PREPARING ROW
|
STA
|
130.000
|
$1,200.000
|
$1,900.000
|
$1,925.000
|
$315.530
|
|
|
REMOVING CONC (PAV)
|
SY
|
2,179.000
|
$5.000
|
$5.500
|
$5.000
|
$9.420
|
|
|
REMOV STAB BASE AND ASPH PAV (10"-18")
|
SY
|
41,329.000
|
$4.000
|
$1.750
|
$2.000
|
$9.260
|
|
|
EXCAVATION (ROADWAY)
|
CY
|
26,481.000
|
$4.000
|
$4.200
|
$2.000
|
$6.990
|
|
|
EMBANKMENT (FINAL)(DENS CONT)(TY C)
|
CY
|
166,506.000
|
$5.000
|
$5.800
|
$4.000
|
$17.420
|
|
|
BACKFILL (TY A)
|
STA
|
187.000
|
$140.000
|
$145.000
|
$200.000
|
$217.240
|
|
|
FURNISHING AND PLACING TOPSOIL
|
CY
|
100.000
|
$25.000
|
$19.000
|
$15.000
|
$35.530
|
|
|
DRILL SEEDING (PERM) (RURAL) (SANDY)
|
SY
|
320,000.000
|
$0.250
|
$0.200
|
$0.140
|
$0.160
|
|
|
DRILL SEEDING (TEMP) (WARM)
|
SY
|
160,000.000
|
$0.250
|
$0.180
|
$0.120
|
$0.150
|
|
|
DRILL SEEDING (TEMP) (COOL)
|
SY
|
160,000.000
|
$0.250
|
$0.180
|
$0.120
|
$0.150
|
|
|
VEGETATIVE WATERING
|
MG
|
365.000
|
$15.000
|
$25.000
|
$20.000
|
$11.810
|
|
|
SOIL RETENTION BLANKETS (CL 1) (TY B)
|
SY
|
5,000.000
|
$2.500
|
$2.000
|
$0.860
|
$1.510
|
|
|
SOIL RETENTION BLANKETS (CL 1) (TY D)
|
SY
|
5,000.000
|
$2.500
|
$2.000
|
$0.880
|
$1.750
|
|
|
PLANT MATERIAL (MIN 12' TRNK HT) (PALM)
|
EA
|
3.000
|
$750.000
|
$750.000
|
$654.500
|
$595.000
|
|
|
PLANT MAINTENANCE
|
MO
|
24.000
|
$3,000.000
|
$700.000
|
$700.000
|
$975.000
|
|
|
VEGETATIVE WATERING
|
MG
|
80.000
|
$35.000
|
$35.000
|
$35.000
|
$11.820
|
|
|
FL BS (RDWY DEL)(TY E GR 4)(FNAL POS)
|
CY
|
35,480.000
|
$22.000
|
$19.750
|
$23.000
|
$28.390
|
|
|
CEMENT
|
TON
|
2,718.000
|
$160.000
|
$152.000
|
$165.000
|
$173.230
|
|
|
CEMENT TREAT (NEW BASE) (10")
|
SY
|
21,946.000
|
$1.250
|
$1.800
|
$1.600
|
$2.150
|
|
|
CEMENT TREAT (NEW BASE 14")
|
SY
|
75,510.000
|
$2.000
|
$2.350
|
$1.800
|
$2.840
|
|
|
CEMENT TREAT (SUBGRADE)(12")
|
SY
|
100,639.000
|
$1.750
|
$2.250
|
$1.800
|
$1.860
|
|
|
PRIME COAT (MC-30)
|
GAL
|
18,483.000
|
$3.500
|
$3.250
|
$3.400
|
$4.290
|
|
|
ASPH (TIER II)
|
GAL
|
6,090.000
|
$4.500
|
$4.500
|
$3.000
|
$2.440
|
|
|
AGGR (GR 4P)
|
CY
|
176.000
|
$110.000
|
$45.000
|
$75.000
|
$113.990
|
|
|
D-GR HMA TY-D SAC-A PG76-22
|
TON
|
1,691.000
|
$76.000
|
$88.000
|
$85.000
|
$94.280
|
|
|
D-GR HMA TY-D SAC-A PG76-22
|
TON
|
852.000
|
$76.000
|
$88.000
|
$85.000
|
$98.670
|
|
|
D-GR HMA TY B SAC-B PG (64-22)
|
TON
|
7,630.000
|
$72.000
|
