VICTORIA CR (0913-27-061)

Items: 61

County: VICTORIA
Length: N/A
Highway: CR
District: YOAKUM
Control Number: 0913-27-061
DBE Goal: N/A
Project: BR 2018(876)
Guaranty: N/A
Time: 300 WORKING DAYS
Engineer's Estimate: $1,735,265.75
Date: 03/06/2018 (8 years ago)
Contract Number: N/A
Type: REPLACE BRIDGE AND APPROACHES
Mail/Deliver Bids To: N/A
SEE PLANS OR PROPOSAL BOOK
Actions:
Notice HCS Excel Tabs Print Print Notice
Pay Estimates:
Bidders (7)
E
Engineer's Estimate
$1,735,265.75
$1,477,750.03
Over/Under Est: -14.84% -$257,515.72
Over/Under Est: -10.12% -$175,558.41
Amt Left: 5.55% $81,957.31
Over/Under Est: -3.88% -$67,246.71
Amt Left: 12.88% $190,269.01
Delta: -6.94% -$108,311.70
Over/Under Est: -0.72% -$12,529.15
Amt Left: 16.58% $244,986.57
Delta: -3.28% -$54,717.56
$1,759,613.35
Over/Under Est: 1.4% $24,347.60
Amt Left: 19.07% $281,863.32
Delta: -2.14% -$36,876.75
$1,910,703.83
Over/Under Est: 10.11% $175,438.08
Amt Left: 29.3% $432,953.80
Delta: -8.59% -$151,090.48
Over/Under Est: 23.45% $406,841.49
Amt Left: 44.96% $664,357.21
Delta: -12.11% -$231,403.41

Bid Items & Bid Tabulations

61 Total 0 of 61
VICTORIA  |  CR  |  YOAKUM  |  0913-27-061  |  03/06/2018  |  $1,735,265.75  |  BR 2018(876)  |  REPLACE BRIDGE AND APPROACHES  |  300 WORKING DAYS
Item Code
Description
Unit
Quantity
Engineer's Estimate
SB CONTRACTORS LLC
HILL COUNTRY BRIDGE, INC.
PROJECT ALLIED RESOURCES, LLC
A GREATER AUSTIN DEVELOPMENT COMPANY, LTD.
FNH CONSTRUCTION, LLC
J3 COMPANY, LLC
DEAN WORD COMPANY, LTD.
PREPARING ROW
STA 9.910 $2,500.000 $2,800.000 $3,000.000 $3,350.000 $700.000 $3,500.000 $2,500.000 $3,114.800
PREPARING ROW (TREE) (6" TO 24" DIA)
EA 1.000 $1,200.000 $1,200.000 $1,100.000 $1,170.000 $500.000 $1,200.000 $2,500.000 $249.600
EXCAVATION (ROADWAY)
CY 1,225.000 $20.000 $10.000 $12.750 $13.500 $20.000 $15.000 $20.000 $25.951
EXCAVATION (CHANNEL)
CY 250.000 $15.000 $10.000 $25.300 $26.300 $45.000 $35.000 $20.000 $25.951
EMBANKMENT (FINAL)(ORD COMP)(TY C)
CY 2,419.000 $30.000 $22.000 $21.550 $22.800 $15.000 $18.000 $20.000 $13.911
EMBANKMENT (VEHICLE)(ORD COMP)(TY C)
CY 65.000 $20.000 $22.000 $25.600 $23.000 $15.000 $50.000 $50.000 $11.137
BLADING
HR 60.000 $100.000 $65.000 $96.400 $145.000 $130.000 $125.000 $75.000 $83.850
CELL FBR MLCH SEED(PERM)(RURAL)(CLAY)
SY 7,655.000 $2.000 $0.450 $0.550 $0.630 $1.000 $1.000 $0.250 $0.260
CELL FBR MLCH SEED(TEMP)(WARM)
SY 1,914.000 $1.000 $0.380 $1.000 $0.240 $2.600 $1.000 $0.450 $0.468
CELL FBR MLCH SEED(TEMP)(COOL)
SY 1,914.000 $1.000 $0.380 $1.000 $0.260 $2.600 $1.000 $0.450 $0.468
VEGETATIVE WATERING
MG 64.500 $80.000 $45.000 $39.000 $2.750 $100.000 $80.000 $35.000 $43.000
FL BS (CMP IN PLC)(TY A GR 5)(FNAL POS)
CY 1,387.000 $120.000 $95.000 $101.700 $109.000 $125.000 $70.000 $75.000 $96.824
