Job Info for 6328-43-001

County: VICTORIA Highway: US0059 Date: 06/06/2018 (6 years ago) Engineer's Estimate: $429,500 Control Number: 6328-43-001
Project: RMC - 632843001 District: YOAKUM Time: 730 CALENDAR DAYS Type: METAL GUARDFENCE REPAIR (ON CALL)

Bidders

Name Total Amount Place Over/Under Est Amt Left From Low Bid Delta Between Bidders
Engineer's Estimate $429,500.00
SHORT-LINE CORPORATION   $397,172.00 1
-7.53% | -$32,328.00
ELITE CASTLE RESOURCES LLC   $399,275.00 2
-7.04% | -$30,225.00
0.53% | $2,103.00
T&L CLEANING SERVICES LLC   $544,500.00 3
26.78% | $115,000.00
37.09% | $147,328.00
36.37% | $145,225.00
ISI CONTRACTING, INC.   $586,375.00 4
36.53% | $156,875.00
47.64% | $189,203.00
7.69% | $41,875.00

Bid Items

Items: 40, 0 filtered
VICTORIA US0059  |  YOAKUM  |  6328-43-001  |  06/06/2018  |  $429,500  |  RMC - 632843001  |  METAL GUARDFENCE REPAIR (ON CALL)  |  730 CALENDAR DAYS
Item code Description Unit Quantity Engineer's Estimate SHORT-LINE CORPORATION ELITE CASTLE RESOURCES LLC T&L CLEANING SERVICES LLC ISI CONTRACTING, INC.
500 6033 MOBILIZATION (CALLOUT) EA 12.000 $1,500.000 $1.000 $150.000 $100.000 $1,500.000
540 6001 MTL W-BEAM GD FEN (TIM POST) LF 500.000 $15.000 $1.000 $25.000 $21.000 $30.000
540 6006 MTL BEAM GD FEN TRANS (THRIE-BEAM) EA 25.000 $750.000 $1.000 $1,000.000 $1,800.000 $2,600.000
540 6008 MTL BEAM GD FEN TRANS (T101) EA 5.000 $500.000 $750.000 $800.000 $1,500.000 $1,400.000
544 6001 GUARDRAIL END TREATMENT (INSTALL) EA 5.000 $2,000.000 $500.000 $2,800.000 $3,000.000 $3,000.000
770 6001 REPAIR RAIL ELEMENT (W - BEAM) LF 3,000.000 $25.000 $28.000 $28.000 $20.000 $16.000
770 6002 REPAIR RAIL ELEMENT (THRIE - BEAM) LF 30.000 $50.000 $50.000 $80.000 $30.000 $50.000
770 6003 REP RAIL ELMNT(THRIE-BM TRANS TO W -BM) LF 30.000 $50.000 $50.000 $80.000 $30.000 $50.000
770 6004 REPAIR RAIL ELEMENT (CURVED RAIL) LF 250.000 $25.000 $10.000 $5.000 $30.000 $30.000
770 6010 REM / REPL TIMBER/STL POST W/O CONC FND EA 300.000 $40.000 $75.000 $60.000 $50.000 $55.000
770 6011 REM / REPL TIMBER / STL POST W/CONC FND EA 50.000 $50.000 $20.000 $60.000 $100.000 $55.000
770 6017 REALIGN POSTS EA 200.000 $20.000 $40.000 $20.000 $20.000 $15.000
770 6019 REMOVE & REPLACE BLOCKOUT EA 250.000 $10.000 $100.000 $10.000 $20.000 $10.000
770 6021 REPLACE SINGLE GDRAIL TERMINAL RAIL LF 600.000 $25.000 $20.000 $20.000 $30.000 $25.000
770 6022 REPLACE SINGLE GDRAIL TERMINAL POST EA 75.000 $50.000 $50.000 $100.000 $50.000 $60.000
770 6027 REMOVE GDRAIL END TRT / REPL WITH SGT EA 20.000 $2,100.000 $2,300.000 $2,800.000 $3,000.000 $3,000.000
770 6028 REPL SINGLE GDRAIL TERM IMPACT HEAD EA 10.000 $900.000 $900.000 $1,350.000 $1,200.000 $1,100.000
770 6029 REM & RESET SGT IMPACT HEAD EA 10.000 $100.000 $100.000 $500.000 $100.000 $120.000
770 6030 REPLACE SGT CABLE ASSEMBLY EA 10.000 $20.000 $20.000 $20.000 $100.000 $150.000
770 6031 REPLACE SGT CABLE ANCHOR EA 5.000 $20.000 $20.000 $20.000 $100.000 $120.000
770 6032 REPLACE SGT STRUT EA 150.000 $28.000 $1.000 $1.000 $100.000 $120.000
770 6033 REPLACE SGT OBJECT MARKER EA 100.000 $20.000 $1.000 $1.000 $50.000 $35.000
771 6001 REPLACE POSTS (TL-3) EA 1,000.000 $75.000 $1.000 $1.000 $90.000 $75.000
771 6002 REPLACE POSTS (TL-4) EA 500.000 $75.000 $80.000 $130.000 $100.000 $120.000
771 6003 CABLE SPLICE / TURNBUCKLE (TL-3) EA 5.000 $100.000 $1.000 $1.000 $300.000 $350.000
771 6004 CABLE SPLICE / TURNBUCKLE (TL-4) EA 5.000 $100.000 $50.000 $1,000.000 $300.000 $350.000
771 6005 REPAIR CONCRETE FOUNDATION (TL-3) EA 5.000 $100.000 $1.000 $1.000 $50.000 $70.000
771 6006 REPAIR CONCRETE FOUNDATION (TL-4) EA 5.000 $100.000 $50.000 $80.000 $100.000 $70.000
771 6007 REPR OR REPLC CABLE BARR TERM SEC(TL-3) EA 15.000 $500.000 $1.000 $1.000 $1,500.000 $500.000
771 6008 REPR OR REPLC CABLE BARR TERM SEC(TL-4) EA 15.000 $500.000 $500.000 $500.000 $1,500.000 $750.000
771 6009 REPLACE CABLE (TL-3) LF 1,000.000 $5.000 $0.010 $1.000 $1.000 $1.000
771 6010 REPLACE CABLE (TL-4) LF 1,000.000 $5.000 $1.000 $3.000 $1.000 $1.000
774 6005 RMV/REPL(VIA-SAND FILL PLASTIC BARRELS) EA 20.000 $300.000 $500.000 $480.000 $300.000 $400.000
776 6004 REPAIR (STL POST W/ DOUBLED W-BEAMS-T6) LF 50.000 $75.000 $1.000 $40.000 $100.000 $50.000
776 6011 REP METAL POST W/ BASE PLATE(T101 RAIL) EA 5.000 $100.000 $150.000 $190.000 $100.000 $150.000
776 6020 REPAIR (TY T101RC) LF 150.000 $20.000 $25.000 $50.000 $50.000 $100.000
776 6021 REPAIR (TY T1 - 101R) LF 300.000 $20.000 $20.000 $50.000 $60.000 $100.000
776 6024 REP METAL PST W/ BASE PLATE (TY T101RC) EA 5.000 $150.000 $150.000 $190.000 $300.000 $200.000
776 6025 REP METAL PST W/ BASE PLATE(TY T1-101R) EA 5.000 $150.000 $150.000 $190.000 $300.000 $125.000
6185 6002 TMA (STATIONARY) DAY 200.000 $150.000 $500.000 $50.000 $100.000 $250.000
Totals: $429,500.00 $397,172.00 $399,275.00 $544,500.00 $586,375.00