$61.000
|
$78.000
|
$72.550
|
|
|
D-GR HMA TY B SAC-B PG (64-22)
|
TON
|
6,642.000
|
$74.000
|
$61.000
|
$78.000
|
$72.840
|
|
|
STONE-MTRX-ASPH SMA-D SAC-A PG76-22
|
TON
|
16,669.000
|
$82.000
|
$90.000
|
$100.000
|
$101.080
|
|
|
STONE-MTRX-ASPH SMA-D SAC-B PG76-22
|
TON
|
10,027.000
|
$82.000
|
$82.000
|
$97.000
|
$97.520
|
|
|
PLANE ASPH CONC PAV(0" TO 1")
|
SY
|
1,160.000
|
$1.500
|
$13.000
|
$2.000
|
$8.760
|
|
|
PLANE ASPH CONC PAV(0" TO 2")
|
SY
|
1,118.000
|
$4.000
|
$15.000
|
$3.000
|
$9.130
|
|
|
PLANE ASPH CONC PAV (2")
|
SY
|
41,329.000
|
$2.000
|
$1.000
|
$1.000
|
$1.860
|
|
|
PLANE ASPH CONC PAV (0" TO 1 1/2")
|
SY
|
106.000
|
$2.000
|
$34.000
|
$25.000
|
$80.180
|
|
|
CEM STABIL BKFL
|
CY
|
206.000
|
$60.000
|
$40.000
|
$60.000
|
$45.120
|
|
|
CEM STABIL BKFL
|
CY
|
475.000
|
$60.000
|
$70.000
|
$60.000
|
$64.120
|
|
|
CUT & RESTORING PAV
|
SY
|
426.000
|
$70.000
|
$55.000
|
$85.000
|
$72.080
|
|
|
TRENCH EXCAVATION PROTECTION
|
LF
|
656.000
|
$2.000
|
$4.000
|
$0.100
|
$5.150
|
|
|
DRILL SHAFT (36 IN)
|
LF
|
1,440.000
|
$150.000
|
$225.000
|
$200.000
|
$252.690
|
|
|
DRILL SHAFT (NON - REINFORCED) (12 IN)
|
LF
|
16.000
|
$125.000
|
$65.000
|
$66.990
|
$150.000
|
|
|
DRILL SHAFT (SIGN MTS) (24 IN)
|
LF
|
96.000
|
$200.000
|
$145.000
|
$149.430
|
$220.000
|
|
|
DRILL SHAFT (RDWY ILL POLE) (30 IN)
|
LF
|
210.000
|
$200.000
|
$185.000
|
$190.660
|
$250.000
|
|
|
CL B CONC (MISC)
|
CY
|
3.200
|
$220.000
|
$450.000
|
$700.000
|
$1,000.000
|
|
|
CL C CONC (ABUT)
|
CY
|
108.800
|
$900.000
|
$1,100.000
|
$850.000
|
$1,258.000
|
|
|
CL C CONC (CAP)
|
CY
|
68.200
|
$1,100.000
|
$1,200.000
|
$1,500.000
|
$1,314.000
|
|
|
CL C CONC (COLUMN)
|
CY
|
53.400
|
$910.000
|
$900.000
|
$1,300.000
|
$1,210.000
|
|
|
REINF CONC SLAB
|
SF
|
15,600.000
|
$18.000
|
$15.000
|
$18.000
|
$12.000
|
|
|
APPROACH SLAB
|
CY
|
139.400
|
$475.000
|
$500.000
|
$550.000
|
$467.000
|
|
|
RETAINING WALL (MSE)
|
SF
|
73,851.000
|
$42.000
|
$52.500
|
$50.000
|
$30.000
|
|
|
PRESTR CONC GIRDER (TX28)
|
LF
|
1,935.000
|
$125.000
|
$150.000
|
$125.000
|
$274.000
|
|
|
RIPRAP (CONC)(5 IN)
|
CY
|
558.000
|
$375.000
|
$305.000
|
$325.000
|
$450.000
|
|
|
RIPRAP (STONE PROTECTION)(18 IN)
|
CY
|
206.000
|
$165.000
|
$150.000
|
$150.000
|
$74.030
|
|
|
RIPRAP (MOW STRIP)(4 IN)
|
CY
|
264.200
|
$450.000
|
$305.000
|
$350.000
|
$450.000
|
|
|
RAIL (TY SSTR)
