Job Info for 0922-00-066

County: WEBB Highway: VA Date: 08/05/2020 (4 years ago) Engineer's Estimate: $2,790,115 Control Number: 0922-00-066
Project: STP 2B20(133) District: LAREDO Time: 244 WORKING DAYS Type: UPGRADE BRIDGE RAIL AND MBGF

Bidders

Name Total Amount Place Over/Under Est Amt Left From Low Bid Delta Between Bidders
Engineer's Estimate $2,790,115.02
RELMCO, INC.   $2,347,169.08 1
-15.88% | -$442,945.94
VECTOR UTILITIES LLC   $2,418,596.80 2
-13.32% | -$371,518.22
3.04% | $71,427.72
FNH CONSTRUCTION, LLC   $3,581,955.00 3
28.38% | $791,839.98
52.61% | $1,234,785.92
48.10% | $1,163,358.20
ALTUS CONSTRUCTION LLC   $4,043,914.21 4
44.94% | $1,253,799.19
72.29% | $1,696,745.13
12.90% | $461,959.21

Bid Items

Items: 65, 0 filtered
WEBB VA  |  LAREDO  |  0922-00-066  |  08/05/2020  |  $2,790,115  |  STP 2B20(133)  |  UPGRADE BRIDGE RAIL AND MBGF  |  244 WORKING DAYS
Item code Description Unit Quantity Engineer's Estimate RELMCO, INC. VECTOR UTILITIES LLC FNH CONSTRUCTION, LLC ALTUS CONSTRUCTION LLC
104 6010 REMOVING CONC (RIPRAP) CY 6.000 $150.000 $76.160 $8.860 $250.000 $95.570
132 6001 EMBANKMENT (FINAL)(ORD COMP)(TY A) CY 21.000 $30.000 $75.000 $52.930 $35.000 $127.430
134 6001 BACKFILL (TY A) STA 39.000 $145.000 $224.000 $156.600 $450.000 $509.710
432 6001 RIPRAP (CONC)(4 IN) CY 7.000 $400.000 $615.000 $508.590 $550.000 $764.560
432 6002 RIPRAP (CONC)(5 IN) CY 151.000 $450.000 $475.000 $517.740 $550.000 $637.130
432 6045 RIPRAP (MOW STRIP)(4 IN) CY 145.000 $500.000 $485.000 $543.910 $550.000 $637.130
438 6001 CLEANING AND SEALING EXISTING JOINTS LF 1,895.000 $20.000 $45.000 $33.480 $50.000 $51.570
451 6005 RETROFIT RAIL (TY T221) LF 720.000 $180.000 $135.000 $155.140 $150.000 $254.850
451 6019 RETROFIT RAIL (TY T631) LF 2,900.000 $100.000 $87.000 $89.950 $125.000 $102.690
451 6024 RETROFIT RAIL (TY SSTR) LF 562.000 $200.000 $130.000 $155.470 $185.000 $254.850
467 6177 SET (TY I)(S= 5 FT)(HW= 4 FT)(4:1) (C) EA 8.000 $8,000.000 $7,500.000 $8,746.800 $14,000.000 $11,340.970
467 6182 SET (TY I)(S= 5 FT)(HW= 5 FT)(4:1) (C) EA 2.000 $9,000.000 $9,000.000 $10,049.510 $15,000.000 $12,105.530
467 6186 SET (TY I)(S= 5 FT)(HW= 6 FT)(4:1) (C) EA 4.000 $10,000.000 $10,500.000 $10,751.330 $16,000.000 $12,742.660
467 6219 SET (TY I)(S= 6 FT)(HW= 5 FT)(4:1) (C) EA 3.000 $10,000.000 $10,250.000 $11,628.810 $16,500.000 $15,291.190
467 6249 SET (TY I)(S= 7 FT)(HW= 5 FT)(4:1) (C) EA 12.000 $14,000.000 $11,005.000 $11,905.220 $17,000.000 $17,839.730
