WASHINGTON PR0012 (6414-36-001)

Items: 59

County: WASHINGTON
Length: N/A
Highway: PR0012
District: BRYAN
Control Number: 6414-36-001
DBE Goal: N/A
Project: RMC - 641436001
Guaranty: N/A
Time: 92 W
Engineer's Estimate: $630,048.92
Date: 02/02/2023 (3 years ago)
Contract Number: N/A
Type: ROADWAY ENTRANCE & WALL, LIGHTING & LANDSCAPING
Mail/Deliver Bids To: N/A
JAMES KREAMER
ROSS MCCALL
Actions:
Notice HCS Excel Tabs Print Print Notice
Documents:
Bidders (2)
E
Engineer's Estimate
$630,048.92
$899,167.10
Over/Under Est: 42.71% $269,118.18
Over/Under Est: 127.36% $802,447.76
Amt Left: 59.31% $533,329.58
Subcontractor Percentage Amount
BAYER CONSTRUCTION ELECTRICAL CONTRACTORS, INC. 0.00% $0.00
BROCK CONSTRUCTION, LLC 0.00% $0.00
CEN TEX HYDROSEED, INC. 0.00% $0.00
DAVID & DEIKE INTERESTS, L.L.C. 0.00% $0.00
JASON STORM LLC 0.00% $0.00
Total: 0.00% $0.00