|
LF
|
5,691.300
|
$40.000
|
$55.750
|
$40.000
|
$50.000
|
|
|
SEALED EXPANSION JOINT (4 IN) (SEJ - A)
|
LF
|
158.000
|
$100.000
|
$100.000
|
$85.000
|
$184.150
|
|
|
CONC BOX CULV (4 FT X 2 FT)
|
LF
|
478.000
|
$180.000
|
$260.000
|
$200.000
|
$192.000
|
|
|
RC PIPE (CL III)(18 IN)
|
LF
|
1,081.000
|
$40.000
|
$27.000
|
$47.000
|
$31.000
|
|
|
RC PIPE (CL III)(24 IN)
|
LF
|
788.000
|
$60.000
|
$36.000
|
$50.000
|
$55.000
|
|
|
RC PIPE (CL III)(30 IN)
|
LF
|
267.000
|
$90.000
|
$51.000
|
$55.000
|
$70.000
|
|
|
RC PIPE (CL V)(18 IN)
|
LF
|
128.000
|
$70.000
|
$36.000
|
$50.000
|
$90.000
|
|
|
INLET (COMPL)(POD)(FG)(4FTX4FT)
|
EA
|
22.000
|
$330.000
|
$4,175.000
|
$2,750.000
|
$3,020.000
|
|
|
INLET (COMPL)(PSL)(FG)(3FTX3FT-3FTX3FT)
|
EA
|
7.000
|
$4,000.000
|
$3,700.000
|
$2,700.000
|
$2,330.000
|
|
|
SET (TY I)(S=3 FT)(HW=3FT)(3:1)(C)
|
EA
|
1.000
|
$10,000.000
|
$7,700.000
|
$2,500.000
|
$2,000.000
|
|
|
SET (TY I)(S= 4 FT)(HW= 3 FT)(4:1) (C)
|
EA
|
2.000
|
$4,300.000
|
$8,600.000
|
$2,500.000
|
$2,000.000
|
|
|
SET (TY II) (18 IN) (RCP) (3: 1) (C)
|
EA
|
2.000
|
$1,000.000
|
$750.000
|
$680.000
|
$815.000
|
|
|
SET (TY II) (18 IN) (RCP) (4: 1) (C)
|
EA
|
46.000
|
$1,000.000
|
$750.000
|
$680.000
|
$815.000
|
|
|
SET (TY II) (18 IN) (RCP) (6: 1) (C)
|
EA
|
2.000
|
$1,200.000
|
$825.000
|
$750.000
|
$880.000
|
|
|
SET (TY II) (24 IN) (RCP) (3: 1) (C)
|
EA
|
2.000
|
$1,000.000
|
$950.000
|
$950.000
|
$1,105.000
|
|
|
SET (TY II) (24 IN) (RCP) (4: 1) (C)
|
EA
|
2.000
|
$1,100.000
|
$950.000
|
$950.000
|
$1,110.000
|
|
|
SET (TY II) (24 IN) (RCP) (6: 1) (C)
|
EA
|
8.000
|
$1,400.000
|
$985.000
|
$1,100.000
|
$1,270.000
|
|
|
SET (TY II) (30 IN) (RCP) (3: 1) (C)
|
EA
|
3.000
|
$1,400.000
|
$1,450.000
|
$1,300.000
|
$1,500.000
|
|
|
SET (TY II) (30 IN) (RCP) (4: 1) (C)
|
EA
|
3.000
|
$1,400.000
|
$1,450.000
|
$1,300.000
|
$1,500.000
|
|
|
REMOV STR (INLET)
|
EA
|
2.000
|
$900.000
|
$350.000
|
$500.000
|
$525.000
|
|
|
REMOV STR (SET)
|
EA
|
24.000
|
$500.000
|
$185.000
|
$250.000
|
$175.000
|
|
|
REMOV STR (PIPE)
|
LF
|
1,156.000
|
$18.000
|
$7.000
|
$5.000
|
$4.000
|
|
|
MOBILIZATION
|
LS
|
1.000
|
$925,000.000
|
$700,000.000
|
$1,500,000.000
|
$836,265.490
|
|
|
BARRICADES, SIGNS AND TRAFFIC HANDLING
|
MO
|
15.000
|
$7,500.000
|
$3,500.000
|
$2,500.000
|
$10,322.660
|
|
|
ROCK FILTER DAMS (INSTALL) (TY 2)
|
LF
|
