Job Info for 6282-02-001

County: WALKER Highway: SH0030 Date: 06/01/2021 (3 years ago) Engineer's Estimate: $172,663 Control Number: 6282-02-001
Project: RMC - 628202001 District: BRYAN Time: 730 CALENDAR DAYS Type: MBGF & CABLE BARRIER REPAIR
HCS

Bidders

Name Total Amount Place Over/Under Est Amt Left From Low Bid Delta Between Bidders
Engineer's Estimate $172,663.00
ROY LEE WALKER   $198,527.00 1
14.98% | $25,864.00
T & L CLEANING SERVICES   $236,362.00 2
36.89% | $63,699.00
19.06% | $37,835.00
SHORT-LINE CORPORATION   $291,675.00 3
68.93% | $119,012.00
46.92% | $93,148.00
23.40% | $55,313.00

Bid Items

Items: 32, 0 filtered
WALKER SH0030  |  BRYAN  |  6282-02-001  |  06/01/2021  |  $172,663  |  RMC - 628202001  |  MBGF & CABLE BARRIER REPAIR  |  730 CALENDAR DAYS
Item code Description Unit Quantity Engineer's Estimate ROY LEE WALKER T & L CLEANING SERVICES SHORT-LINE CORPORATION
432 6045 RIPRAP (MOW STRIP)(4 IN) CY 30.000 $200.000 $80.000 $300.000 $100.000
500 6033 MOBILIZATION (CALLOUT) EA 100.000 $150.000 $1.000 $100.000 $100.000
540 6006 MTL BEAM GD FEN TRANS (THRIE-BEAM) EA 9.000 $10.000 $100.000 $1,600.000 $1,500.000
540 6010 MTL W-BEAM GD FEN ADJUSTMENT LF 150.000 $2.500 $1.000 $2.000 $5.000
770 6001 REPAIR RAIL ELEMENT (W - BEAM) LF 3,000.000 $10.000 $10.000 $13.000 $20.000
770 6002 REPAIR RAIL ELEMENT (THRIE - BEAM) LF 75.000 $6.000 $1.000 $20.000 $25.000
770 6003 REP RAIL ELMNT(THRIE-BM TRANS TO W -BM) LF 40.000 $5.000 $1.000 $22.000 $25.000
770 6006 RAISE RAIL ELEMENT LF 75.000 $5.000 $1.000 $2.000 $5.000
770 6010 REM / REPL TIMBER/STL POST W/O CONC FND EA 225.000 $20.000 $45.000 $30.000 $40.000
770 6011 REM / REPL TIMBER / STL POST W/CONC FND EA 10.000 $20.000 $45.000 $35.000 $40.000
770 6017 REALIGN POSTS EA 225.000 $5.000 $20.000 $10.000 $15.000
770 6019 REMOVE & REPLACE BLOCKOUT EA 15.000 $10.000 $10.000 $10.000 $65.000
770 6021 REPLACE SINGLE GDRAIL TERMINAL RAIL LF 450.000 $20.000 $16.000 $20.000 $25.000
770 6022 REPLACE SINGLE GDRAIL TERMINAL POST EA 50.000 $100.000 $45.000 $35.000 $50.000
770 6023 REPAIR OF TERMINAL ANCHORS POSTS EA 10.000 $56.000 $1.000 $1.000 $5.000
770 6024 REPLACE TERMINAL ANCHOR POSTS EA 10.000 $50.000 $1.000 $1.000 $5.000
770 6027 REMOVE GDRAIL END TRT / REPL WITH SGT EA 25.000 $1,850.000 $2,200.000 $2,000.000 $3,000.000
770 6028 REPL SINGLE GDRAIL TERM IMPACT HEAD EA 15.000 $785.000 $1,000.000 $750.000 $700.000
770 6030 REPLACE SGT CABLE ASSEMBLY EA 6.000 $35.000 $1.000 $1.000 $100.000
770 6031 REPLACE SGT CABLE ANCHOR EA 5.000 $20.000 $1.000 $1.000 $100.000
770 6032 REPLACE SGT STRUT EA 6.000 $18.000 $1.000 $1.000 $100.000
770 6033 REPLACE SGT OBJECT MARKER EA 5.000 $14.000 $1.000 $25.000 $100.000
770 6037 REPAIR RAIL ELEMENT (CURVED RAIL)(FURN) LF 75.000 $10.000 $10.000 $10.000 $25.000
770 6046 REM & RESET SGT IMPACT HEAD (FURNISHED) EA 25.000 $500.000 $100.000 $50.000 $100.000
770 6052 REPAIR STEEL POST WITH BASE PLATE EA 10.000 $50.000 $1.000 $1.000 $150.000
771 6002 REPLACE POSTS (TL-4) EA 800.000 $20.000 $78.000 $70.000 $75.000
771 6004 CABLE SPLICE / TURNBUCKLE (TL-4) EA 15.000 $50.000 $10.000 $100.000 $100.000
771 6006 REPAIR CONCRETE FOUNDATION (TL-4) EA 125.000 $25.000 $10.000 $100.000 $50.000
771 6008 REPR OR REPLC CABLE BARR TERM SEC(TL-4) EA 10.000 $200.000 $100.000 $500.000 $300.000
771 6010 REPLACE CABLE (TL-4) LF 500.000 $2.000 $1.000 $1.000 $1.000
771 6012 REPLACE POST HARDWARE (TL-4) EA 150.000 $20.000 $10.000 $13.000 $25.000
6001 6001 PORTABLE CHANGEABLE MESSAGE SIGN DAY 10.000 $100.000 $1.000 $1.000 $500.000
Totals: $172,663.00 $198,527.00 $236,362.00 $291,675.00