WHARTON US0059 (6452-69-001)

Items: 15

County: WHARTON
Length: N/A
Highway: US0059
District: YOAKUM
Control Number: 6452-69-001
DBE Goal: N/A
Project: RMC - 645269001
Guaranty: N/A
Time: 60 W
Engineer's Estimate: $1,741,431.10
Date: 11/02/2023 (2 years ago)
Contract Number: N/A
Type: THERMOPLASTIC PAVEMENT MARKINGS
Mail/Deliver Bids To: N/A
CAMILLE MAREK
KELLY ROTHER
Actions:
Notice HCS Excel Tabs Print Print Notice
Documents:
Bidders (8)
E
Engineer's Estimate
$1,741,431.10
Over/Under Est: -25.46% -$443,387.18
$1,532,688.53
Over/Under Est: -11.99% -$208,742.57
Amt Left: 18.08% $234,644.61
$1,599,891.55
Over/Under Est: -8.13% -$141,539.55
Amt Left: 23.25% $301,847.63
Delta: -4.38% -$67,203.02
Over/Under Est: -7.85% -$136,645.30
Amt Left: 23.63% $306,741.88
Delta: -0.31% -$4,894.25
$1,702,195.96
Over/Under Est: -2.25% -$39,235.14
Amt Left: 31.14% $404,152.04
Delta: -6.07% -$97,410.16
Over/Under Est: -1.09% -$19,003.17
Amt Left: 32.69% $424,384.01
Delta: -1.19% -$20,231.97
Over/Under Est: 4.05% $70,553.26
Amt Left: 39.59% $513,940.44
Delta: -5.20% -$89,556.43
Over/Under Est: 10.34% $179,988.90
Amt Left: 48.02% $623,376.08
Delta: -6.04% -$109,435.64

Bid Items & Bid Tabulations

15 Total 0 of 15
WHARTON  |  US0059  |  YOAKUM  |  6452-69-001  |  11/02/2023  |  $1,741,431.10  |  RMC - 645269001  |  THERMOPLASTIC PAVMT MRK  |  60 W
Item Code
Description
Unit
Quantity
Engineer's Estimate
HIGHWAY BARRICADES AND SERVICES, LLC
STRIPE LINES, INC.
BATTERSON, LLP
TRP CONSTRUCTION GROUP, LLC
STRIPE-A-ZONE, LLC
PROFESSIONAL TRAFFIC CONTROL LLC
CENTERLINE TECHNOLOGIES, LLC
INTERSTATE BARRICADES & MARKINGS, INC.
MOBILIZATION
LS 1.000 $160,000.000 $5,000.000 $10,000.000 $1,000.000 $6,500.000 $20,000.000 $77,000.000 $25,000.000 $75,000.000
BARRICADES, SIGNS AND TRAFFIC HANDLING
MO 4.000 $2,500.000 $500.000 $150.000 $100.000 $2,000.000 $1,000.000 $1,000.000 $1.000 $1,000.000
REFL PAV MRK TY I (W)8"(SLD)(090MIL)
LF 16,485.000 $0.800 $0.650 $0.880 $0.830 $0.800 $0.800 $0.750 $0.750 $1.250
RE PM W/RET REQ TY I (W)6"(BRK)(060MIL)
LF 4,300.000 $0.540 $0.380 $1.800 $0.330 $0.400 $0.520 $0.520 $0.420 $0.350
RE PM W/RET REQ TY I (W)6"(SLD)(060MIL)
LF 372,928.000 $0.540 $0.380 $0.360 $0.330 $0.350 $0.500 $0.520 $0.420 $0.350
RE PM W/RET REQ TY I (Y)6"(BRK)(060MIL)
LF 50,982.000 $0.540 $0.380 $0.360 $0.330 $0.400 $0.520 $0.520 $0.420 $0.350
RE PM W/RET REQ TY I (Y)6"(SLD)(060MIL)
LF 121,704.000 $0.540 $0.380 $0.360 $0.330 $0.350 $0.500 $0.520 $0.420 $0.350
REF PROF PAV MRK TY I(W)6"(SLD)(100MIL)
LF 604,747.000 $0.680 $0.580 $0.740 $0.850 $0.800 $0.700 $0.585 $0.780 $0.850
REF PROF PAV MRK TY I(Y)6"(BRK)(100MIL)
LF 104,786.000 $0.720 $0.580 $0.740 $0.850 $0.900 $0.720 $0.585 $0.780 $0.850
REF PROF PAV MRK TY I(Y)6"(SLD)(100MIL)
LF 302,483.000 $0.680 $0.580 $0.740 $0.850 $0.800 $0.700 $0.585 $0.780 $0.850
TMA (MOBILE OPERATION)
DAY 150.000 $500.000 $5.000 $10.000 $1.000 $25.000 $25.000 $650.000 $1.000 $100.000
HPPM-RIB W/RET REQ TYI(W)6"(BRK)100MIL
LF 53,537.000 $0.520 $0.490 $0.550 $0.540 $0.600 $0.680 $0.650 $0.750 $0.750
HPPM-RIB W/RET REQ TYI(W)6"(SLD)100MIL
LF 541,185.000 $0.480 $0.480 $0.550 $0.540 $0.550 $0.670 $0.650 $0.750 $0.750
HPPM-RIB W/RET REQ TYI(Y)6"(BRK)100MIL
LF 46,334.000 $0.520 $0.490 $0.550 $0.540 $0.600 $0.680 $0.650 $0.750 $0.750
HPPM-RIB W/RET REQ TYI(Y)6"(SLD)100MIL
LF 364,451.000 $0.500 $0.480 $0.550 $0.540 $0.550 $0.670 $0.650 $0.750 $0.750
Totals: $1,741,431.100 $1,298,043.920 $1,532,688.530 $1,599,891.550 $1,604,785.800 $1,702,195.960 $1,722,427.940 $1,811,984.360 $1,921,420.000