340.000
|
$43.000
|
$60.000
|
$25.000
|
$58.870
|
|
|
ROCK FILTER DAMS (REMOVE)
|
LF
|
340.000
|
$12.000
|
$20.000
|
$10.000
|
$33.430
|
|
|
CONSTRUCTION EXITS (INSTALL) (TY 1)
|
SY
|
1,360.000
|
$20.000
|
$18.000
|
$10.000
|
$27.980
|
|
|
CONSTRUCTION EXITS (REMOVE)
|
SY
|
1,360.000
|
$8.000
|
$10.000
|
$1.000
|
$11.410
|
|
|
TEMP SEDMT CONT FENCE (INSTALL)
|
LF
|
21,201.000
|
$2.500
|
$2.500
|
$2.000
|
$3.400
|
|
|
TEMP SEDMT CONT FENCE (REMOVE)
|
LF
|
21,201.000
|
$1.000
|
$0.500
|
$0.250
|
$1.220
|
|
|
BIODEG EROSN CONT LOGS (INSTL) (12")
|
LF
|
1,450.000
|
$2.500
|
$4.500
|
$3.750
|
$4.080
|
|
|
BIODEG EROSN CONT LOGS (REMOVE)
|
LF
|
1,450.000
|
$1.000
|
$0.500
|
$0.500
|
$1.970
|
|
|
CONSTRUCTING DETOURS
|
SY
|
3,568.000
|
$40.000
|
$58.000
|
$23.000
|
$66.650
|
|
|
PORT CTB (FUR & INST)(F-SHAPE)(TY 1)
|
LF
|
15,570.000
|
$30.000
|
$22.000
|
$45.000
|
$20.720
|
|
|
PORT CTB (MOVE)(F-SHAPE)(TY 1)
|
LF
|
31,710.000
|
$4.500
|
$4.000
|
$4.000
|
$8.910
|
|
|
PORT CTB (REMOVE)(F-SHAPE)(TY 1)
|
LF
|
15,570.000
|
$6.000
|
$8.000
|
$5.000
|
$8.460
|
|
|
DRIVEWAYS (ACP)
|
SY
|
106.000
|
$25.000
|
$48.000
|
$60.000
|
$64.090
|
|
|
RUMBLE STRIPS (SHOULDER)
|
LF
|
42,173.000
|
$0.500
|
$0.300
|
$0.180
|
$0.210
|
|
|
MTL W-BEAM GD FEN (TIM POST)
|
LF
|
1,662.500
|
$25.000
|
$22.000
|
$20.000
|
$23.500
|
|
|
MTL BEAM GD FEN TRANS (THRIE-BEAM)
|
EA
|
4.000
|
$1,700.000
|
$1,600.000
|
$1,500.000
|
$1,630.000
|
|
|
DOWNSTREAM ANCHOR TERMINAL SECTION
|
EA
|
8.000
|
$1,200.000
|
$1,400.000
|
$950.000
|
$975.000
|
|
|
GUARDRAIL END TREATMENT (INSTALL)
|
EA
|
12.000
|
$2,250.000
|
$2,750.000
|
$2,600.000
|
$2,670.000
|
|
|
CRASH CUSH ATTEN (INSTL)
|
EA
|
7.000
|
$15,000.000
|
$15,000.000
|
$16,000.000
|
$4,562.120
|
|
|
CRASH CUSH ATTEN (MOVE & RESET)
|
EA
|
11.000
|
$1,900.000
|
$2,500.000
|
$1,500.000
|
$1,273.050
|
|
|
CRASH CUSH ATTEN (REMOVE)
|
EA
|
7.000
|
$1,000.000
|
$1,000.000
|
$500.000
|
$578.660
|
|
|
CHAIN LINK FENCE (INSTALL) (6')
|
LF
|
80.000
|
$25.000
|
$25.000
|
$50.000
|
$40.000
|
|
|
IN RD IL (U/P) (TY 1) (150W EQ) LED
|
EA
|
8.000
|
$1,400.000
|
$1,250.000
|
$1,288.270
|
$1,700.000
|
|
|
IN RD IL (TY SA) 40T-8 (250W EQ) LED
|
EA
|
21.000
|
$2,400.000
|
$2,800.000
|
$2,885.720
|
$2,900.000
|
|
|
CONDT (PVC) (SCH 40) (2")
|
LF
|
3,875.000
|
$8.000
|
$6.000
|
$6.180
|
$9.500
|
|
|
CONDT (RM) (3/4")
|
LF
|
60.000
