VICTORIA US 59 (0088-05-104)
Items: 79
County: VICTORIA
Length: N/A
Highway: US 59
District: YOAKUM
Control Number: 0088-05-104
DBE Goal: N/A
Project: NH 2020(988)
Guaranty: N/A
Time: 255 WORKING DAYS
Engineer's Estimate: $6,402,469.80
Date: 07/09/2020 (5 years ago)
Contract Number: N/A
Type: INSTALL MEDIAN BARRIER AND WIDEN ROADWAY
Mail/Deliver Bids To: N/A
SEE PLANS OR PROPOSAL BOOK
Bidders (3)
| Bidder | Total Amount | Over/Under Est | Amt Left From Low Bid | Delta Between Bidders |
|---|---|---|---|---|
|
E
Engineer's Estimate
|
$6,402,469.80 | |||
| $6,878,588.24 |
7.44%
$476,118.44
|
|||
| $7,072,205.34 |
10.46%
$669,735.54
|
2.81%
$193,617.10
|
||
| $7,848,219.30 |
22.58%
$1,445,749.50
|
14.1%
$969,631.06
|
-10.97%
-$776,013.96
|
E
Engineer's Estimate
$6,402,469.80
1
Awarded
$6,878,588.24
Over/Under Est:
7.44%
$476,118.44
$7,072,205.34
Over/Under Est:
10.46%
$669,735.54
Amt Left:
2.81%
$193,617.10
$7,848,219.30
Over/Under Est:
22.58%
$1,445,749.50
Amt Left:
14.1%
$969,631.06
Delta:
-10.97%
-$776,013.96
| Subcontractor | Percentage | Amount |
|---|---|---|
| ROADWAY SPECIALTIES, INC. | 7.24% | $500,802.74 |
| HIGHWAY BARRICADES AND SERVICES, LLC | 0.73% | $50,495.30 |
| LONESTAR TRAFFIC SAFETY, LLC | 0.40% | $27,668.66 |
| LONE STAR EROSION CONTROL | 0.40% | $27,668.66 |
| FLASHER EQUIPMENT COMPANY | 0.14% | $9,684.03 |
| TRP CONSTRUCTION GROUP, LLC | 0.12% | $8,300.60 |
| PRIMATE CONSTRUCTION, LP | 0.11% | $7,608.88 |
| Total: | 9.14% | $632,228.87 |
Bid Items & Bid Tabulations
79
Total
0 of 79