Job Info for 0275-12-085

County: WHEELER Highway: IH 40 Date: 04/04/2024 (7 months ago) Engineer's Estimate: $3,795,408 Control Number: 0275-12-085
Project: F 2024(846) District: CHILDRESS Time: 193 WORKING DAYS Type: REPLACE GUARDRAIL
Bidder's List
Email All | Notice | Questions
HCS
Pay Estimates: 1 | 2 | 3 | 4 | 5 | 6
Plans: Plans | Proposal

Bidders

Name Total Amount Place Over/Under Est Amt Left From Low Bid Delta Between Bidders
Engineer's Estimate $3,795,407.50
3LW CIVIL LLC   $3,449,940.40 1
-9.1% | -$345,467.10
HJC FARMS, INC.   $3,911,868.32 2
3.07% | $116,460.82
13.39% | $461,927.92
BUILT RIGHT CONSTRUCTION OF OKLAHOMA, LLC   $4,139,066.00 3
9.05% | $343,658.50
19.98% | $689,125.60
5.81% | $227,197.68
GIBSON & ASSOCIATES, INC.   $4,757,640.10 4
25.35% | $962,232.60
37.9% | $1,307,699.70
14.94% | $618,574.10
Subcontractor Percentage Amount
JB PINNACLE GROUP, LLC 13.61% $469,536.89
STRUCTURAL INTEGRITY GROUP LLC 12.72% $438,832.42
MACIAS SPECIALTY CONTRACTING LLC 6.51% $224,591.12
KING GEORGE TRAFFIC SOLUTIONS LLC 1.42% $48,989.15
BARRICADES UNLIMITED 0.85% $29,324.49
Total: 35.11% $1,211,274.07

