Job Info for 6422-27-001

County: WALLER Highway: FM3318 Date: 01/04/2024 (10 months ago) Changed Engineer's Estimate: $645,641 Control Number: 6422-27-001
Project: RMC - 642227001 District: HOUSTON Time: 26 W Type: ACP OVERLAY
Bidder's List
Email All | Notice | Questions
HCS
Pay Estimates: 1 | 2 | 3 | 4 | 5 | 6
Plans

Bidders

Name Total Amount Place Over/Under Est Amt Left From Low Bid Delta Between Bidders
Engineer's Estimate $645,640.85
CORNERSTONE PAVING AND CONSTRUCTION, L.L.C.   $598,559.40 1
-7.29% | -$47,081.45
TEXAS MATERIALS GROUP, INC.   $674,837.70 2
4.52% | $29,196.85
12.74% | $76,278.30
JAMES CONSTRUCTION GROUP, LLC   $676,935.70 3
4.85% | $31,294.85
13.09% | $78,376.30
0.31% | $2,098.00
DURWOOD GREENE CONSTRUCTION CO.   $683,431.30 4
5.85% | $37,790.45
14.18% | $84,871.90
0.96% | $6,495.60
HAYDEN PAVING, INC.   $726,361.35 5
12.5% | $80,720.50
21.35% | $127,801.95
6.28% | $42,930.05
BLACKSMITH VENTURES LLC   $788,299.45 6
22.1% | $142,658.60
31.7% | $189,740.05
8.53% | $61,938.10
MB WESTERN INDUSTRIAL CONTRACTING COMPANY   $966,448.57 7
49.69% | $320,807.72
61.46% | $367,889.17
22.60% | $178,149.12

Bid Items

Items: 19, 0 filtered
WALLER FM3318  |  HOUSTON  |  6422-27-001  |  01/04/2024  |  $645,641  |  RMC - 642227001  |  ACP OVERLAY  |  26 W
Item code Description Unit Quantity Engineer's Estimate CORNERSTONE PAVING AND CONSTRUCTION, L.L.C. TEXAS MATERIALS GROUP, INC. JAMES CONSTRUCTION GROUP, LLC DURWOOD GREENE CONSTRUCTION CO. HAYDEN PAVING, INC. BLACKSMITH VENTURES LLC MB WESTERN INDUSTRIAL CONTRACTING COMPANY
134 6004 BACKFILL (TY A OR B) STA 120.000 $235.000 $325.000 $172.000 $250.000 $200.000 $300.000 $250.000 $909.000
305 6015 SALV, HAUL & STKPL RCL APH PV (1 1/2") SY 31,193.000 $2.500 $1.700 $2.300 $2.000 $2.500 $1.200 $3.000 $4.370
351 6002 FLEXIBLE PAVEMENT STRUCTURE REPAIR(6") SY 500.000 $64.000 $85.000 $70.000 $61.000 $57.000 $200.000 $75.000 $71.690
500 6001 MOBILIZATION LS 1.000 $58,694.620 $27,000.000 $20,000.000 $67,000.000 $65,000.000 $85,000.000 $75,000.000 $95,000.000
502 6001 BARRICADES, SIGNS AND TRAFFIC HANDLING MO 2.000 $8,900.000 $3,000.000 $1,600.000 $15,500.000 $3,500.000 $5,000.000 $5,000.000 $3,552.000
533 6004 RUMBLE STRIPS (CENTERLINE) ASPHALT LF 11,840.000 $0.400 $0.700 $0.450 $1.000 $0.650 $0.450 $0.600 $1.030
662 6004 WK ZN PAV MRK NON-REMOV (W)4"(SLD) LF 48,612.000 $0.510 $0.290 $0.450 $0.290 $0.300 $0.300 $0.300 $0.350
662 6016 WK ZN PAV MRK NON-REMOV (W)24"(SLD) LF 24.000 $11.170 $5.000 $5.700 $5.000 $4.000 $10.000 $6.000 $6.080
662 6032 WK ZN PAV MRK NON-REMOV (Y)4"(BRK) LF 3,146.000 $0.550 $0.290 $0.350 $0.290 $0.300 $0.300 $0.300 $0.350
662 6034 WK ZN PAV MRK NON-REMOV (Y)4"(SLD) LF 26,560.000 $0.530 $0.290 $0.350 $0.290 $0.300 $0.300 $0.300 $0.350
666 6048 REFL PAV MRK TY I (W)24"(SLD)(100MIL) LF 12.000 $10.530 $10.000 $11.500 $10.000 $20.000 $15.000 $10.000 $12.150
666 6312 RE PM W/RET REQ TY I (Y)4"(BRK)(100MIL) LF 1,573.000 $1.140 $0.520 $0.600 $0.520 $0.850 $0.550 $0.550 $0.630
666 6315 RE PM W/RET REQ TY I (Y)4"(SLD)(100MIL) LF 13,280.000 $1.610 $0.520 $0.600 $0.520 $0.850 $0.550 $0.540 $0.630
666 6342 REF PROF PAV MRK TY I(W)4"(SLD)(100MIL) LF 24,306.000 $1.110 $0.920 $1.050 $0.920 $1.100 $0.950 $0.950 $1.120
672 6009 REFL PAV MRKR TY II-A-A EA 244.000 $8.730 $6.000 $6.850 $6.000 $6.000 $8.000 $6.000 $7.290
3076 6042 D-GR HMA TY-D SAC-B PG70-22 TON 2,580.000 $120.000 $135.600 $166.000 $141.000 $155.000 $145.000 $175.000 $188.330
3076 6066 TACK COAT GAL 3,461.000 $4.070 $4.000 $4.000 $2.400 $0.750 $4.500 $6.000 $5.470
6185 6002 TMA (STATIONARY) DAY 18.000 $296.000 $175.000 $275.000 $563.000 $250.000 $100.000 $250.000 $1.000
6185 6005 TMA (MOBILE OPERATION) DAY 8.000 $492.000 $175.000 $400.000 $936.000 $200.000 $500.000 $250.000 $1.000
Totals: $645,640.85 $598,559.40 $674,837.70 $676,935.70 $683,431.30 $726,361.35 $788,299.45 $966,448.57