Bid Items & Bid Tabulations

59 Total 0 of 59
WASHINGTON  |  PR0012  |  BRYAN  |  6414-36-001  |  02/02/2023  |  $630,048.92  |  RMC - 641436001  |  ROADWAY ENTRANCE & WALL, LIGHTING &...  |  92 W
Item Code
Description
Unit
Quantity
Engineer's Estimate
TEXAS MATERIALS GROUP, INC.
SPAWGLASS CIVIL CONSTRUCTION, INC.
PREP ROW (TREE)(GREATER THAN 24" DIA)
EA 2.000 $2,480.000 $6,300.000 $5,088.080
PREPARING ROW (HAND CLEARING)
AC 0.170 $10,700.000 $40,000.000 $5,985.940
REMOVING CONC (MISC)
SY 13.000 $400.000 $220.000 $442.960
REMOVING STAB BASE AND ASPH PAV (2")
SY 324.000 $8.000 $28.000 $18.480
EXCAVATION (ROADWAY)
CY 206.000 $15.000 $50.000 $70.250
EMBANKMENT (FINAL)(ORD COMP)(TY A)
CY 101.000 $8.000 $110.000 $90.730
EROSION CONTROL COMPOST
CY 3.000 $19.000 $750.000 $63.450
BROADCAST SEED (PERM) (RURAL) (SANDY)
SY 1,089.000 $0.120 $1.500 $0.290
VEGETATIVE WATERING
MG 5.040 $25.000 $600.000 $101.760
IRRIGATION SYSTEM
LS 1.000 $27,400.000 $12,000.000 $11,630.760
WILDFLOWER SEEDING
AC 0.140 $1,200.000 $5,000.000 $1,029.640
PLANT MATERIAL (1-GAL)
EA 110.000 $20.000 $14.000 $12.990
PLANT MATERIAL (5-GAL)
EA 29.000 $30.000 $39.000 $30.230
PLANT SOIL MIX
CY 29.000 $70.000 $190.000 $69.440
PLANT MATERIAL (200 GAL) (TREE)
EA 4.000 $3,000.000 $4,000.000 $3,238.410
PLANT MAINTENANCE
MO 6.000 $500.000 $500.000 $1,556.360
FL BS (CMP IN PLACE)(TY A GR 1-2)(8")
SY 692.000 $16.000 $70.000 $31.120
CEMENT
TON 8.000 $245.000 $300.000 $235.900
CEMENT TREAT (NEW BASE) (6")
SY 30.000 $4.000 $150.000 $175.490
CEMENT TREAT(EXIST MATL)(8")
SY 715.000 $5.000 $14.000 $29.450
PRIME COAT (RC-250)
GAL 173.000 $7.000 $16.000 $23.940
AGGR (TY-B GR-5 OR TY-L GR-5)
CY 11.000 $156.000 $750.000 $179.580
RIPRAP (CONC)(4 IN)
CY 0.150 $700.000 $6,400.000 $109,689.130
RC PIPE (CL III)(24 IN)
LF 130.000 $100.000 $137.000 $72.740
SET (TY II) (24 IN) (RCP) (6: 1) (C)
EA 2.000 $1,500.000 $2,700.000 $1,710.220
PIPE (PVC) (SCH 80) (6 IN)
LF 30.000 $50.000 $125.000 $95.360
REMOV STR (ROCKWALL)
EA 3.000 $1,000.000 $4,500.000 $1,316.910
REMOV STR (SMALL FENCE)
LF 332.000 $6.000 $4.800 $15.150
REMOV STR (FLAG POLE)
EA 1.000 $10.000 $1,000.000 $299.300
REMOV STR (DRIVEWAY CULVERT)
EA 1.000 $600.000 $2,300.000 $2,753.550
MOBILIZATION
LS 1.000 $64,241.460 $85,000.000 $248,181.330
BARRICADES, SIGNS AND TRAFFIC HANDLING
MO 6.000 $5,000.000 $2,800.000 $7,562.100
TEMP SEDMT CONT FENCE (INSTALL)
LF 425.000 $4.000 $5.000 $2.390
TEMP SEDMT CONT FENCE (REMOVE)
LF 425.000 $2.000 $2.000 $2.630
COLORED TEXTURED CONC (6")
SY 118.000 $110.000 $300.000 $456.540
CONC CURB & GUTTER (TY I)
LF 331.000 $165.000 $85.000 $108.640
CONDT (PVC) (SCH 40) (1/2")
LF 300.000 $8.430 $10.000 $18.480
CONDT (PVC) (SCH 40) (1 1/4")
LF 160.000 $24.750 $15.000 $22.240
ELEC CONDR (NO.12) INSULATED
LF 2,235.000 $1.030 $1.000 $1.840
GROUND BOX TY A (122311)
EA 4.000 $916.550 $1,300.000 $719.430
ELC SRV TY D 120/240 060(NS)AL(E)PS(U)
EA 1.000 $5,393.530 $5,500.000 $13,441.360
IN SM RD SN SUP&AM TY10BWG(1)SA(P)
EA 1.000 $708.000 $900.000 $863.930
RELOCATE SM RD SN SUP&AM TY 10BWG
EA 2.000 $770.000 $700.000 $1,119.380
REFL PAV MRK TY I (W)24"(SLD)(100MIL)
LF 26.000 $12.000 $15.000 $10.090
REFL PAV MRK TY I (Y)8"(SLD)(100MIL)
LF 330.000 $2.000 $5.000 $10.090
DITCH CLEANING AND RESHAPING (FOOT)
LF 60.000 $5.000 $60.000 $76.360
LANDSCAPE AMENITY (TY 1)
EA 1.000 $149,800.000 $140,000.000 $355,978.770
LANDSCAPE AMENITY (TY 2)
EA 2.000 $21,200.000 $50,000.000 $98,117.010
LANDSCAPE AMENITY (TY 3)
EA 2.000 $2,400.000 $12,000.000 $5,713.620
LANDSCAPE AMENITY (TY 4)
EA 19.000 $1,000.000 $1,200.000 $2,153.130
LANDSCAPE AMENITY (TY 5)
EA 92.000 $200.000 $700.000 $550.450
LANDSCAPE AMENITY (TY 6)
EA 4.000 $2,400.000 $1,500.000 $1,549.240
LANDSCAPE AMENITY (TY 7)
EA 2.000 $600.000 $2,400.000 $888.890
TREE PROTECTION
EA 7.000 $900.000 $400.000 $502.150
D-GR HMA TY-D PG64-22
TON 152.000 $231.000 $190.000 $199.330
D-GR HMA TY-D SAC-A PG76-28
TON 330.000 $94.000 $200.000 $263.380
D-GR HMA TY-F PG64-22
TON 73.000 $134.000 $210.000 $251.410
BONDING COURSE
GAL 136.000 $6.000 $10.000 $10.180
TMA (STATIONARY)
DAY 30.000 $225.000 $200.000 $549.030
Totals: $630,048.920 $899,167.100 $1,432,496.709