WALKER SH0030 (6430-26-001)

Items: 44

County: WALKER
Length: N/A
Highway: SH0030
District: BRYAN
Control Number: 6430-26-001
DBE Goal: N/A
Project: RMC - 643026001
Guaranty: N/A
Time: 365 CALENDAR DAYS
Engineer's Estimate: $583,280.00
Date: 02/01/2023 (3 years ago)
Contract Number: N/A
Type: METAL BEAM GUARD FENCE REPAIR
Mail/Deliver Bids To: N/A
Actions:
Notice HCS Excel Tabs Print Print Notice
Documents:
Bidders (4)
E
Engineer's Estimate
$583,280.00
$548,925.00
Over/Under Est: -5.89% -$34,355.00
Over/Under Est: 12.91% $75,320.00
Amt Left: 19.98% $109,675.00
Over/Under Est: 13.1% $76,395.00
Amt Left: 20.18% $110,750.00
Delta: -0.16% -$1,075.00
Over/Under Est: 24.8% $144,640.00
Amt Left: 32.61% $178,995.00
Delta: -10.35% -$68,245.00

Bid Items & Bid Tabulations

44 Total 0 of 44
WALKER  |  SH0030  |  BRYAN  |  6430-26-001  |  02/01/2023  |  $583,280.00  |  RMC - 643026001  |  METAL BEAM GUARD FENCE REPAIR  |  365 CALENDAR DAYS
Item Code
Description
Unit
Quantity
Engineer's Estimate
GARRET SHIELDS INFRASTRUCTURE
ABOVE ALL CONSTRUCTION
SJ&J CONSTRUCTION, LLC
ROY JORGENSEN ASSOCIATES, INC.
RIPRAP (MOW STRIP)(4 IN)
CY 15.000 $550.000 $400.000 $450.000 $700.000 $420.000
MOBILIZATION (CALLOUT)
EA 20.000 $500.000 $1,500.000 $200.000 $3,000.000 $500.000
MTL W-BEAM GD FEN (TIM POST)
LF 75.000 $30.000 $50.000 $35.000 $28.000 $30.000
MTL W-BEAM GD FEN (STEEL POST)
LF 100.000 $38.000 $50.000 $50.000 $38.000 $40.000
MTL BEAM GD FEN TRANS (THRIE-BEAM)
EA 5.000 $2,000.000 $2,500.000 $2,000.000 $1,800.000 $2,000.000
MTL W-BEAM GD FEN ADJUSTMENT
LF 50.000 $13.000 $30.000 $20.000 $2.000 $10.000
DOWNSTREAM ANCHOR TERMINAL SECTION
EA 5.000 $1,600.000 $1,500.000 $2,000.000 $2,000.000 $1,800.000
MTL BM GD FEN TRANS (31"-28")
EA 100.000 $800.000 $600.000 $500.000 $600.000 $1,250.000
REMOVE METAL BEAM GUARD FENCE
LF 175.000 $4.000 $2.000 $5.000 $3.000 $4.000
REMOVE TERMINAL ANCHOR SECTION
EA 5.000 $200.000 $300.000 $300.000 $200.000 $500.000
REMOVE DOWNSTREAM ANCHOR TERMINAL
EA 5.000 $51.000 $200.000 $300.000 $200.000 $1.000
GUARDRAIL END TREATMENT (INSTALL)
EA 20.000 $2,800.000 $2,500.000 $3,500.000 $3,950.000 $3,500.000
GUARDRAIL END TREATMENT (REMOVE)
EA 15.000 $260.000 $500.000 $300.000 $300.000 $500.000
REPAIR RAIL ELEMENT (W - BEAM)
LF 3,500.000 $30.000 $30.000 $35.000 $19.000 $25.000
REPAIR RAIL ELEMENT (THRIE - BEAM)
LF 110.000 $30.000 $10.000 $50.000 $38.000 $35.000
REP RAIL ELMNT(THRIE-BM TRANS TO W -BM)
