PREPARING ROW
|
STA
|
8.350
|
$2,000.000
|
$35,000.000
|
$10,000.000
|
|
|
EXCAVATION (ROADWAY)
|
CY
|
816.000
|
$9.500
|
$15.000
|
$35.000
|
|
|
EXCAVATION (CHANNEL)
|
CY
|
1,069.000
|
$15.000
|
$15.000
|
$40.000
|
|
|
EMBANKMENT (FINAL)(ORD COMP)(TY A)
|
CY
|
4,407.000
|
$13.000
|
$25.000
|
$35.000
|
|
|
EMBANKMENT (FINAL)(DENS CONT)(TY C)
|
CY
|
819.000
|
$14.000
|
$40.000
|
$45.000
|
|
|
BLADING
|
HR
|
40.000
|
$200.000
|
$105.000
|
$165.000
|
|
|
DRILL SEEDING (PERM) (RURAL) (CLAY)
|
SY
|
2,752.000
|
$1.000
|
$1.650
|
$0.750
|
|
|
DRILL SEEDING (PERM) (RURAL) (CLAY)
|
AC
|
2.200
|
$1,500.000
|
$1,650.000
|
$2,000.000
|
|
|
DRILL SEEDING (TEMP) (WARM)
|
AC
|
2.200
|
$500.000
|
$1,650.000
|
$2,000.000
|
|
|
DRILL SEEDING (TEMP) (COOL)
|
SY
|
2,752.000
|
$1.000
|
$1.650
|
$0.600
|
|
|
VEGETATIVE WATERING
|
MG
|
31.000
|
$300.000
|
$80.000
|
$25.000
|
|
|
PROOF ROLLING
|
HR
|
5.000
|
$125.000
|
$90.000
|
$100.000
|
|
|
FL BS (CMP IN PLC)(TYA GR1-2)(FNAL POS)
|
CY
|
2,362.000
|
$100.000
|
$110.000
|
$175.000
|
|
|
PRIME COAT (MC-30)
|
GAL
|
2,043.000
|
$4.500
|
$6.000
|
$8.000
|
|
|
ASPH (AC-15P)
|
GAL
|
5,907.000
|
$3.000
|
$7.000
|
$6.500
|
|
|
AGGR(TY-PD GR-3S SAC-B)
|
CY
|
28.000
|
$102.000
|
$250.000
|
$525.000
|
|
|
AGGR(TY-PD GR-3 SAC-B)
|
CY
|
49.000
|
$130.000
|
$250.000
|
$525.000
|
|
|
AGGR(TY-PD GR-4S SAC-B)
|
CY
|
21.000
|
$72.000
|
$250.000
|
$525.000
|
|
|
AGGR(TY-PD GR-4 SAC-B)
|
CY
|
45.000
|
$115.000
|
$250.000
|
$525.000
|
|
|
FLOWABLE BACKFILL
|
CY
|
64.000
|
$275.000
|
$300.000
|
$450.000
|
|
|
TEMPORARY SPL SHORING
|
SF
|
1,140.000
|
$20.000
|
$35.000
|
$20.000
|
|
|
RIPRAP (STONE PROTECTION)(12 IN)
|
CY
|
733.000
|
$200.000
|
$195.000
|
$200.000
|
|
|
RIPRAP (MOW STRIP)(4 IN)
|
CY
|
65.000
|
$750.000
|
$700.000
|
$650.000
|
|
|
RAIL (TY T223)
|
LF
|
152.000
|
$175.000
|
$100.000
|
$250.000
|
|
|
RAIL (TY T631)
|
LF
|
623.000
|
$105.000
|
$114.730
|
$100.000
|
|
|
CONC BOX CULV (8 FT X 4 FT)
|
LF
|
60.000
|
$750.000
|
$1,380.000
|
$1,400.000
|
|
|
CONC BOX CULV (10 FT X 5 FT)
|
LF
|
93.000
|
$1,200.000
|
$1,992.000
|
$1,600.000
|
|
|
CONC BOX CULV (10 FT X 6 FT)
|
LF
|
210.000
|
$1,200.000
|
$2,071.500
|
$1,700.000
|
|
|
CONC BOX CULV (8 FT X 3 FT)
|
LF
|
60.000
|
$560.000
|
$1,303.500
|
$1,400.000
|
|
|
CONC BOX CULV (12 FT X 5 FT)
|
LF
|
90.000
|
$1,000.000
|
$2,569.500
|
$2,000.000
|
|
|
CONCRETE BOX CULVERT (12 FT X 7 FT)
|
LF
|
180.000
|
$1,000.000
|
$2,790.000
|
$2,200.000
|
|
|
WINGWALL (FW - 0) (HW=8 FT)
|
EA
|
1.000
|
$22,000.000
|
$42,525.000
|
$35,000.000
|
|
|
WINGWALL (FW - S) (HW=7 FT)
|
EA
|
2.000
|
$20,000.000
|
$27,600.000
|
$25,000.000
|
|
|
WINGWALL (PW - 1) (HW=10 FT)
|
EA
|
1.000
|
$45,000.000
|
$54,075.000
|
$60,000.000
|
|
|