PRIME COAT (MC-30)
GAL 1,174.000 $8.000 $6.000 $7.100 $9.900 $7.000 $6.000 $12.000 $7.160
AGGR(TY-PE GR-4 SAC-B)
CY 90.000 $200.000 $275.000 $126.900 $216.000 $125.000 $250.000 $212.000 $397.750
ASPH (AC-15P OR AC-10-2TR OR CRS-2P)
GAL 3,992.000 $5.000 $6.000 $5.600 $6.600 $5.500 $6.000 $10.000 $4.408
CEM STABIL BKFL
CY 160.000 $150.000 $160.000 $125.300 $135.000 $210.000 $225.000 $130.000 $131.150
CUT & RESTORING PAV
SY 70.000 $125.000 $45.000 $100.000 $76.000 $95.000 $175.000 $70.000 $127.925
CUT AND RESTORE PAV (FLEX BASE)
SY 31.000 $100.000 $40.000 $84.000 $58.000 $60.000 $75.000 $80.000 $53.750
STL H - PILING (HP 14 X 73)
LF 874.000 $120.000 $84.000 $109.700 $110.000 $90.000 $110.000 $100.000 $220.746
DRILL SHAFT (24 IN)
LF 597.000 $200.000 $180.000 $185.500 $168.000 $185.000 $246.000 $250.000 $180.360
CL C CONC (ABUT)
CY 65.600 $1,000.000 $750.000 $715.000 $983.000 $950.000 $1,200.000 $1,500.000 $1,671.625
CL C CONC (CAP)
CY 16.000 $1,200.000 $1,200.000 $1,050.000 $1,010.000 $1,300.000 $950.000 $2,000.000 $1,542.625
CL C CONC (COLUMN)
CY 4.600 $1,200.000 $1,200.000 $1,490.000 $1,040.000 $1,500.000 $750.000 $2,000.000 $1,924.250
REINF CONC SLAB (SLAB BEAM)
SF 7,243.000 $20.000 $14.750 $16.200 $20.200 $16.000 $19.000 $30.000 $33.750
APPROACH SLAB
CY 52.000 $500.000 $425.000 $455.000 $452.000 $550.000 $490.000 $900.000 $641.775
PRESTR CONC SLAB BEAM (4SB15)
LF 1,464.000 $125.000 $128.000 $139.500 $142.000 $130.000 $135.000 $160.000 $182.164
PRESTR CONC SLAB BEAM (5SB15)
LF 247.410 $175.000 $165.500 $179.750 $142.000 $130.000 $135.000 $160.000 $202.930
RIPRAP (STONE COMMON)(DRY)(18 IN)
CY 299.000 $150.000 $120.000 $168.500 $181.000 $185.000 $80.000 $150.000 $139.750
RAIL (TY T223)
LF 598.000 $120.000 $105.000 $88.700 $115.000 $180.000 $140.000 $120.000 $120.669
ARMOR JOINT (SEALED)
LF 158.000 $75.000 $65.000 $70.000 $78.000 $120.000 $50.000 $80.000 $68.800
RC PIPE (CL III)(15 IN)
LF 72.000 $50.000 $60.000 $40.400 $57.000 $120.000 $35.000 $70.000 $60.200
RC PIPE (CL III)(30 IN)
LF 80.000 $85.000 $90.000 $65.850 $123.000 $170.000 $85.000 $90.000 $91.375
RC PIPE (CL IV)(18 IN)
LF 250.000 $55.000 $65.000 $44.450 $60.000 $73.000 $48.000 $75.000 $65.575
INLET (COMPL)(PSL)(FG)(4FTX4FT-4FTX4FT)
EA 1.000 $4,500.000 $3,500.000 $3,000.000 $5,770.000 $4,500.000 $3,800.000 $6,500.000 $5,912.500
SET (TY II) (15 IN) (RCP) (6: 1) (P)
EA 4.000 $1,200.000 $950.000 $1,040.000 $807.000 $1,900.000 $440.000 $2,000.000 $1,191.100
SET (TY II) (18 IN) (RCP) (6: 1) (P)
EA 3.000 $1,500.000 $1,100.000 $1,300.000 $951.000 $2,100.000 $702.000 $2,000.000 $1,531.875
SET (TY II) (30 IN) (RCP) (6: 1) (P)
EA 1.000 $2,000.000 $2,500.000 $2,590.000 $2,340.000 $6,400.000 $1,800.000 $3,000.000 $2,983.125
REMOV STR (BRIDGE 0 - 99 FT LENGTH)
