WICHITA VA (0903-00-120)

Items: 15

County: WICHITA
Length: N/A
Highway: VA
District: WICHITA FALLS
Control Number: 0903-00-120
DBE Goal: N/A
Project: F 2022(377)
Guaranty: N/A
Time: 78 WORKING DAYS
Engineer's Estimate: $633,165.40
Date: 05/05/2022 (4 years ago)
Contract Number: N/A
Type: INSTALL ILLUMINATION
Mail/Deliver Bids To: N/A
SEE PLANS OR PROPOSAL BOOK
Actions:
Notice HCS Excel Tabs Print Print Notice
Documents:
Bidders (5)
E
Engineer's Estimate
$633,165.40
Over/Under Est: 31.59% $199,993.46
Over/Under Est: 34.09% $215,872.81
Amt Left: 1.91% $15,879.35
Over/Under Est: 39.28% $248,733.12
Amt Left: 5.85% $48,739.66
Delta: -3.87% -$32,860.31
$942,539.33
Over/Under Est: 48.86% $309,373.93
Amt Left: 13.13% $109,380.47
Delta: -6.88% -$60,640.81
Over/Under Est: 54.92% $347,741.55
Amt Left: 17.73% $147,748.09
Delta: -4.07% -$38,367.62
Subcontractor Percentage Amount
MEDELLIN HDD LLC 6.42% $53,488.80
Total: 6.42% $53,488.80

Bid Items & Bid Tabulations

15 Total 0 of 15
WICHITA  |  VA  |  WICHITA FALLS  |  0903-00-120  |  05/05/2022  |  $633,165.40  |  F 2022(377)  |  INSTL ILLUM  |  78 WORKING DAYS
Item Code
Description
Unit
Quantity
Engineer's Estimate
WG ENGINEERING & CONSTRUCTION, LLC
HIGHWAY INTELLIGENT TRAFFIC SOLUTIONS, INC.
SIEMENS MOBILITY, INC.
MICA CORPORATION
SOUTH TEXAS ILLUMINATION, LLC
DRILL SHAFT (RDWY ILL POLE) (30 IN)
LF 360.000 $255.000 $348.000 $244.500 $462.400 $219.050 $485.000
RIPRAP (CONC)(CL B)
CY 12.770 $400.000 $418.000 $729.500 $575.100 $3,474.000 $585.000
MOBILIZATION
LS 1.000 $56,470.000 $85,500.000 $92,293.920 $87,313.000 $84,515.000 $75,000.000
BARRICADES, SIGNS AND TRAFFIC HANDLING
MO 6.000 $2,000.000 $4,280.000 $9,290.050 $2,012.600 $14,650.000 $13,000.000
BIODEG EROSN CONT LOGS (INSTL) (18")
LF 880.000 $5.940 $5.000 $1.930 $3.500 $6.900 $5.000
BIODEG EROSN CONT LOGS (REMOVE)
LF 880.000 $1.140 $2.000 $0.680 $2.400 $1.950 $5.000
IN RD IL (TY ST) 40T-8 (250W EQ) LED
EA 2.000 $3,795.000 $4,798.000 $4,628.750 $4,899.200 $4,360.000 $6,500.000
IN RD IL (TY ST) 50T-10 (400W EQ) LED
EA 34.000 $4,195.000 $5,265.000 $5,216.250 $5,149.900 $4,637.000 $6,500.000
CONDT (PVC) (SCH 40) (2")
LF 4,235.000 $11.500 $18.000 $15.250 $26.700 $17.520 $10.000
CONDT (PVC) (SCH 80) (2") (BORE)
LF 1,695.000 $23.500 $33.000 $26.050 $39.200 $40.050 $25.000
ELEC CONDR (NO.6) BARE
LF 5,930.000 $1.700 $3.000 $2.050 $1.800 $2.380 $1.850
ELEC CONDR (NO.6) INSULATED
LF 11,860.000 $1.850 $3.000 $2.120 $2.000 $2.470 $1.850
GROUND BOX TY A (122311)W/APRON
EA 44.000 $925.000 $1,025.000 $1,366.000 $1,796.400 $1,803.000 $1,100.000
ELC SRV TY A 120/240 060(NS)SS(E)SP(O)
EA 20.000 $6,100.000 $6,465.000 $8,741.250 $4,623.200 $9,319.000 $7,950.000
TMA (STATIONARY)
DAY 156.000 $180.000 $235.000 $216.630 $212.800 $138.050 $500.000
Totals: $633,165.400 $833,158.860 $849,038.215 $881,898.527 $942,539.330 $980,906.950