Show Job Controls
Bid Cobra

VAN ZANDT FM 1255 (1322-02-017)

Items: 120

County: VAN ZANDT
Length: N/A
Highway: FM 1255
District: TYLER
Control Number: 1322-02-017
DBE Goal: N/A
Project: F 2024(023)
Guaranty: N/A
Time: 363 WORKING DAYS
Engineer's Estimate: $22,915,166.99
Date: 09/07/2023 (2 years ago)
Contract Number: N/A
Type: REHABILITATE EXISTING ROADWAY
Mail/Deliver Bids To: N/A
LANCE POMYKAL
JOSH FULTON
Actions:
Notice HCS Excel Tabs Print Print Notice
Bidders (3)
E
Engineer's Estimate
$22,915,166.99
$17,084,796.24
Over/Under Est: -25.44% -$5,830,370.75
$17,259,654.84
Over/Under Est: -24.68% -$5,655,512.15
Amt Left: 1.02% $174,858.60
$25,436,732.15
Over/Under Est: 11% $2,521,565.16
Amt Left: 48.89% $8,351,935.91
Delta: -47.38% -$8,177,077.31
Subcontractor Percentage Amount
STRIPING TECHNOLOGY, L.P. 2.33% $402,998.83
SOUTHWEST ENVIRONMENT SERVICES LLC 1.79% $309,599.96
PATTERSON'S COMPLETE TREE SERVICE LLC 0.97% $167,772.05
DUSTIN ALLEN, INC. 0.56% $96,858.09
ISAACS CONSTRUCTION SERVICES LLC 0.45% $77,832.39
TEX OP CONSTRUCTION, LP 0.36% $62,265.91
CAP RIVER LLC 0.20% $34,592.17
FLEX SUPPLY, LLC 0.18% $31,132.96
Total: 6.84% $1,183,052.36