|
$20.000
|
$16.000
|
$16.490
|
$22.000
|
|
|
CONDT (RM) (1")
|
LF
|
155.000
|
$30.000
|
$18.000
|
$18.550
|
$23.000
|
|
|
ELEC CONDR (NO.12) BARE
|
LF
|
60.000
|
$2.000
|
$1.200
|
$1.240
|
$1.550
|
|
|
ELEC CONDR (NO.12) INSULATED
|
LF
|
120.000
|
$2.000
|
$1.200
|
$1.240
|
$1.550
|
|
|
ELEC CONDR (NO.8) BARE
|
LF
|
3,965.000
|
$2.000
|
$1.600
|
$1.650
|
$1.500
|
|
|
ELEC CONDR (NO.8) INSULATED
|
LF
|
8,250.000
|
$2.000
|
$1.700
|
$1.750
|
$1.500
|
|
|
GROUND BOX TY A (122311)W/APRON
|
EA
|
16.000
|
$1,200.000
|
$780.000
|
$803.880
|
$920.000
|
|
|
ELC SRV TY A 240/480 060(NS)SS(E)GC(O)
|
EA
|
5.000
|
$5,000.000
|
$5,400.000
|
$5,564.920
|
$7,300.000
|
|
|
ALUMINUM SIGNS (TY G)
|
SF
|
1,077.000
|
$25.000
|
$25.000
|
$22.000
|
$22.000
|
|
|
IN SM RD SN SUP&AM TYS80(1)SA(P)
|
EA
|
19.000
|
$500.000
|
$400.000
|
$450.000
|
$575.000
|
|
|
IN SM RD SN SUP&AM TYS80(1)SA(P-BM)
|
EA
|
5.000
|
$1,000.000
|
$690.000
|
$600.000
|
$725.000
|
|
|
IN SM RD SN SUP&AM TYS80(1)SA(T)
|
EA
|
20.000
|
$750.000
|
$650.000
|
$550.000
|
$725.000
|
|
|
IN SM RD SN SUP&AM TYS80(1)SA(U-2EXT)
|
EA
|
4.000
|
$1,000.000
|
$1,100.000
|
$900.000
|
$1,215.000
|
|
|
IN BRIDGE MNT CLEARANCE SGN ASSM(TY N)
|
EA
|
4.000
|
$1,800.000
|
$4,600.000
|
$1,850.000
|
$1,595.000
|
|
|
IN SM RD SN SUP&AM (RAIL MOUNT)
|
EA
|
2.000
|
$3,450.000
|
$6,000.000
|
$3,000.000
|
$2,980.000
|
|
|
REMOVE SM RD SN SUP&AM
|
EA
|
33.000
|
$90.000
|
$50.000
|
$50.000
|
$85.000
|
|
|
INSTL DEL ASSM (D-SW)SZ 1(FLX)GND
|
EA
|
92.000
|
$60.000
|
$44.000
|
$50.000
|
$49.000
|
|
|
INSTL DEL ASSM (D-SW)SZ (BRF)GF1 (BR)
|
EA
|
10.000
|
$60.000
|
$22.000
|
$35.000
|
$35.000
|
|
|
INSTL DEL ASSM (D-SY)SZ (BRF)GF1 (BR)
|
EA
|
26.000
|
$60.000
|
$23.000
|
$35.000
|
$35.000
|
|
|
INSTL OM ASSM (OM-2Z)(FLX)GND
|
EA
|
17.000
|
$60.000
|
$39.000
|
$50.000
|
$50.000
|
|
|
WK ZN PAV MRK NON-REMOV (W)4"(BRK)
|
LF
|
4,644.000
|
$0.500
|
$0.480
|
$0.450
|
$0.450
|
|
|
WK ZN PAV MRK NON-REMOV (W)4"(SLD)
|
LF
|
33,065.000
|
$0.500
|
$0.420
|
$0.400
|
$0.400
|
|
|
WK ZN PAV MRK NON-REMOV (W)8"(SLD)
|
LF
|
2,098.000
|
$1.000
|
$1.000
|
$1.000
|
$1.000
|
|
|
WK ZN PAV MRK NON-REMOV (W)24"(SLD)
|
LF
|
32.000
|
$5.000
|
$3.000
|
$3.000
|
$3.000
|
|
|
WK ZN PAV MRK NON-REMOV (Y)4"(SLD)
|
LF
|
30,762.000
|
$0.500
|
$0.450
|
$0.400
|
$0.400
|
|
|
WK ZN PAV MRK REMOV (W)4"(BRK)
|
LF
|
1,835.000
|
$0.500
|
