LF
|
1,727.680
|
$400.000
|
$200.000
|
$315.000
|
$500.000
|
$475.000
|
|
|
RIPRAP (STONE PROTECTION)(12 IN)
|
CY
|
140.000
|
$230.000
|
$275.000
|
$188.000
|
$300.000
|
$275.000
|
|
|
RIPRAP (MOW STRIP)(4 IN)
|
CY
|
107.000
|
$600.000
|
$400.000
|
$774.000
|
$600.000
|
$750.000
|
|
|
RAIL (TY SSTR)
|
LF
|
438.000
|
$170.000
|
$120.000
|
$196.000
|
$200.000
|
$350.000
|
|
|
SEALED EXPANSION JOINT (4 IN) (SEJ - B)
|
LF
|
186.000
|
$175.000
|
$175.000
|
$163.000
|
$210.000
|
$200.000
|
|
|
CONC BOX CULV (5 FT X 2 FT)
|
LF
|
68.000
|
$528.000
|
$400.000
|
$709.000
|
$500.000
|
$650.000
|
|
|
RC PIPE (CL III)(18 IN)
|
LF
|
432.000
|
$100.000
|
$65.000
|
$71.000
|
$60.000
|
$113.000
|
|
|
RC PIPE (CL III)(24 IN)
|
LF
|
805.000
|
$120.000
|
$85.000
|
$86.000
|
$85.000
|
$130.000
|
|
|
RC PIPE (CL III)(36 IN)
|
LF
|
102.000
|
$190.000
|
$160.000
|
$234.000
|
$160.000
|
$330.000
|
|
|
WINGWALL (PW - 1) (HW=3 FT)
|
EA
|
2.000
|
$12,500.000
|
$9,000.000
|
$12,940.000
|
$20,000.000
|
$29,750.000
|
|
|
SET (TY II) (18 IN) (RCP) (3: 1) (C)
|
EA
|
2.000
|
$1,447.000
|
$1,000.000
|
$1,285.000
|
$1,400.000
|
$1,900.000
|
|
|
SET (TY II) (18 IN) (RCP) (4: 1) (C)
|
EA
|
4.000
|
$1,450.000
|
$1,000.000
|
$1,345.000
|
$1,500.000
|
$1,900.000
|
|
|
SET (TY II) (18 IN) (RCP) (6: 1) (P)
|
EA
|
23.000
|
$1,450.000
|
$1,150.000
|
$1,509.000
|
$1,600.000
|
$1,900.000
|
|
|
SET (TY II) (24 IN) (RCP) (3: 1) (C)
|
EA
|
10.000
|
$1,942.000
|
$1,300.000
|
$1,896.000
|
$1,800.000
|
$2,100.000
|
|
|
SET (TY II) (24 IN) (RCP) (4: 1) (C)
|
EA
|
2.000
|
$2,100.000
|
$1,300.000
|
$1,561.000
|
$1,900.000
|
$2,200.000
|
|
|
SET (TY II) (24 IN) (RCP) (6: 1) (P)
|
EA
|
4.000
|
$2,100.000
|
$1,650.000
|
$1,680.000
|
$2,000.000
|
$2,500.000
|
|
|
REMOV STR (SET)
|
EA
|
12.000
|
$400.000
|
$300.000
|
$400.000
|
$175.000
|
$775.000
|
|
|
REMOV STR (PIPE)
|
LF
|
1,380.000
|
$15.000
|
$10.000
|
$10.000
|
$7.000
|
$15.000
|
|
|
REMOV STR (BRIDGE 0 - 99 FT LENGTH)
|
EA
|
2.000
|
$48,000.000
|
$50,000.000
|
$50,000.000
|
$20,000.000
|
$100.000
|
|
|
MOBILIZATION
|
LS
|
1.000
|
$950,026.450
|
$500,000.000
|
$700,000.000
|
$1,000,000.000
|
$1,000,000.000
|
|
|
BARRICADES, SIGNS AND TRAFFIC HANDLING
|
MO
|
8.000
|
$6,875.000
|
$5,300.000
|
$8,500.000
|
$8,000.000
|
$4,000.000
|
|
|