WINGWALL (PW - 1) (HW=5 FT)
|
EA
|
2.000
|
$19,075.000
|
$20,850.000
|
$26,000.000
|
|
|
WINGWALL (PW - 1) (HW=7 FT)
|
EA
|
2.000
|
$44,000.000
|
$34,275.000
|
$50,000.000
|
|
|
WINGWALL (PW - 1) (HW=9 FT)
|
EA
|
2.000
|
$30,000.000
|
$62,475.000
|
$70,000.000
|
|
|
SET (TY I)(S= 8 FT)(HW= 5 FT)(4:1) (C)
|
EA
|
4.000
|
$12,500.000
|
$19,456.500
|
$20,000.000
|
|
|
REMOV STR (BRIDGE 0 - 99 FT LENGTH)
|
EA
|
6.000
|
$20,000.000
|
$18,500.000
|
$40,000.000
|
|
|
MOBILIZATION
|
LS
|
1.000
|
$306,757.250
|
$425,000.000
|
$450,000.000
|
|
|
BARRICADES, SIGNS AND TRAFFIC HANDLING
|
MO
|
22.000
|
$3,500.000
|
$6,500.000
|
$10,000.000
|
|
|
ROCK FILTER DAMS (INSTALL) (TY 3)
|
LF
|
854.000
|
$50.000
|
$65.000
|
$100.000
|
|
|
ROCK FILTER DAMS (REMOVE)
|
LF
|
854.000
|
$13.000
|
$20.000
|
$30.000
|
|
|
CONSTRUCTION EXITS (INSTALL) (TY 1)
|
SY
|
624.000
|
$30.000
|
$38.500
|
$25.000
|
|
|
CONSTRUCTION EXITS (REMOVE)
|
SY
|
624.000
|
$10.000
|
$16.500
|
$10.000
|
|
|
BACKHOE WORK (EROSION & SEDMT CONT)
|
HR
|
7.900
|
$70.000
|
$100.000
|
$200.000
|
|
|
TEMP SEDMT CONT FENCE (INSTALL)
|
LF
|
1,763.000
|
$3.000
|
$5.000
|
$6.000
|
|
|
TEMP SEDMT CONT FENCE (REMOVE)
|
LF
|
1,763.000
|
$1.000
|
$3.000
|
$2.000
|
|
|
CONSTRUCTING DETOURS
|
SY
|
7,116.000
|
$85.000
|
$60.000
|
$50.000
|
|
|
ONE-WAY TRAF CONT (FLAGGER CONT)
|
HR
|
896.000
|
$100.000
|
$85.000
|
$50.000
|
|
|
PORT CTB (FUR & INST)(LOW PROF)(TY 1)
|
LF
|
2,060.000
|
$35.000
|
$50.000
|
$85.000
|
|
|
PORT CTB (FUR & INST)(LOW PROF)(TY 2)
|
LF
|
120.000
|
$35.000
|
$50.000
|
$125.000
|
|
|
PORT CTB (MOVE)(LOW PROF)(TY 1)
|
LF
|
3,660.000
|
$7.000
|
$20.000
|
$10.000
|
|
|
PORT CTB (MOVE)(LOW PROF)(TY 2)
|
LF
|
320.000
|
$10.000
|
$20.000
|
$40.000
|
|
|
PORT CTB (STKPL)(LOW PROF)(TY 1)
|
LF
|
1,980.000
|
$8.000
|
$20.000
|
$12.000
|
|
|
PORT CTB (STKPL)(LOW PROF)(TY 2)
|
LF
|
40.000
|
$10.000
|
$20.000
|
$40.000
|
|
|
PORT CTB (REMOVE)(LOW PROF)(TY 1)
|
LF
|
1,960.000
|
$17.000
|
$20.000
|
$10.000
|
|
|
PORT CTB (REMOVE)(LOW PROF)(TY 2)
|
LF
|
80.000
|
$17.000
|
$20.000
|
$16.000
|
|
|
MTL W-BEAM GD FEN (TIM POST)
|
LF
|
1,437.500
|
$28.000
|
$26.180
|
$26.520
|
|
|
MTL BEAM GD FEN TRANS (THRIE-BEAM)
|
EA
|
3.000
|
$2,000.000
|
$2,535.500
|
$2,500.000
|
|
|
TL-3 31" SHORT RADIUS (COMPLETE)
|
EA
|
1.000
|
$21,000.000
|
$29,597.700
|
$30,000.000
|
|
|
GUARDRAIL END TREATMENT (INSTALL)
|
EA
|
19.000
|
$3,400.000
|
$3,657.500
|
$4,000.000
|
|
|
REMOVE SM RD SN SUP&AM
|
EA
|
8.000
|
$120.000
|
$110.000
|
$100.000
|
|
|
INSTL DEL ASSM (D-SW)SZ 1(BRF)GF2(BI)
|
EA
|
16.000
|
$35.000
|
$65.000
|
$75.000
|
|
|
INSTL OM ASSM (OM-2Z)(WFLX)GND(BI)
|
EA
|
16.000
|
$70.000
|
$126.500
|
$100.000
|
|
Totals: |
$3,374,329.750
|
$4,871,880.840
|
$4,917,131.200
|