$0.600
|
$0.600
|
$0.600
|
|
|
WK ZN PAV MRK REMOV (W)4"(DOT)
|
LF
|
380.000
|
$1.500
|
$0.600
|
$0.600
|
$0.600
|
|
|
WK ZN PAV MRK REMOV (W)4"(SLD)
|
LF
|
24,556.000
|
$0.600
|
$0.600
|
$0.550
|
$0.550
|
|
|
WK ZN PAV MRK REMOV (W)8"(SLD)
|
LF
|
1,982.000
|
$2.000
|
$1.300
|
$1.250
|
$1.250
|
|
|
WK ZN PAV MRK REMOV (Y)4"(SLD)
|
LF
|
25,131.000
|
$0.750
|
$0.600
|
$0.550
|
$0.550
|
|
WK ZN PAV MRK SHT TERM (TAB)TY W
|
EA
|
2,847.000
|
$0.750
|
$1.000
|
$1.000
|
$1.110
|
|
WK ZN PAV MRK SHT TERM (TAB)TY Y-2
|
EA
|
1,937.000
|
$0.750
|
$1.000
|
$1.000
|
$1.060
|
|
REFL PAV MRK TY I (W)4"(DOT)(100MIL)
|
LF
|
900.000
|
$0.750
|
$0.400
|
$0.400
|
$0.400
|
|
REFL PAV MRK TY I (W)8"(SLD)(100MIL)
|
LF
|
2,737.000
|
$0.650
|
$0.900
|
$0.850
|
$0.850
|
|
REFL PAV MRK TY I (W)24"(SLD)(100MIL)
|
LF
|
84.000
|
$2.500
|
$4.000
|
$4.000
|
$4.000
|
|
|
PAVEMENT SEALER 4"
|
LF
|
48,289.000
|
$0.500
|
$0.150
|
$0.120
|
$0.120
|
|
|
PAVEMENT SEALER 8"
|
LF
|
2,737.000
|
$0.500
|
$0.250
|
$0.240
|
$0.240
|
|
|
PAVEMENT SEALER 24"
|
LF
|
84.000
|
$2.000
|
$0.800
|
$0.720
|
$0.720
|
|
RE PM W/RET REQ TY I (W)4"(BRK)(100MIL)
|
LF
|
8,440.000
|
$0.500
|
$0.400
|
$0.380
|
$0.380
|
|
RE PM W/RET REQ TY I (W)4"(SLD)(100MIL)
|
LF
|
38,949.000
|
$0.500
|
$0.400
|
$0.380
|
$0.380
|
|
RE PM W/RET REQ TY I (Y)4"(SLD)(100MIL)
|
LF
|
38,833.000
|
$0.500
|
$0.400
|
$0.380
|
$0.380
|
|
PREFAB PAV MRK TY C (W) (NUMBER)
|
EA
|
2.000
|
$200.000
|
$185.000
|
$185.000
|
$185.000
|
|
REFL PAV MRKR TY II-A-A
|
EA
|
4.000
|
$3.000
|
$4.000
|
$3.750
|
$3.750
|
|
REFL PAV MRKR TY II-C-R
|
EA
|
524.000
|
$3.000
|
$4.000
|
$3.750
|
$3.750
|
|
|
ELIM EXT PAV MRK & MRKS (4")
|
LF
|
72,000.000
|
$0.500
|
$0.500
|
$0.450
|
$0.450
|
|
|
FULL - WIDTH MOWING
|
AC
|
50.000
|
$100.000
|
$300.000
|
$82.500
|
$75.000
|
|
|
CARBON FIBER REINF POLYMER STRENGTHNING
|
SF
|
634.000
|
$40.000
|
$56.000
|
$50.000
|
$56.000
|
|
|
TRANSPLANT PLANT MATERIAL
|
EA
|
22.000
|
$1,000.000
|
$900.000
|
$764.500
|
$695.000
|
|
|
GEOGRID BASE REINFORCEMENT (TY II)
|
SY
|
20,063.000
|
$1.500
|
$1.750
|
$1.500
|
$3.450
|
|
|
PORTABLE CHANGEABLE MESSAGE SIGN
|
EA
|
2.000
|
$10,000.000
|
$3,000.000
|
$4,500.000
|
$9,601.700
|
|
|
TMA (STATIONARY)
|
EA
|
2.000
|
$10,000.000
|
$3,000.000
|
$2,500.000
|
$436.530
|
|
Totals: |
$14,830,225.150
|
$15,409,267.695
|
$16,143,202.070
|
$17,541,525.290
|