County: WALKER Highway: FM1791 Date: 10/08/2019 (5 years ago) Engineer's Estimate: $163,658 Control Number: 6345-89-001
Project: BPM - 634589001 District: BRYAN Time: 30 W Type: BRIDGE RAIL AND DECK REPAIR

Bidders

Name Total Amount Place Over/Under Est Amt Left From Low Bid Delta Between Bidders
Engineer's Estimate $163,657.50
KNIFE RIVER CORPORATION - SOUTH   $142,716.98 1
-12.8% | -$20,940.52
FUQUA CONSTRUCTION CO., INC.   $217,886.58 2
33.14% | $54,229.08
52.67% | $75,169.60
FNH CONSTRUCTION, LLC   $267,313.00 3
63.34% | $103,655.50
87.3% | $124,596.02
22.68% | $49,426.42

Bid Items

Items: 18, 0 filtered
WALKER FM1791  |  BRYAN  |  6345-89-001  |  10/08/2019  |  $163,658  |  BPM - 634589001  |  BRIDGE RAIL AND DECK REPAIR  |  30 W
Item code Description Unit Quantity Engineer's Estimate KNIFE RIVER CORPORATION - SOUTH FUQUA CONSTRUCTION CO., INC. FNH CONSTRUCTION, LLC
429 6005 CONC STR REPAIR(DECK REP (FULL DEPTH)) SF 34.000 $450.000 $800.000 $910.000 $1,000.000
500 6001 MOBILIZATION LS 1.000 $12,000.000 $13,200.000 $33,320.000 $26,500.000
502 6001 BARRICADES, SIGNS AND TRAFFIC HANDLING MO 2.000 $3,000.000 $3,500.000 $4,091.850 $8,500.000
512 6005 PORT CTB (FUR & INST)(F-SHAPE)(TY 1) LF 360.000 $38.000 $25.000 $109.200 $100.000
512 6053 PORT CTB (REMOVE)(F-SHAPE)(TY 1) LF 360.000 $15.000 $25.000 $35.000 $50.000
545 6005 CRASH CUSH ATTEN (REMOVE) EA 2.000 $13,000.000 $1,200.000 $2,100.000 $2,500.000
545 6013 CRASH CUSH ATTEN (INSTL)(R)(N)(TL3) EA 2.000 $1,200.000 $5,900.000 $11,200.000 $16,500.000
662 6063 WK ZN PAV MRK REMOV (W)4"(SLD) LF 986.000 $1.250 $4.400 $3.938 $5.000
662 6075 WK ZN PAV MRK REMOV (W)24"(SLD) LF 24.000 $20.000 $29.000 $26.250 $40.000
666 6224 PAVEMENT SEALER 4" LF 2,248.000 $1.000 $0.590 $0.525 $2.000
666 6315 RE PM W/RET REQ TY I (Y)4"(SLD)(100MIL) LF 2,248.000 $1.000 $3.650 $3.255 $2.000
672 6009 REFL PAV MRKR TY II-A-A EA 29.000 $5.000 $35.300 $31.500 $15.000
677 6001 ELIM EXT PAV MRK & MRKS (4") LF 2,248.000 $0.500 $3.820 $3.413 $2.000
681 6001 TEMP TRAF SIGNALS EA 1.000 $50,000.000 $8,200.000 $13,639.500 $16,500.000
778 6013 CONCRETE RAIL REPLACEMENT (TYPE 201) LF 19.000 $600.000 $800.000 $651.000 $250.000
6001 6002 PORTABLE CHANGEABLE MESSAGE SIGN EA 2.000 $6,000.000 $5,900.000 $5,092.080 $10,000.000
6185 6002 TMA (STATIONARY) DAY 5.000 $200.000 $300.000 $1,212.400 $550.000
6185 6003 TMA (MOBILE OPERATION) HR 40.000 $25.000 $56.000 $77.000 $850.000
Totals: $163,657.50 $142,716.98 $217,886.59 $267,313.00