Job Info for 0018-06-212

County: WEBB Highway: IH 35 Date: 02/01/2023 (1 year ago) Engineer's Estimate: $31,488,481 Control Number: 0018-06-212
Project: C 18-6-212 District: LAREDO Time: 315 WORKING DAYS Type: RESURFACE ROADWAY
HCS
Pay Estimates: 1 | 2 | 3 | 4 | 5 | 6 | 7 | 8 | 9 | 10 | 11 | 12 | 13 | 14
Plans: Plans | Revision | Proposal

Bidders

Name Total Amount Place Over/Under Est Amt Left From Low Bid Delta Between Bidders
Engineer's Estimate $31,488,480.95
ANDERSON COLUMBIA CO., INC.   $29,750,032.69 1
-5.52% | -$1,738,448.26
TEXAS MATERIALS GROUP, INC.   $31,585,467.64 2
0.31% | $96,986.69
6.17% | $1,835,434.95
HUNTER INDUSTRIES, LTD.   $40,022,446.45 3
27.1% | $8,533,965.50
34.53% | $10,272,413.76
26.71% | $8,436,978.81
Subcontractor Percentage Amount
K. L. DURHAM CONSTRUCTION, L.L.C. 2.53% $752,675.83
RPV CONSTRUCTION, LLC 1.77% $526,575.58
HIGHWAY BARRICADES AND SERVICES, LLC 1.30% $386,750.42
TEXAS ICON CONSTRUCTION, LLC 1.30% $386,750.42
CHEROKEE SERVICES 0.38% $113,050.12
SURFACE PREPARATION TECHNOLOGIES, LLC 0.13% $38,675.04
TRP CONSTRUCTION GROUP, LLC 0.01% $2,975.00
Total: 7.42% $2,207,452.41