CONSTRUCTION EXITS (INSTALL) (TY 1)
|
SY
|
156.000
|
$35.000
|
$30.000
|
$20.000
|
$50.000
|
$35.000
|
|
|
CONSTRUCTION EXITS (REMOVE)
|
SY
|
156.000
|
$12.000
|
$12.000
|
$8.000
|
$10.000
|
$10.000
|
|
|
TEMP SEDMT CONT FENCE (INSTALL)
|
LF
|
34,185.000
|
$5.000
|
$4.250
|
$4.000
|
$6.000
|
$4.250
|
|
|
TEMP SEDMT CONT FENCE (REMOVE)
|
LF
|
34,185.000
|
$2.000
|
$1.400
|
$1.000
|
$1.000
|
$1.250
|
|
|
BIODEG EROSN CONT LOGS (INSTL) (12")
|
LF
|
771.000
|
$6.000
|
$6.000
|
$6.000
|
$6.000
|
$6.150
|
|
|
BIODEG EROSN CONT LOGS (REMOVE)
|
LF
|
771.000
|
$2.500
|
$1.500
|
$1.000
|
$1.000
|
$1.350
|
|
|
ONE-WAY TRAF CONT (PORT TRAF SIG)
|
MO
|
1.000
|
$5,680.000
|
$7,400.000
|
$42,400.000
|
$20,000.000
|
$15,000.000
|
|
|
DRIVEWAYS (CONC)
|
SY
|
98.000
|
$90.000
|
$97.000
|
$100.000
|
$90.000
|
$200.000
|
|
|
DRIVEWAYS (ACP)
|
SY
|
1,222.000
|
$83.000
|
$38.000
|
$38.000
|
$60.000
|
$55.000
|
|
|
DRIVEWAYS (BASE)
|
SY
|
1,299.000
|
$70.000
|
$18.000
|
$9.000
|
$30.000
|
$15.000
|
|
|
MTL W-BEAM GD FEN (STEEL POST)
|
LF
|
1,075.000
|
$90.000
|
$35.000
|
$35.000
|
$40.000
|
$34.600
|
|
|
MTL BEAM GD FEN TRANS (THRIE-BEAM)
|
EA
|
4.000
|
$2,300.000
|
$2,500.000
|
$2,440.000
|
$3,000.000
|
$2,440.000
|
|
|
REMOVE METAL BEAM GUARD FENCE
|
LF
|
962.000
|
$4.000
|
$4.000
|
$4.000
|
$3.000
|
$3.500
|
|
|
REMOVE TERMINAL ANCHOR SECTION
|
EA
|
6.000
|
$250.000
|
$250.000
|
$250.000
|
$1,000.000
|
$250.000
|
|
|
GUARDRAIL END TREATMENT (INSTALL)
|
EA
|
12.000
|
$3,300.000
|
$3,450.000
|
$3,440.000
|
$4,000.000
|
$3,440.000
|
|
|
GUARDRAIL END TREATMENT (REMOVE)
|
EA
|
4.000
|
$320.000
|
$250.000
|
$250.000
|
$1,000.000
|
$250.000
|
|
|
CRASH CUSHION ATTEN (INSTALL) (QUAD)(N)
|
EA
|
4.000
|
$25,000.000
|
$32,000.000
|
$26,100.000
|
$25,000.000
|
$26,100.000
|
|
|
RELOCATE EXISTING MAILBOX
|
EA
|
5.000
|
$300.000
|
$500.000
|
$453.000
|
$100.000
|
$500.000
|
|
|
IN SM RD SN SUP&AM TYS80(1)SA(P)
|
EA
|
14.000
|
$800.000
|
$950.000
|
$629.000
|
$700.000
|
$950.000
|
|
|
IN SM RD SN SUP&AM TYS80(1)SA(P-BM)
|
EA
|
6.000
|
$850.000
|
$1,350.000
|
$1,278.000
|
$800.000
|
$1,350.000
|
|
|
IN SM RD SN SUP&AM TYS80(1)SA(T)
|
EA
|
7.000
|
$1,125.000
|
$1,350.000
|
$1,327.000
|
$1,000.000
|
$1,350.000
|
|
|
IN SM RD SN SUP&AM TYS80(1)SA(U)
|
EA
|
2.000
|