467 6254 SET (TY I)(S= 7 FT)(HW= 6 FT)(4:1) (C) EA 18.000 $16,000.000 $11,500.000 $12,276.690 $17,500.000 $20,388.260
467 6257 SET (TY I)(S= 7 FT)(HW= 7 FT)(4:1) (C) EA 11.000 $18,000.000 $12,250.000 $13,187.320 $18,000.000 $22,936.790
467 6280 SET (TY I)(S= 8 FT)(HW= 6 FT)(4:1) (C) EA 6.000 $17,000.000 $11,125.000 $15,146.240 $18,500.000 $24,848.190
467 6284 SET (TY I)(S= 8 FT)(HW= 7 FT)(4:1) (C) EA 1.000 $19,000.000 $14,939.470 $20,357.860 $19,000.000 $25,485.320
467 6287 SET (TY I)(S= 8 FT)(HW= 8 FT)(4:1) (C) EA 2.000 $20,000.000 $16,500.000 $20,920.160 $25,000.000 $31,856.660
467 6547 SET (TY II) (DES 4) (CMP) (4: 1) (C) EA 3.000 $2,500.000 $2,000.000 $3,149.940 $5,000.000 $6,371.330
480 6001 CLEAN EXIST CULVERTS EA 20.000 $2,500.000 $2,500.000 $2,790.220 $1,500.000 $2,563.350
496 6005 REMOV STR (WINGWALL) EA 20.000 $2,000.000 $621.600 $1,171.890 $2,500.000 $1,840.790
496 6006 REMOV STR (HEADWALL) EA 1.000 $1,000.000 $842.800 $2,008.950 $2,500.000 $1,769.040
496 6007 REMOV STR (PIPE) LF 6.000 $100.000 $76.150 $1.120 $30.000 $25.400
496 6008 REMOV STR (BOX CULVERT) LF 417.000 $100.000 $67.080 $61.380 $150.000 $86.750
496 6100 REMOVE STR (GABION) LF 30.000 $100.000 $24.550 $117.190 $250.000 $118.760
500 6001 MOBILIZATION LS 1.000 $210,000.000 $220,000.000 $164,000.000 $360,000.000 $401,393.870
502 6001 BARRICADES, SIGNS AND TRAFFIC HANDLING MO 13.000 $5,000.000 $5,000.000 $2,790.220 $8,500.000 $19,113.990
506 6003 ROCK FILTER DAMS (INSTALL) (TY 3) LF 915.000 $48.000 $25.000 $49.670 $30.000 $106.070
506 6011 ROCK FILTER DAMS (REMOVE) LF 915.000 $12.500 $15.000 $21.210 $15.000 $34.510
506 6020 CONSTRUCTION EXITS (INSTALL) (TY 1) SY 819.000 $24.500 $15.000 $24.550 $30.000 $19.660
506 6024 CONSTRUCTION EXITS (REMOVE) SY 819.000 $9.000 $8.000 $13.390 $15.000 $7.650
506 6030 BACKHOE WORK (EROSION & SEDMT CONT) HR 21.000 $70.000 $25.000 $112.260 $150.000 $191.140
506 6038 TEMP SEDMT CONT FENCE (INSTALL) LF 660.000 $2.250 $5.350 $5.580 $4.000 $5.100
506 6039 TEMP SEDMT CONT FENCE (REMOVE) LF 660.000 $0.650 $2.400 $2.510 $2.000 $1.270
510 6001 ONE-WAY TRAF CONT (FLAGGER CONT) HR 384.000 $90.000 $101.850 $137.120 $150.000 $191.140
510 6003 ONE-WAY TRAF CONT (PORT TRAF SIG) MO 5.000 $5,000.000 $4,000.000 $4,464.340 $5,000.000 $12,742.660
512 6072 PTB (FRN&INSTL)(SGL SLP)(TY 1) OR (STL) LF 1,500.000 $90.000 $30.000 $30.870 $100.000 $82.830
512 6074 PTB (MOVE)(SGL SLP)(TY 1) OR (STL) LF 2,940.000 $12.000 $15.000 $8.510 $20.000 $31.860