Bid Items

Items: 46, 0 filtered
WHEELER IH 40  |  CHILDRESS  |  0275-12-085  |  04/04/2024  |  $3,795,408  |  F 2024(846)  |  REPLACE GUARDRAIL  |  193 WORKING DAYS
Item code Description Unit Quantity Engineer's Estimate 3LW CIVIL LLC HJC FARMS, INC. BUILT RIGHT CONSTRUCTION OF OKLAHOMA, LLC GIBSON & ASSOCIATES, INC.
104 6009 REMOVING CONC (RIPRAP) SY 243.000 $45.000 $40.000 $95.000 $100.000 $95.000
401 6001 FLOWABLE BACKFILL CY 30.000 $500.000 $750.000 $900.000 $350.000 $800.000
428 6001 PENETRATING CONCRETE SURFACE TREATMENT SY 1,643.000 $35.000 $11.000 $12.400 $20.000 $11.000
429 6001 CONC STR REPAIR(CLEAN & COAT WTH EPOXY) SF 127.000 $220.000 $247.500 $260.000 $300.000 $231.000
429 6003 CONC STR REPAIR(DECK REP(PART DEPTH)) SF 175.000 $190.000 $247.500 $161.000 $335.000 $143.000
429 6007 CONC STR REPAIR (VERTICAL & OVERHEAD) SF 201.000 $250.000 $247.500 $266.000 $325.000 $236.500
432 6001 RIPRAP (CONC)(4 IN) CY 5.000 $1,200.000 $750.000 $562.500 $1,000.000 $1,500.000
432 6045 RIPRAP (MOW STRIP)(4 IN) CY 822.000 $560.000 $550.000 $562.500 $700.000 $950.000
438 6002 CLEANING AND SEALING EXIST JOINTS(CL3) LF 948.000 $70.000 $47.300 $48.000 $60.000 $65.000
438 6006 CLEANING AND SEALING JOINTS (CL 3) LF 701.000 $35.000 $47.300 $65.000 $60.000 $47.000
439 6013 MULTI-LAYER POLYMER OVERLAY SY 3,709.000 $60.000 $43.750 $57.000 $65.000 $55.000
451 6024 RETROFIT RAIL (TY SSTR) LF 1,998.000 $270.000 $242.000 $325.000 $300.000 $325.000
454 6007 HEADER TYPE EXPANSION JOINT LF 7.000 $200.000 $577.500 $282.000 $600.000 $250.000
483 6013 SHOT BLASTING SY 3,709.000 $6.000 $6.600 $5.630 $8.000 $10.000
500 6001 MOBILIZATION LS 1.000 $345,000.000 $338,980.000 $450,000.000 $400,000.000 $650,000.000
502 6001 BARRICADES, SIGNS AND TRAFFIC HANDLING MO 12.000 $10,000.000 $8,500.000 $3,000.000 $3,000.000 $12,900.000
506 6038 TEMP SEDMT CONT FENCE (INSTALL) LF 150.000 $5.000 $0.100 $7.000 $5.000 $6.600
506 6039 TEMP SEDMT CONT FENCE (REMOVE) LF 150.000 $5.000 $0.100 $1.000 $1.000 $1.650
506 6042 BIODEG EROSN CONT LOGS (INSTL) (18") LF 750.000 $10.000 $0.100 $9.000 $15.000 $11.000
512 6001 PORT CTB (FUR & INST)(SGL SLOPE)(TY 1) LF 3,200.000 $100.000 $55.000 $105.000 $110.000 $110.000
512 6025 PORT CTB (MOVE)(SGL SLP)(TY 1) LF 6,400.000 $12.000 $22.000 $18.000 $15.000 $24.000
512 6049 PORT CTB (REMOVE)(SGL SLP)(TY 1) LF 3,200.000 $10.000 $35.000 $25.000 $20.000 $38.500
540 6002 MTL W-BEAM GD FEN (STEEL POST) LF 15,275.000 $20.000 $30.000 $28.250 $38.000 $32.480
540 6006 MTL BEAM GD FEN TRANS (THRIE-BEAM) EA 15.000 $2,500.000 $2,420.000 $2,500.000 $3,000.000 $2,688.000
540 6016 DOWNSTREAM ANCHOR TERMINAL SECTION EA 26.000 $1,600.000 $1,350.000 $1,450.000 $1,700.000 $1,680.000
542 6001 REMOVE METAL BEAM GUARD FENCE LF 15,625.000 $4.500 $1.250 $3.000 $4.000 $3.360
542 6002 REMOVE TERMINAL ANCHOR SECTION EA 30.000 $300.000 $250.000 $300.000 $300.000 $336.000
544 6001 GUARDRAIL END TREATMENT (INSTALL) EA 42.000 $3,900.000 $3,400.000 $3,325.000 $4,000.000 $3,354.400
544 6003 GUARDRAIL END TREATMENT (REMOVE) EA 32.000 $350.000 $250.000 $300.000 $300.000 $336.000
545 6003 CRASH CUSH ATTEN (MOVE & RESET) EA 4.000 $3,500.000 $1,500.000 $2,500.000 $2,200.000 $5,000.000
545 6005 CRASH CUSH ATTEN (REMOVE) EA 2.000 $2,500.000 $1,250.000 $1,500.000 $1,500.000 $5,000.000
545 6019 CRASH CUSH ATTEN (INSTL)(S)(N)(TL3) EA 2.000 $11,000.000 $9,000.000 $8,000.000 $11,000.000 $15,000.000
666 6170 REFL PAV MRK TY II (W) 4" (SLD) LF 11,160.000 $1.500 $0.830 $0.900 $1.000 $0.830
666 6207 REFL PAV MRK TY II (Y) 4" (SLD) LF 11,160.000 $1.500 $0.830 $0.900 $1.000 $0.830
666 6306 RE PM W/RET REQ TY I (W)6"(BRK)(100MIL) LF 990.000 $1.200 $1.210 $1.320 $1.200 $2.200
666 6309 RE PM W/RET REQ TY I (W)6"(SLD)(100MIL) LF 3,600.000 $1.200 $1.210 $1.320 $1.200 $1.210
666 6321 RE PM W/RET REQ TY I (Y)6"(SLD)(100MIL) LF 3,600.000 $1.200 $1.210 $1.320 $1.200 $1.210
672 6016 TRAFFIC BUTTON TY W EA 144.000 $10.000 $4.400 $4.800 $5.000 $4.400
672 6017 TRAFFIC BUTTON TY Y EA 144.000 $10.000 $4.400 $4.800 $5.000 $4.400
677 6001 ELIM EXT PAV MRK & MRKS (4") LF 14,835.000 $1.800 $0.500 $0.550 $0.600 $0.500
780 6002 CNC CRACK REPAIR (DISCRETE)(INJECT) LF 533.000 $65.000 $99.000 $140.500 $130.000 $125.000
786 6001 CARBON FIBER REINF POLYMER PROTECTION SF 1,131.000 $150.000 $92.400 $50.750 $80.000 $45.000
4106 6001 POLYESTER POLYMER CONC OVERLAY (3/4") SY 1,787.000 $170.000 $122.100 $165.000 $100.000 $175.000
6001 6002 PORTABLE CHANGEABLE MESSAGE SIGN EA 2.000 $17,000.000 $8,500.000 $15,000.000 $10,200.000 $18,000.000
6185 6002 TMA (STATIONARY) DAY 193.000 $290.000 $150.000 $100.000 $200.000 $50.000
6185 6003 TMA (MOBILE OPERATION) HR 40.000 $100.000 $115.000 $100.000 $75.000 $100.000
Totals: $3,795,407.50 $3,449,940.40 $3,911,868.32 $4,139,066.00 $4,757,640.10