EA 2.000 $15,000.000 $6,800.000 $14,900.000 $11,900.000 $12,300.000 $5,500.000 $20,000.000 $26,287.500
REMOV STR (BRIDGE 100 - 499 FT LENGTH)
EA 1.000 $35,000.000 $13,617.270 $20,900.000 $40,200.000 $12,300.000 $27,500.000 $50,000.000 $59,350.000
REMOV STR (SMALL)
EA 6.000 $500.000 $700.000 $640.000 $617.000 $910.000 $200.000 $1,500.000 $564.375
MOBILIZATION
LS 1.000 $150,000.000 $147,010.520 $155,300.000 $166,000.000 $168,000.000 $250,000.000 $170,000.000 $214,196.223
BARRICADES, SIGNS AND TRAFFIC HANDLING
MO 21.000 $2,500.000 $2,250.000 $1,730.000 $705.000 $1,500.000 $4,000.000 $2,916.080 $4,376.627
ROCK FILTER DAMS (INSTALL) (TY 1)
LF 225.000 $50.000 $30.000 $38.000 $23.700 $31.000 $65.000 $24.840 $25.834
ROCK FILTER DAMS (REMOVE)
LF 225.000 $10.000 $10.000 $7.000 $7.800 $15.000 $30.000 $7.000 $7.280
TEMP SEDMT CONT FENCE (INSTALL)
LF 4,135.000 $2.500 $2.750 $3.100 $4.220 $3.100 $4.000 $2.300 $2.392
TEMP SEDMT CONT FENCE (REMOVE)
LF 4,135.000 $1.000 $1.000 $0.630 $1.180 $1.000 $1.500 $0.250 $0.260
DRIVEWAYS (ACP)
SY 103.000 $50.000 $52.000 $37.750 $26.900 $40.000 $71.000 $80.000 $61.039
DRIVEWAYS (SURF TREAT)
SY 35.000 $40.000 $48.000 $32.700 $19.600 $39.000 $30.000 $70.000 $53.514
DRIVEWAYS (BASE)
SY 71.000 $50.000 $32.000 $22.550 $20.300 $33.500 $50.000 $60.000 $34.164
MTL W-BEAM GD FEN (TIM POST)
LF 837.500 $25.000 $25.000 $24.600 $23.800 $27.000 $19.000 $25.000 $20.020
MTL BEAM GD FEN TRANS (THRIE-BEAM)
EA 10.000 $1,500.000 $1,800.000 $1,815.000 $1,860.000 $2,000.000 $1,500.000 $1,500.000 $1,872.480
GUARDRAIL END TREATMENT (INSTALL)
EA 10.000 $2,200.000 $2,700.000 $2,700.000 $2,620.000 $3,000.000 $2,300.000 $2,600.000 $2,554.240
CRASH CUSH ATTEN (INSTL)
EA 2.000 $12,000.000 $16,000.000 $17,300.000 $13,600.000 $17,700.000 $11,000.000 $15,000.000 $15,418.000
WIRE FENCE (TY A)
LF 1,242.000 $12.000 $9.000 $6.250 $14.900 $13.500 $12.000 $12.000 $16.125
WIRE FENCE (WATER GAP)
LF 128.000 $40.000 $30.000 $75.600 $47.500 $33.500 $25.000 $20.000 $49.450
MAILBOX INSTALL-M (TWG-POST) TY 1
EA 1.000 $300.000 $385.000 $390.000 $528.000 $430.000 $275.000 $427.950 $445.068
MAILBOX INSTALL-S (TWG-POST) TY 2
EA 2.000 $350.000 $200.000 $203.000 $346.000 $220.000 $300.000 $259.500 $269.880
RELOCATE SM RD SN SUP&AM TY 10BWG
EA 2.000 $350.000 $450.000 $457.000 $657.000 $500.000 $480.000 $459.000 $477.360
INSTL DEL ASSM (D-SW)SZ (BRF)CTB (BI)
EA 18.000 $25.000 $15.000 $15.250 $40.200 $33.500 $30.000 $12.000 $12.480
INSTL DEL ASSM (D-SW)SZ 1(BRF)GF2(BI)
EA 24.000 $20.000 $15.000 $15.250 $45.000 $33.500 $25.000 $32.000 $16.380
LANDSCAPE FENCE
LF 1,130.000 $30.000 $12.000 $9.900 $22.300 $45.000 $15.000 $12.000 $16.125
Totals: $1,735,265.750 $1,477,750.035 $1,559,707.348 $1,668,019.045 $1,722,736.600 $1,759,613.350 $1,910,703.830 $2,142,107.337