512 6076 PTB (REMOVE)(SGL SLP)(TY 1) OR (STL) LF 1,500.000 $15.000 $25.000 $8.760 $20.000 $31.860
540 6001 MTL W-BEAM GD FEN (TIM POST) LF 2,125.000 $20.000 $22.430 $23.400 $25.000 $25.230
540 6006 MTL BEAM GD FEN TRANS (THRIE-BEAM) EA 11.000 $2,000.000 $1,481.470 $1,545.280 $1,850.000 $1,834.940
542 6001 REMOVE METAL BEAM GUARD FENCE LF 2,150.000 $3.000 $1.150 $1.210 $3.000 $1.400
542 6002 REMOVE TERMINAL ANCHOR SECTION EA 2.000 $250.000 $215.070 $224.340 $500.000 $254.850
542 6005 RM MTL BM GD FEN TRANS (T101) EA 12.000 $200.000 $379.850 $396.210 $500.000 $286.710
544 6001 GUARDRAIL END TREATMENT (INSTALL) EA 15.000 $2,700.000 $3,017.980 $3,147.980 $2,850.000 $3,236.640
544 6003 GUARDRAIL END TREATMENT (REMOVE) EA 14.000 $250.000 $401.250 $418.530 $1,000.000 $477.850
545 6003 CRASH CUSH ATTEN (MOVE & RESET) EA 14.000 $750.000 $665.000 $552.460 $5,000.000 $1,363.460
545 6005 CRASH CUSH ATTEN (REMOVE) EA 2.000 $500.000 $875.000 $419.650 $2,500.000 $879.240
545 6019 CRASH CUSH ATTEN (INSTL)(S)(N)(TL3) EA 3.000 $7,000.000 $7,500.000 $7,696.530 $12,500.000 $10,894.980
658 6049 INSTL OM ASSM (OM-2Z)(FLX)GND(BI) EA 16.000 $100.000 $6.680 $83.710 $100.000 $95.570
658 6062 INSTL DEL ASSM (D-SW)SZ 1(BRF)GF2(BI) EA 85.000 $30.000 $2.510 $55.800 $100.000 $63.710
662 6050 WK ZN PAV MRK REMOV (REFL) TY II-A-A EA 1,920.000 $3.300 $3.210 $3.350 $15.000 $4.700
662 6063 WK ZN PAV MRK REMOV (W)4"(SLD) LF 9,422.000 $0.660 $0.640 $0.670 $2.000 $1.340
662 6075 WK ZN PAV MRK REMOV (W)24"(SLD) LF 192.000 $6.000 $8.560 $8.930 $20.000 $5.100
662 6095 WK ZN PAV MRK REMOV (Y)4"(SLD) LF 51,200.000 $1.000 $0.640 $0.670 $1.000 $1.020
662 6110 WK ZN PAV MRK SHT TERM (TAB)TY Y EA 1,280.000 $1.000 $0.160 $1.670 $5.000 $4.740
666 6312 RE PM W/RET REQ TY I (Y)4"(BRK)(100MIL) LF 4,378.000 $0.300 $0.530 $0.560 $1.000 $1.200
666 6315 RE PM W/RET REQ TY I (Y)4"(SLD)(100MIL) LF 35,022.000 $0.300 $0.530 $0.520 $1.000 $1.150
677 6001 ELIM EXT PAV MRK & MRKS (4") LF 17,511.000 $0.500 $0.500 $0.520 $1.000 $1.150
677 6028 ELIM EXT PV MRK & MRKS (RUMBLE STRIP) LF 960.000 $10.000 $8.560 $8.930 $4.000 $3.820
6001 6002 PORTABLE CHANGEABLE MESSAGE SIGN EA 4.000 $15,000.000 $10,000.000 $7,254.560 $16,500.000 $9,557.000
6056 6001 PREFORMED IN-LANE(TRANS) RUMBLE STRIP LF 960.000 $10.000 $14.980 $15.630 $2.000 $25.490
6185 6002 TMA (STATIONARY) DAY 100.000 $250.000 $175.000 $156.250 $250.000 $509.710
Totals: $2,790,115.02 $2,347,169.08 $2,418,596.80 $3,581,955.00 $4,043,914.21