Job Info for 0802-02-075

County: WICHITA Highway: FM 369 Date: 12/02/2020 (3 years ago) Engineer's Estimate: $1,303,273 Control Number: 0802-02-075
Project: STP 2B20(326) District: WICHITA FALLS Time: 51 WORKING DAYS Type: PAVEMENT REPAIR AND OVERLAY

Bidders

Name Total Amount Place Over/Under Est Amt Left From Low Bid Delta Between Bidders
Engineer's Estimate $1,303,272.90
INTEGRITY SERVICES, LLC   $976,487.33 1
-25.07% | -$326,785.57
ZACK BURKETT CO.   $1,000,931.52 2
-23.2% | -$302,341.38
2.5% | $24,444.19
EUROVIA ATLANTIC COAST LLC   $1,183,653.66 3
-9.18% | -$119,619.24
21.22% | $207,166.33
18.26% | $182,722.14
PEACHTREE CONSTRUCTION, LTD.   $1,184,096.34 4
-9.14% | -$119,176.56
21.26% | $207,609.01
0.04% | $442.68
A. L. HELMCAMP, INC.   $1,386,086.35 5
6.35% | $82,813.45
41.95% | $409,599.02
17.06% | $201,990.01

Bid Items

Items: 42, 0 filtered
WICHITA FM 369  |  WICHITA FALLS  |  0802-02-075  |  12/02/2020  |  $1,303,273  |  STP 2B20(326)  |  PAVMT REPAIR AND OVERLAY  |  51 WORKING DAYS
Item code Description Unit Quantity Engineer's Estimate INTEGRITY SERVICES, LLC ZACK BURKETT CO. EUROVIA ATLANTIC COAST LLC PEACHTREE CONSTRUCTION, LTD. A. L. HELMCAMP, INC.
132 6003 EMBANKMENT (FINAL)(ORD COMP)(TY B) CY 212.000 $40.000 $20.000 $12.000 $60.000 $63.000 $60.000
134 6001 BACKFILL (TY A) STA 78.510 $430.000 $95.000 $145.000 $230.000 $220.000 $400.000
164 6021 CELL FBR MLCH SEED(PERM)(RURAL)(SANDY) SY 3,600.000 $1.500 $0.830 $0.750 $0.750 $0.250 $0.850
168 6001 VEGETATIVE WATERING MG 14.000 $100.000 $65.000 $25.000 $105.000 $25.000 $45.000
314 6010 EMULS ASPH (EROSN CONT)(SS-1) GAL 1,742.000 $3.250 $4.000 $3.400 $2.500 $4.000 $7.500
346 6014 STONE-MTRX-ASPH SMA-D SAC-A PG76-22 TON 4,847.000 $125.000 $113.300 $108.500 $117.000 $126.000 $130.000
351 6036 FLEX PAVEMENT STRUCTURE REPAIR (2-8") SY 1,108.000 $82.000 $8.800 $46.000 $45.000 $54.500 $70.000
351 6039 FLEX PAVEMENT STRUCTURE REPAIR (8"-12") SY 890.000 $102.000 $22.000 $69.000 $72.000 $85.000 $120.000
354 6004 PLAN & TEXT ASPH CONC PAV(0" TO 4") SY 2,078.000 $8.000 $5.500 $4.500 $4.500 $3.700 $9.000
354 6021 PLANE ASPH CONC PAV(0" TO 2") SY 3,543.000 $4.500 $3.300 $2.500 $5.700 $3.150 $6.000
432 6045 RIPRAP (MOW STRIP)(4 IN) CY 90.000 $650.000 $500.000 $600.000 $665.000 $630.000 $900.000
442 6008 STR STEEL (MISCELLANEOUS BRIDGE) LB 17,897.500 $5.000 $3.080 $4.910 $4.150 $4.350 $4.000
500 6001 MOBILIZATION LS 1.000 $116,843.000 $130,484.710 $75,875.000 $100,000.000 $95,000.000 $130,000.000
502 6001 BARRICADES, SIGNS AND TRAFFIC HANDLING MO 3.000 $6,000.000 $1,700.000 $1,467.000 $24,650.000 $14,250.000 $15,000.000
506 6041 BIODEG EROSN CONT LOGS (INSTL) (12") LF 1,600.000 $4.000 $2.970 $2.700 $2.700 $6.500 $3.500
