WHARTON CO (0913-09-119)

Items: 40

County: WHARTON
Length: N/A
Highway: CO
District: YOAKUM
Control Number: 0913-09-119
DBE Goal: 500.0%
Project: BR 2B23(212)
Guaranty: N/A
Time: 223 WORKING DAYS
Engineer's Estimate: $2,107,468.50
Date: 08/02/2024 (1 year ago)
Contract Number: N/A
Type: BRIDGE REPLACEMENT
Mail/Deliver Bids To: N/A
RYAN SIMPER
PAUL RODRIGUEZ
Actions:
Notice Questions HCS Excel Tabs Print Print Notice
Bidders (7)
E
Engineer's Estimate
$2,107,468.50
1
$2,156,908.46
Over/Under Est: 2.35% $49,439.96
Over/Under Est: 2.47% $52,060.73
Amt Left: 0.12% $2,620.77
$2,199,255.21
Over/Under Est: 4.36% $91,786.71
Amt Left: 1.96% $42,346.75
Delta: -1.84% -$39,725.98
Over/Under Est: 9.27% $195,428.72
Amt Left: 6.77% $145,988.76
Delta: -4.71% -$103,642.01
$2,460,389.39
Over/Under Est: 16.75% $352,920.89
Amt Left: 14.07% $303,480.93
Delta: -6.84% -$157,492.17
Over/Under Est: 21.29% $448,655.30
Amt Left: 18.51% $399,215.34
Delta: -3.89% -$95,734.41
Over/Under Est: 38.44% $810,205.32
Amt Left: 35.27% $760,765.36
Delta: -14.14% -$361,550.02
Subcontractor Percentage Amount
JH CONTRACT FIELD SERVICES, LLC 6.82% $147,101.16
SYLVA CONSTRUCTION, LLC 4.13% $89,080.32
MESA ROD BUSTERS INC 0.66% $14,235.60
SUPERIOR TRAFFIC CONTROL, LLC 0.49% $10,568.85
Total: 12.10% $260,985.93