$1,200.000
|
$500.000
|
$1,579.000
|
$1,300.000
|
$500.000
|
|
|
REMOVE SM RD SN SUP&AM (SIGN ONLY)
|
EA
|
33.000
|
$120.000
|
$125.000
|
$119.000
|
$75.000
|
$250.000
|
|
|
INSTL DEL ASSM (D-SW)SZ (BRF)CTB (BI)
|
EA
|
14.000
|
$32.000
|
$20.000
|
$28.000
|
$100.000
|
$20.000
|
|
|
INSTL DEL ASSM (D-SW)SZ 1(BRF)GF2(BI)
|
EA
|
21.000
|
$30.000
|
$30.000
|
$52.000
|
$1,000.000
|
$30.000
|
|
|
WK ZN PAV MRK REMOV (REFL) TY II-A-A
|
EA
|
285.000
|
$4.000
|
$5.000
|
$4.000
|
$0.500
|
$3.800
|
|
|
WK ZN PAV MRK REMOV (W)4"(SLD)
|
LF
|
4,785.000
|
$1.000
|
$0.700
|
$0.500
|
$0.500
|
$0.700
|
|
|
WK ZN PAV MRK REMOV (W)24"(SLD)
|
LF
|
36.000
|
$10.000
|
$11.000
|
$13.000
|
$8.000
|
$12.800
|
|
|
WK ZN PAV MRK REMOV (Y)4"(SLD)
|
LF
|
11,400.000
|
$1.000
|
$0.700
|
$0.500
|
$0.500
|
$0.650
|
|
REFL PAV MRK TY I (W)24"(SLD)(100MIL)
|
LF
|
58.000
|
$7.800
|
$11.000
|
$13.000
|
$6.500
|
$12.800
|
|
RE PM W/RET REQ TY I (Y)6"(BRK)(100MIL)
|
LF
|
12,995.000
|
$1.000
|
$0.750
|
$0.500
|
$1.000
|
$0.650
|
|
RE PM W/RET REQ TY I (Y)6"(SLD)(100MIL)
|
LF
|
9,577.000
|
$0.920
|
$0.750
|
$0.500
|
$1.000
|
$0.650
|
|
|
REF PROF PAV MRK TY I(W)6"(SLD)(100MIL)
|
LF
|
34,220.000
|
$1.180
|
$0.800
|
$1.000
|
$1.200
|
$0.950
|
|
PREFAB PAV MRK TY C (W) (ARROW)
|
EA
|
1.000
|
$240.000
|
$200.000
|
$291.000
|
$400.000
|
$280.000
|
|
REFL PAV MRKR TY II-A-A
|
EA
|
287.000
|
$6.910
|
$5.000
|
$4.000
|
$4.000
|
$3.400
|
|
TRAFFIC BUTTON TY Y
|
EA
|
2,303.000
|
$2.400
|
$3.500
|
$2.000
|
$1.200
|
$2.200
|
|
TRAFFIC BUTTON TY B
|
EA
|
3,536.000
|
$2.400
|
$3.500
|
$2.000
|
$1.200
|
$2.200
|
|
|
REPLACE OF SPAN CABLE ASSM
|
LF
|
150.000
|
$5.000
|
$4.000
|
$7.000
|
$100.000
|
$100.000
|
|
|
PRSSR IRRIG PVC PIPE (18")
|
LF
|
335.000
|
$159.000
|
$250.000
|
$102.000
|
$90.000
|
$190.000
|
|
|
PRSSR IRRIG PVC PIPE (24")
|
LF
|
102.000
|
$237.000
|
$480.000
|
$151.000
|
$110.000
|
$290.000
|
|
|
SP MIXES SP-D SAC-A PG76-22
|
TON
|
5,685.000
|
$135.000
|
$113.000
|
$125.000
|
$130.000
|
$190.000
|
|
|
TACK COAT
|
GAL
|
244.000
|
$4.000
|
$5.000
|
$8.000
|
$6.000
|
$9.500
|
|
|
PORTABLE CHANGEABLE MESSAGE SIGN
|
DAY
|
28.000
|
$80.000
|
$390.000
|
$75.000
|
$250.000
|
$500.000
|
|
Totals: |
$10,477,790.960
|
$5,944,074.300
|
$7,924,749.400
|
$9,650,102.800
|
$10,200,565.090
|