WALKER FM 2628 (6400-48-001)

Items: 22

County: WALKER
Length: 0.0100 MILES
Highway: FM 2628
District: BRYAN
Control Number: 6400-48-001
DBE Goal: N/A
Project: RMC - 640048001
Guaranty: $6,000.00
Time: 12 W
Engineer's Estimate: $299,050.00
Date: 11/12/2024 (1 year ago)
Contract Number: 11241701
Type: CULVERT REPLACEMENT
Project ID: A00186735
Project Description: THIS PROJECT IS FOR REPAIRING / REPLACING 7 CULVERTS ON FM 2628 IN WALKER COUNTY.
Mail/Deliver Bids To: N/A
MICHAEL ESTILLETTE
Actions:
Notice Questions HCS Excel Tabs Print Print Notice
Pay Estimates:
Bidders (6)
E
Engineer's Estimate
$299,050.00
$283,536.00
Over/Under Est: -5.19% -$15,514.00
Over/Under Est: 4.28% $12,785.00
Amt Left: 9.98% $28,299.00
$349,348.00
Over/Under Est: 16.82% $50,298.00
Amt Left: 23.21% $65,812.00
Delta: -12.03% -$37,513.00
Over/Under Est: 24.13% $72,150.00
Amt Left: 30.92% $87,664.00
Delta: -6.26% -$21,852.00
$425,090.00
Over/Under Est: 42.15% $126,040.00
Amt Left: 49.92% $141,554.00
Delta: -14.52% -$53,890.00
Over/Under Est: 208.51% $623,550.00
Amt Left: 225.39% $639,064.00
Delta: -117.04% -$497,510.00

Bid Items & Bid Tabulations

22 Total 0 of 22
WALKER  |  FM 2628  |  BRYAN  |  6400-48-001  |  11/12/2024  |  $299,050.00  |  RMC - 640048001  |  CULVERT REPL  |  12 W
Item Code
Description
Unit
Quantity
Engineer's Estimate
GARRET SHIELDS INFRASTRUCTURE
AAD CONTRACTING INC.
STX CIVIL
TAYLOR CONTRACTING LLC
TREVWAY, INC.
ICOS MANAGEMENT, LLC
EXCAV (ROADWAY & CHANNEL)
CY 53.000 $30.000 $50.000 $18.000 $50.000 $45.000 $102.000 $400.000
EMBANK (FNL)(OC)(TY D)
CY 54.000 $55.000 $50.000 $40.000 $54.000 $55.000 $158.000 $500.000
BROADCAST SEED (PERM_RURAL_CLAY)
SY 1,400.000 $1.000 $0.500 $1.500 $1.000 $2.000 $3.700 $2.000
FL BS (CMP IN PLC)(TYD GR1-2)(FNAL POS)
CY 136.000 $110.000 $50.000 $90.000 $139.000 $95.000 $250.000 $300.000
CUT AND RESTORE PAV (FLEX BASE)
SY 485.000 $75.000 $70.000 $45.000 $85.000 $75.000 $75.000 $300.000
CEM STABIL BKFL
CY 170.000 $190.000 $300.000 $200.000 $205.000 $350.000 $225.000 $300.000
TRENCH EXCAVATION PROTECTION
LF 243.000 $15.000 $10.000 $12.000 $10.000 $20.000 $30.000 $200.000
TEMPORARY SPL SHORING
SF 310.000 $50.000 $60.000 $15.000 $22.000 $35.000 $73.000 $100.000
RIPRAP (STONE COMMON)(DRY)(12 IN)
CY 8.000 $400.000 $300.000 $300.000 $249.000 $2,000.000 $1,000.000 $400.000
RC PIPE (CL III)(18 IN)
LF 56.000 $95.000 $100.000 $90.000 $151.000 $250.000 $231.000 $400.000
RC PIPE (CL III)(24 IN)
LF 464.000 $135.000 $140.000 $125.000 $191.000 $135.000 $145.000 $400.000
RC PIPE (CL III)(30 IN)
LF 80.000 $205.000 $160.000 $200.000 $279.000 $200.000 $349.000 $400.000
SET (TY II) (18 IN) (RCP) (4: 1) (C)
EA 2.000 $1,200.000 $1,000.000 $1,100.000 $1,762.000 $1,850.000 $2,433.000 $5,000.000
SET (TY II) (24 IN) (RCP) (4: 1) (C)
EA 18.000 $1,950.000 $1,500.000 $1,400.000 $2,587.000 $1,500.000 $3,000.000 $8,000.000
SET (TY II) (30 IN) (RCP) (3: 1) (C)
EA 2.000 $3,000.000 $2,500.000 $3,000.000 $4,098.000 $4,000.000 $4,500.000 $10,000.000
REMOV STR (PIPE)
LF 415.000 $50.000 $20.000 $50.000 $31.000 $20.000 $35.000 $200.000
MOBILIZATION
LS 1.000 $21,000.000 $25,000.000 $65,000.000 $30,000.000 $37,000.000 $35,000.000 $1,000.000
BARRICADES, SIGNS AND TRAFFIC HANDLING
MO 1.000 $4,000.000 $5,000.000 $10,000.000 $4,180.000 $25,000.000 $7,000.000 $15,000.000
PORTABLE CHANGEABLE MESSAGE SIGN
DAY 46.000 $150.000 $1.000 $300.000 $69.000 $150.000 $400.000 $500.000
TMA (STATIONARY)
DAY 12.000 $300.000 $300.000 $300.000 $313.000 $500.000 $500.000 $1,000.000
TEMP SEDMT CONT FENCE (INSTALL)
LF 500.000 $4.500 $5.000 $4.000 $6.000 $15.000 $4.000 $5.000
TEMP SEDMT CONT FENCE (REMOVE)
LF 500.000 $1.500 $1.000 $2.000 $3.000 $1.000 $1.000 $2.000
Totals: $299,050.000 $283,536.000 $311,835.000 $349,348.000 $371,200.000 $425,090.000 $922,600.000