Bid Items

Items: 52, 0 filtered
WEBB IH 35  |  LAREDO  |  0018-06-212  |  02/01/2023  |  $31,488,481  |  C 18-6-212  |  RESURF ROADWAY  |  315 WORKING DAYS
Item code Description Unit Quantity Engineer's Estimate ANDERSON COLUMBIA CO., INC. TEXAS MATERIALS GROUP, INC. HUNTER INDUSTRIES, LTD.
134 6002 BACKFILL (TY B) STA 1,761.370 $124.000 $100.000 $135.000 $157.500
150 6002 BLADING HR 120.000 $160.000 $180.000 $150.000 $140.400
351 6001 FLEXIBLE PAVEMENT STRUCTURE REPAIR(5") SY 42,058.000 $35.320 $28.000 $35.000 $55.930
351 6004 FLEXIBLE PAVEMENT STRUCTURE REPAIR(8") SY 17,086.000 $55.000 $47.000 $58.000 $88.340
354 6025 PLANE ASPH CONC PAV(4" TO 6") SY 32,955.000 $4.000 $3.600 $4.550 $6.710
354 6048 PLANE ASPH CONC PAV (3") SY 916,212.000 $1.300 $1.700 $1.650 $2.390
354 6125 PLANE ASPH CONC PAV (0" TO 5.5") SY 3,697.000 $7.000 $4.000 $4.000 $7.790
354 6221 PLANE ASPH CONC PAV(MICRO)(0"-3") SY 8,447.000 $8.000 $8.000 $3.750 $4.550
432 6045 RIPRAP (MOW STRIP)(4 IN) CY 727.000 $650.000 $535.000 $625.000 $700.000
438 6001 CLEANING AND SEALING EXISTING JOINTS LF 4,098.000 $35.000 $31.000 $32.000 $36.000
451 6048 RETROFIT RAIL (ADD HSS) LF 2,729.740 $110.000 $110.000 $105.000 $120.000
500 6001 MOBILIZATION LS 1.000 $2,334,076.810 $1,597,000.000 $1,892,829.000 $3,386,174.000
502 6001 BARRICADES, SIGNS AND TRAFFIC HANDLING MO 16.000 $4,000.000 $1,500.000 $2,500.000 $1,919.460
510 6001 ONE-WAY TRAF CONT (FLAGGER CONT) HR 280.000 $150.000 $75.000 $75.000 $128.700
533 6003 RUMBLE STRIPS (SHOULDER) ASPHALT LF 414,924.000 $0.150 $0.100 $0.150 $0.120
540 6001 MTL W-BEAM GD FEN (TIM POST) LF 2,175.000 $28.050 $28.000 $23.750 $26.240
540 6006 MTL BEAM GD FEN TRANS (THRIE-BEAM) EA 17.000 $2,000.000 $2,100.000 $2,350.000 $3,259.660
540 6010 MTL W-BEAM GD FEN ADJUSTMENT LF 450.000 $28.050 $15.000 $13.000 $14.360
540 6011 MTL THRIE-BEAM GD FEN ADJUSTMENT LF 4.000 $130.000 $900.000 $500.000 $552.480
540 6016 DOWNSTREAM ANCHOR TERMINAL SECTION EA 6.000 $1,280.000 $1,400.000 $1,150.000 $1,270.710
540 6031 DOWNSTREAM ANCHOR TERMINAL ADJUSTMENT EA 2.000 $125.000 $400.000 $400.000 $441.990
540 6037 MTL BM GD FEN TRANS (ANCHOR PLATE) EA 2.000 $950.000 $800.000 $550.000 $607.730
542 6001 REMOVE METAL BEAM GUARD FENCE LF 2,150.000 $2.400 $2.000 $1.500 $1.660
542 6002 REMOVE TERMINAL ANCHOR SECTION EA 3.000 $250.000 $180.000 $150.000 $165.750
542 6003 REMOVE DOWNSTREAM ANCHOR TERMINAL EA 1.000 $450.000 $180.000 $100.000 $110.500
542 6004 RM MTL BM GD FENCE TRANS (THRIE-BEAM) EA 14.000 $260.000 $210.000 $100.000 $110.500
544 6001 GUARDRAIL END TREATMENT (INSTALL) EA 32.000 $2,900.000 $3,100.000 $2,795.000 $3,088.390
544 6002 GUARDRAIL END TREATMENT (MOVE & RESET) EA 2.000 $1,250.000 $825.000 $500.000 $552.480
544 6003 GUARDRAIL END TREATMENT (REMOVE) EA 32.000 $300.000 $270.000 $200.000 $220.990
658 6061 INSTL DEL ASSM (D-SW)SZ 1(BRF)GF2 EA 23.000 $40.000 $48.000 $35.000 $35.000
658 6064 INSTL DEL ASSM (D-SY)SZ 1(BRF)GF2 EA 2.000 $50.000 $48.000 $35.000 $35.000
662 6109 WK ZN PAV MRK SHT TERM (TAB)TY W EA 33,671.000 $1.500 $1.500 $1.200 $1.600
666 6018 REFL PAV MRK TY I (W)6"(DOT)(100MIL) LF 507.000 $2.000 $0.850 $0.850 $0.850
666 6036 REFL PAV MRK TY I (W)8"(SLD)(100MIL) LF 10,550.000 $1.100 $1.250 $1.250 $1.250
666 6042 REFL PAV MRK TY I (W)12"(SLD)(100MIL) LF 3,616.000 $4.000 $2.850 $2.850 $2.850
666 6054 REFL PAV MRK TY I (W)(ARROW)(100MIL) EA 3.000 $155.000 $175.000 $175.000 $175.000
666 6078 REFL PAV MRK TY I (W)(WORD)(100MIL) EA 18.000 $172.000 $225.000 $225.000 $225.000
666 6225 PAVEMENT SEALER 6" LF 15,704.000 $0.200 $0.350 $0.350 $0.350
666 6306 RE PM W/RET REQ TY I (W)6"(BRK)(100MIL) LF 67,265.000 $0.700 $0.570 $0.570 $0.570
666 6309 RE PM W/RET REQ TY I (W)6"(SLD)(100MIL) LF 214,253.000 $0.400 $0.550 $0.550 $0.550
666 6321 RE PM W/RET REQ TY I (Y)6"(SLD)(100MIL) LF 222,010.000 $0.400 $0.550 $0.550 $0.550
666 6350 REFL PAV MRK TY I (W)12"(DOT)(100MIL) LF 1,163.000 $4.550 $2.850 $2.850 $2.850
672 6010 REFL PAV MRKR TY II-C-R EA 3,582.000 $4.250 $3.850 $3.850 $3.850
677 6001 ELIM EXT PAV MRK & MRKS (4") LF 14,320.000 $0.450 $0.500 $0.500 $0.500
678 6002 PAV SURF PREP FOR MRK (6") LF 14,871.000 $0.200 $0.040 $0.040 $0.040
3080 6001 STONE-MTRX-ASPH SMA-C SAC-A PG76-22 TON 167,569.000 $129.000 $124.000 $128.500 $155.340
3084 6001 BONDING COURSE GAL 194,283.000 $2.500 $2.250 $3.300 $2.280
4106 6007 POLYESTER POLYMER CONC OVERLAY (1") SY 9,058.000 $120.000 $138.000 $142.000 $175.000
6001 6002 PORTABLE CHANGEABLE MESSAGE SIGN EA 4.000 $9,900.000 $20,200.000 $8,000.000 $7,500.000
6158 6001 TMSP RADAR SPEED CONTROL MONITOR EA 2.000 $12,000.000 $8,640.000 $14,500.000 $8,500.000
6185 6002 TMA (STATIONARY) DAY 287.000 $250.000 $168.000 $175.000 $200.000
6185 6003 TMA (MOBILE OPERATION) HR 1,380.000 $70.000 $56.000 $80.000 $75.000
Totals: $31,488,480.95 $29,750,032.69 $31,585,467.64 $40,022,446.46