506 6043 BIODEG EROSN CONT LOGS (REMOVE) LF 1,600.000 $1.000 $0.720 $0.650 $0.650 $1.050 $1.000
533 6001 RUMBLE STRIPS (SHOULDER) LF 15,029.000 $0.350 $0.170 $0.250 $0.400 $0.300 $0.600
533 6002 RUMBLE STRIPS (CENTERLINE) LF 7,514.000 $0.500 $0.200 $0.300 $0.580 $0.350 $0.600
540 6001 MTL W-BEAM GD FEN (TIM POST) LF 800.000 $22.000 $20.790 $20.000 $19.800 $18.500 $25.000
540 6006 MTL BEAM GD FEN TRANS (THRIE-BEAM) EA 8.000 $1,900.000 $1,431.000 $1,500.000 $1,800.000 $1,000.000 $2,100.000
540 6037 MTL BM GD FEN TRANS (ANCHOR PLATE) EA 8.000 $650.000 $702.000 $820.000 $600.000 $630.000 $700.000
542 6001 REMOVE METAL BEAM GUARD FENCE LF 1,025.000 $3.000 $2.700 $2.000 $3.000 $2.150 $4.000
542 6002 REMOVE TERMINAL ANCHOR SECTION EA 7.000 $280.000 $216.000 $175.000 $300.000 $160.000 $350.000
544 6001 GUARDRAIL END TREATMENT (INSTALL) EA 8.000 $2,800.000 $2,754.000 $2,250.000 $2,700.000 $2,100.000 $3,100.000
544 6003 GUARDRAIL END TREATMENT (REMOVE) EA 5.000 $400.000 $216.000 $175.000 $300.000 $157.000 $350.000
658 6014 INSTL DEL ASSM (D-SW)SZ (BRF)CTB (BI) EA 16.000 $35.000 $21.600 $11.000 $30.000 $19.500 $40.000
658 6062 INSTL DEL ASSM (D-SW)SZ 1(BRF)GF2(BI) EA 24.000 $35.000 $37.800 $14.000 $30.000 $41.000 $40.000
662 6109 WK ZN PAV MRK SHT TERM (TAB)TY W EA 119.000 $3.000 $1.000 $1.000 $1.400 $2.250 $1.000
662 6111 WK ZN PAV MRK SHT TERM (TAB)TY Y-2 EA 846.000 $1.500 $1.000 $1.000 $1.400 $2.250 $1.000
666 6036 REFL PAV MRK TY I (W)8"(SLD)(100MIL) LF 501.000 $2.800 $1.080 $0.800 $0.850 $0.900 $1.000
666 6300 RE PM W/RET REQ TY I (W)4"(BRK)(100MIL) LF 313.000 $2.000 $1.080 $0.450 $0.550 $0.480 $0.650
666 6303 RE PM W/RET REQ TY I (W)4"(SLD)(100MIL) LF 16,764.000 $0.850 $0.540 $0.450 $0.380 $0.480 $0.450
666 6312 RE PM W/RET REQ TY I (Y)4"(BRK)(100MIL) LF 992.000 $0.750 $1.080 $0.450 $0.550 $0.480 $0.650
666 6315 RE PM W/RET REQ TY I (Y)4"(SLD)(100MIL) LF 12,550.000 $0.650 $0.540 $0.450 $0.380 $0.480 $0.450
668 6076 PREFAB PAV MRK TY C (W) (24") (SLD) LF 48.000 $16.000 $16.200 $18.000 $13.000 $19.500 $15.000
668 6077 PREFAB PAV MRK TY C (W) (ARROW) EA 2.000 $250.000 $243.000 $224.000 $275.000 $240.000 $210.000
668 6085 PREFAB PAV MRK TY C (W) (WORD) EA 2.000 $350.000 $324.000 $298.000 $375.000 $315.000 $430.000
672 6007 REFL PAV MRKR TY I-C EA 41.000 $6.000 $5.400 $5.000 $7.000 $5.250 $8.000
672 6009 REFL PAV MRKR TY II-A-A EA 201.000 $5.000 $5.400 $5.000 $5.000 $5.250 $6.000
3084 6001 BONDING COURSE GAL 2,643.000 $3.750 $4.000 $3.750 $4.000 $3.950 $4.000
6185 6002 TMA (STATIONARY) DAY 45.000 $275.000 $180.000 $25.000 $275.000 $100.000 $250.000
6185 6005 TMA (MOBILE OPERATION) DAY 10.000 $750.000 $366.000 $150.000 $565.000 $250.000 $450.000
Totals: $1,303,272.90 $976,487.33 $1,000,931.53 $1,183,653.67 $1,184,096.34 $1,386,086.35