WICHITA US 287 (0043-08-075)
Items: 29
County: WICHITA
Length: N/A
Highway: US 287
District: WICHITA FALLS
Control Number: 0043-08-075
DBE Goal: N/A
Project: NH 1802(303)
Guaranty: N/A
Time: 85 WORKING DAYS
Engineer's Estimate: $2,415,816.50
Date: 08/07/2018 (7 years ago)
Contract Number: N/A
Type: INSTALL MEDIAN BARRIER
Mail/Deliver Bids To: N/A
SEE PLANS OR PROPOSAL BOOK
Bidders (7)
| Bidder | Total Amount | Over/Under Est | Amt Left From Low Bid | Delta Between Bidders |
|---|---|---|---|---|
|
E
Engineer's Estimate
|
$2,415,816.50 | |||
| $2,014,723.35 |
-16.6%
-$401,093.15
|
|||
| $2,045,849.80 |
-15.31%
-$369,966.70
|
1.54%
$31,126.45
|
||
| $2,157,916.80 |
-10.68%
-$257,899.70
|
7.11%
$143,193.45
|
-5.48%
-$112,067.00
|
|
| $2,277,035.09 |
-5.74%
-$138,781.41
|
13.02%
$262,311.74
|
-5.52%
-$119,118.29
|
|
| $2,323,611.80 |
-3.82%
-$92,204.70
|
15.33%
$308,888.45
|
-2.05%
-$46,576.71
|
|
| $2,348,914.20 |
-2.77%
-$66,902.30
|
16.59%
$334,190.85
|
-1.09%
-$25,302.40
|
|
| $2,759,144.00 |
14.21%
$343,327.50
|
36.95%
$744,420.65
|
-17.46%
-$410,229.80
|
E
Engineer's Estimate
$2,415,816.50
1
Awarded
$2,014,723.35
Over/Under Est:
-16.6%
-$401,093.15
$2,045,849.80
Over/Under Est:
-15.31%
-$369,966.70
Amt Left:
1.54%
$31,126.45
$2,157,916.80
Over/Under Est:
-10.68%
-$257,899.70
Amt Left:
7.11%
$143,193.45
Delta:
-5.48%
-$112,067.00
$2,277,035.09
Over/Under Est:
-5.74%
-$138,781.41
Amt Left:
13.02%
$262,311.74
Delta:
-5.52%
-$119,118.29
$2,323,611.80
Over/Under Est:
-3.82%
-$92,204.70
Amt Left:
15.33%
$308,888.45
Delta:
-2.05%
-$46,576.71
$2,348,914.20
Over/Under Est:
-2.77%
-$66,902.30
Amt Left:
16.59%
$334,190.85
Delta:
-1.09%
-$25,302.40
$2,759,144.00
Over/Under Est:
14.21%
$343,327.50
Amt Left:
36.95%
$744,420.65
Delta:
-17.46%
-$410,229.80
Bid Items & Bid Tabulations
29
Total
0 of 29