Job Info for 6422-63-001

County: WALKER Highway: IH0045 Date: 12/01/2022 (1 year ago) Engineer's Estimate: $753,000 Control Number: 6422-63-001
Project: MMC - 642263001 District: BRYAN Time: 180 CALENDAR DAYS Type: HOT MIX
HCS
Pay Estimates: 1 | 2 | 3 | 4 | 5
Proposal

Bidders

Name Total Amount Place Over/Under Est Amt Left From Low Bid Delta Between Bidders
Engineer's Estimate $753,000.00
VULCAN CONSTRUCTION MATERIALS, LLC   $678,200.00 1
-9.93% | -$74,800.00
TEXAS MATERIALS GROUP, INC.   $714,550.00 2
-5.11% | -$38,450.00
5.36% | $36,350.00
WALLER COUNTY ASPHALT INC.   $822,100.00 3
9.18% | $69,100.00
21.22% | $143,900.00
15.05% | $107,550.00
BIG CREEK CONSTRUCTION, LTD.   $857,000.00 4
13.81% | $104,000.00
26.36% | $178,800.00
4.25% | $34,900.00

Bid Items

Items: 2, 0 filtered
WALKER IH0045  |  BRYAN  |  6422-63-001  |  12/01/2022  |  $753,000  |  MMC - 642263001  |  HOT MIX  |  180 CALENDAR DAYS
Item code Description Unit Quantity Engineer's Estimate VULCAN CONSTRUCTION MATERIALS, LLC TEXAS MATERIALS GROUP, INC. WALLER COUNTY ASPHALT INC. BIG CREEK CONSTRUCTION, LTD.
8011 6001 D-GR HMA(SQ) TY D PG 64-22 (PICKUP) TON 200.000 $90.000 $83.500 $85.000 $89.000 $85.000
8011 6002 D-GR HMA(SQ) TY D PG 64-22 (DELIVERY) TON 7,000.000 $105.000 $94.500 $99.650 $114.900 $120.000
Totals: $753,000.00 $678,200.00 $714,550.00 $822,100.00 $857,000.00