LF 30.000 $40.000 $200.000 $50.000 $50.000 $35.000
REPAIR RAIL ELEMENT (CURVED RAIL)
LF 25.000 $40.000 $30.000 $100.000 $50.000 $35.000
RAISE RAIL ELEMENT
LF 500.000 $15.000 $5.000 $20.000 $3.000 $10.000
REM / REPL TIMBER POST W / O CONC FND
EA 100.000 $20.000 $200.000 $100.000 $65.000 $40.000
REM / REPL STEEL POST W / O CONC FND
EA 25.000 $50.000 $45.000 $100.000 $100.000 $100.000
REM / REPL TIMBER POST W / CONC FND
EA 25.000 $30.000 $300.000 $100.000 $75.000 $40.000
REM / REPL STEEL POST W / CONC FND
EA 10.000 $150.000 $45.000 $100.000 $120.000 $100.000
REPAIR STEEL POST WITH BASE PLATE
EA 5.000 $200.000 $100.000 $300.000 $350.000 $350.000
REALIGN POSTS
EA 100.000 $30.000 $20.000 $50.000 $30.000 $15.000
REMOVE & REPLACE BLOCKOUT
EA 300.000 $30.000 $15.000 $50.000 $30.000 $25.000
REPLACE STL BLOCKOUTS W /WOOD BLOCKOUTS
EA 15.000 $5.000 $300.000 $50.000 $28.000 $25.000
REPLACE SINGLE GDRAIL TERMINAL RAIL
LF 300.000 $40.000 $50.000 $35.000 $48.000 $35.000
REPLACE SINGLE GDRAIL TERMINAL POST
EA 15.000 $100.000 $100.000 $100.000 $75.000 $80.000
REMOVE GDRAIL END TRT / REPL WITH SGT
EA 30.000 $4,500.000 $3,500.000 $4,000.000 $3,900.000 $3,500.000
REPL SINGLE GDRAIL TERM IMPACT HEAD
EA 10.000 $1,100.000 $1,000.000 $1,200.000 $1,800.000 $1,400.000
REM & RESET SGT IMPACT HEAD
EA 10.000 $150.000 $500.000 $300.000 $300.000 $300.000
REPLACE SGT CABLE ASSEMBLY
EA 10.000 $35.000 $100.000 $120.000 $90.000 $120.000
REPLACE SGT CABLE ANCHOR
EA 10.000 $20.000 $75.000 $120.000 $90.000 $100.000
REPLACE SGT STRUT
EA 10.000 $30.000 $75.000 $120.000 $90.000 $100.000
REPLACE SGT OBJECT MARKER
EA 10.000 $35.000 $20.000 $50.000 $25.000 $45.000
REMOVE AND REPLACE DAT
EA 10.000 $1,400.000 $500.000 $2,200.000 $1,900.000 $1,800.000
REPLACE POSTS (TL-4)
EA 250.000 $170.000 $5.000 $200.000 $360.000 $320.000
CABLE SPLICE / TURNBUCKLE (TL-4)
EA 10.000 $100.000 $130.000 $300.000 $400.000 $400.000
REPAIR CONCRETE FOUNDATION (TL-4)
EA 10.000 $80.000 $75.000 $500.000 $100.000 $500.000
REPR OR REPLC CABLE BARR TERM SEC(TL-4)
EA 10.000 $1,500.000 $1,500.000 $2,000.000 $1,900.000 $1,750.000
REPLACE CABLE (TL-4)
LF 400.000 $3.000 $20.000 $5.000 $10.000 $1.000
CHECK / RE-TENSION CABLE
EA 50.000 $150.000 $200.000 $500.000 $220.000 $750.000
PORTABLE CHANGEABLE MESSAGE SIGN
DAY 15.000 $180.000 $60.000 $500.000 $100.000 $1.000
TMA (STATIONARY)
DAY 50.000 $300.000 $500.000 $500.000 $220.000 $1,250.000
Totals: $583,280.000 $548,925.000 $658,600.000 $659,675.000 $727,920.000