Bid Items & Bid Tabulations

40 Total 0 of 40
WHARTON  |  CO  |  YOAKUM  |  0913-09-119  |  08/02/2024  |  $2,107,468.50  |  BR 2B23(212)  |  BRIDGE REPL  |  223 WORKING DAYS
Item Code
Description
Unit
Quantity
Engineer's Estimate
TREVWAY, INC.
A GREATER AUSTIN DEVELOPMENT COMPANY, LLC
C. E. BARKER, LTD.
KNIFE RIVER CORPORATION - SOUTH
TALBERT COMPANIES LLC
E-Z BEL CONSTRUCTION, LLC
FUQUA CONSTRUCTION CO., INC.
PREPARING ROW
STA 11.520 $4,000.000 $3,000.000 $6,445.000 $8,700.000 $10,517.000 $3,832.500 $3,000.000 $15,000.000
EXCAVATION (ROADWAY)
CY 1,061.000 $22.000 $30.000 $30.900 $39.690 $19.500 $32.850 $30.000 $36.460
EXCAVATION (CHANNEL)
CY 844.000 $22.000 $25.000 $26.800 $39.690 $14.650 $43.800 $26.000 $41.100
EMBANKMENT (FINAL)(ORD COMP)(TY C)
CY 691.000 $30.000 $27.000 $27.800 $27.290 $26.000 $65.700 $27.000 $49.470
BLADING
HR 24.000 $125.000 $100.000 $61.800 $173.640 $216.000 $222.460 $60.000 $143.090
BROADCAST SEED (PERM) (RURAL) (CLAY)
SY 3,090.000 $2.000 $3.000 $1.400 $0.870 $0.780 $0.770 $1.000 $1.430
BROADCAST SEED (TEMP) (WARM)
SY 776.000 $2.000 $1.000 $2.550 $3.350 $3.000 $2.960 $1.000 $0.810
BROADCAST SEED (TEMP) (COOL)
SY 776.000 $2.000 $1.000 $2.550 $3.350 $3.000 $2.960 $1.000 $1.350
VEGETATIVE WATERING
MG 26.200 $90.000 $100.000 $140.000 $179.840 $82.000 $328.500 $60.000 $308.970
FL BS (CMP IN PLC)(TY E GR 5)(FNL POS)
CY 940.000 $150.000 $246.000 $142.150 $111.630 $178.300 $116.490 $138.000 $140.000
ASPH (RC-250)
GAL 741.000 $11.000 $20.550 $17.800 $11.160 $15.000 $32.850 $16.000 $18.320
AGGR(TY-E GR-5 SAC-B)
CY 30.000 $900.000 $1,284.000 $524.000 $328.670 $945.000 $1,460.000 $993.000 $60.000
AGGR(TY-PE GR-4 SAC-B)
CY 30.000 $900.000 $1,541.000 $524.000 $328.670 $952.000 $1,460.000 $1,012.000 $520.330
ASPH (AC 20-5TR OR AC-20XP OR CRS-2P)
GAL 1,259.000 $20.000 $17.000 $15.800 $9.920 $11.000 $32.790 $14.000 $5.230
CEM STABIL BKFL
CY 114.000 $220.000 $175.000 $268.500 $217.050 $193.600 $273.750 $550.000 $253.340
TRENCH EXCAVATION PROTECTION
LF 4.000 $250.000 $500.000 $110.000 $155.040 $30.000 $30.660 $1.000 $59.000
DRILL SHAFT (24 IN)
LF 780.000 $265.000 $327.000 $265.000 $321.800 $275.450 $262.800 $240.330 $406.850
CL C CONC (ABUT)
CY 75.600 $1,300.000 $800.000 $1,455.000 $1,843.880 $1,426.000 $1,368.750 $1,100.000 $1,849.530
CL C CONC (CAP)
CY 16.600 $1,400.000 $2,200.000 $2,080.000 $2,536.370 $2,894.000 $1,423.500 $1,800.000 $2,051.810
CL C CONC (COLUMN)
CY 5.600 $1,500.000 $2,124.000 $2,985.000 $2,536.370 $3,482.000 $1,368.750 $3,100.000 $2,002.910
REINF CONC SLAB
SF 6,264.000 $25.000 $20.000 $29.850 $31.940 $34.150 $27.380 $30.000 $36.090
PRESTR CONC SLAB BEAM (4SB12)
LF 812.790 $250.000 $221.000 $198.750 $211.310 $227.000 $190.910 $350.000 $277.300
PRESTR CONC SLAB BEAM (4SB15)
LF 711.860 $250.000 $222.000 $198.750 $211.310 $205.600 $196.820 $310.000 $330.400
RIPRAP (STONE PROTECTION)(18 IN)
CY 1,230.000 $200.000 $206.000 $240.000 $217.050 $189.300 $287.160 $469.000 $253.660
RAIL (TY T223)
LF 462.000 $145.000 $191.000 $225.000 $229.450 $197.000 $174.600 $300.000 $277.010
ARMOR JOINT (SEALED)
LF 174.000 $150.000 $88.000 $155.000 $76.090 $136.000 $136.880 $135.000 $207.530
RC PIPE (CL III)(24 IN)
LF 342.000 $125.000 $100.000 $77.000 $98.090 $77.500 $161.940 $150.000 $156.230
SET (TY II) (24 IN) (RCP) (6: 1) (P)
EA 2.000 $3,000.000 $2,000.000 $4,325.000 $4,216.950 $2,350.000 $2,190.000 $4,000.000 $2,904.150
REMOV STR (BRIDGE 0 - 99 FT LENGTH)
EA 3.000 $35,000.000 $30,000.000 $21,200.000 $11,989.370 $15,000.000 $21,900.000 $15,000.000 $43,942.440
MOBILIZATION
LS 1.000 $200,000.000 $200,000.000 $216,800.000 $210,000.000 $346,600.000 $305,746.850 $225,000.000 $336,891.440
BARRICADES, SIGNS AND TRAFFIC HANDLING
MO 16.000 $3,000.000 $1,000.000 $2,350.000 $2,759.620 $1,200.000 $10,354.700 $1,500.000 $5,000.000
TEMP SEDMT CONT FENCE (INSTALL)
LF 1,983.000 $5.000 $3.000 $6.700 $5.890 $5.280 $5.200 $4.000 $5.200
TEMP SEDMT CONT FENCE (REMOVE)
LF 1,983.000 $1.000 $1.000 $2.400 $1.860 $1.500 $1.640 $2.000 $1.720
DRIVEWAYS (SURF TREAT)
SY 59.000 $55.000 $38.000 $103.000 $62.010 $88.000 $56.450 $27.700 $52.750
MTL W-BEAM GD FEN (TIM POST)
LF 275.000 $28.000 $44.000 $25.750 $43.410 $26.600 $30.660 $50.000 $37.750
MTL BEAM GD FEN TRANS (THRIE-BEAM)
EA 11.000 $2,500.000 $2,195.000 $2,715.000 $2,728.620 $2,739.000 $1,881.210 $800.000 $2,751.800
GUARDRAIL END TREATMENT (INSTALL)
EA 11.000 $3,500.000 $4,132.000 $3,400.000 $3,844.870 $3,100.000 $3,591.600 $800.000 $3,795.040
CRASH CUSH ATTEN (INSTL)(L)(N)(TL2)
EA 1.000 $25,000.000 $40,000.000 $32,000.000 $25,941.810 $29,500.000 $36,956.250 $10,000.000 $48,380.000
INSTL DEL ASSM (D-SW)SZ (BRF)CTB (BI)
EA 7.000 $35.000 $25.000 $26.000 $37.210 $23.000 $15.330 $75.000 $30.410
INSTL DEL ASSM (D-SW)SZ 1(BRF)GF2(BI)
EA 11.000 $35.000 $25.000 $31.000 $24.810 $29.000 $30.660 $75.000 $39.830
Totals: $2,107,468.500 $2,156,908.460 $2,159,529.238 $2,199,255.242 $2,302,897.226 $2,460,389.404 $2,556,123.800 $2,917,673.855