Bid Items & Bid Tabulations

120 Total 0 of 120
VAN ZANDT  |  FM 1255  |  TYLER  |  1322-02-017  |  09/07/2023  |  $22,915,166.99  |  F 2024(023)  |  REHAB EXIST ROADWAY  |  363 WORKING DAYS
Item Code
Description
Unit
Quantity
Engineer's Estimate
REYNOLDS & KAY, LTD.
A. L. HELMCAMP, INC.
EAST TEXAS BRIDGE, INC.
PREPARING ROW
STA 473.970 $10,000.000 $774.000 $2,250.000 $10,000.000
REMOVING CONC (DRIVEWAYS)
SY 625.000 $25.000 $40.000 $100.000 $25.000
SUBGRADE WIDENING (ORD COMP)
STA 431.970 $350.000 $325.000 $450.000 $650.000
EMBANKMENT (VEHICLE)(ORD COMP)(TY C)
CY 1,069.000 $45.400 $40.000 $150.000 $35.000
BACKFILL (TY A)
STA 466.000 $212.500 $360.000 $175.000 $750.000
BLADING
STA 489.000 $400.000 $115.000 $325.000 $300.000
FURNISHING AND PLACING TOPSOIL (4")
SY 10,831.000 $8.080 $4.000 $10.000 $5.000
BROADCAST SEED (PERM) (RURAL) (SANDY)
SY 77,590.000 $0.250 $0.110 $0.140 $0.120
BOND FBR MTRX SEED (PERM)(RURAL)(SAND)
SY 155,178.000 $1.500 $0.620 $0.610 $0.650
BONDED FBR MTRX SEED (TEMP)(WARM)
SY 77,590.000 $1.500 $0.570 $0.550 $0.560
BONDED FBR MTRX SEED (TEMP)(COOL)
SY 77,590.000 $1.510 $0.560 $0.550 $0.560
VEGETATIVE WATERING
MG 3,176.000 $50.000 $12.000 $1.500 $6.000
FL BS (CMP IN PLACE)(TYC GR1-2)(IN VEH)
CY 1,300.000 $150.000 $125.000 $150.000 $200.000
FL BS (CMP IN PLC)(TYA GR1-2) (6")
SY 139,192.000 $25.000 $28.000 $22.000 $35.000
REWORK BS MTL (TY C) (8") (ORD COMP)
SY 115,193.000 $15.500 $3.000 $5.750 $22.000
CEMENT
TON 2,240.000 $300.000 $350.000 $360.000 $350.000
CEMENT TREAT(EXIST MATL)(8")
SY 143,992.000 $5.380 $6.550 $15.000 $7.000
EMULS ASPH (EROSN CONT)(CSS-1)
GAL 6,187.000 $7.000 $7.000 $5.000 $6.000
ASPH (RC-250)
GAL 33,598.000 $7.000 $7.000 $6.000 $6.000
ASPH (AC-20XP, AC-10-2TR, OR AC-20-5TR)
GAL 112,660.000 $7.000 $5.500 $6.000 $6.500
AGGR (TY-PD GR-3 OR TY-PL GR-3)
CY 1,169.000 $380.000 $200.000 $250.000 $235.000
AGGR(TY-PD GR-4 OR TY-PL GR-4)
CY 1,202.000 $145.000 $175.000 $250.000 $235.000
AGGR (TY-PD GR-5 OR TY-PL GR-5)
CY 1,034.000 $176.000 $185.000 $350.000 $265.000
FLEXIBLE PAVEMENT STRUCTURE REPAIR(8")
SY 10,520.000 $108.500 $117.000 $105.000 $110.000
CEM STABIL BKFL
CY 147.000 $271.250 $415.000 $347.000 $400.000
FLOWABLE BACKFILL
CY 147.000 $737.760 $415.000 $347.000 $400.000
TEMPORARY SPL SHORING
SF 1,776.000 $45.000 $75.000 $50.000 $80.000
CL C CONC (COLLAR)
EA 44.000 $2,000.000 $1,350.000 $2,625.000 $2,500.000
RIPRAP (STONE COMMON)(DRY)(18 IN)
CY 35.000 $175.940 $425.000 $285.000 $250.000
RIPRAP (MOW STRIP)(4 IN)
CY 111.000 $600.000 $1,000.000 $693.000 $700.000
CLEANING AND SEALING EXIST JOINTS(CL7)
LF 37.000 $75.000 $130.000 $210.000 $100.000
CONC BOX CULV (6 FT X 6 FT)(EXTEND)
LF 26.000 $1,347.200 $1,700.000 $908.000 $1,000.000
CONC BOX CULV (7 FT X 4 FT)(EXTEND)
LF 24.000 $1,636.900 $1,800.000 $966.000 $1,400.000
CONC BOX CULV (8 FT X 4 FT)(EXTEND)
LF 14.000 $1,484.060 $1,850.000 $1,155.000 $1,500.000
RC PIPE (CL III)(18 IN)
LF 3,692.000 $66.000 $72.000 $57.000 $70.000
RC PIPE (CL III)(24 IN)
LF 392.000 $90.000 $97.000 $95.000 $100.000
RC PIPE (CL III)(30 IN)
LF 172.000 $140.000 $165.000 $146.000 $135.000
RC PIPE (CL III)(36 IN)
LF 84.000 $145.000 $190.000 $158.000 $200.000
HEADWALL (CH - PW - 0) (DIA= 18 IN)
EA 2.000 $7,500.000 $11,500.000 $4,525.000 $7,500.000
HEADWALL (CH - PW - 0) (DIA= 24 IN)
EA 3.000 $8,000.000 $14,000.000 $6,650.000 $8,500.000
HEADWALL (CH - PW - 0) (DIA= 30 IN)
EA 4.000 $8,500.000 $15,000.000 $7,875.000 $12,000.000
HEADWALL (CH - PW - 0) (DIA= 36 IN)
EA 7.000 $10,000.000 $19,000.000 $9,420.000 $15,000.000
WINGWALL (PW - 1) (HW=5 FT)
EA 4.000 $20,500.000 $28,000.000 $13,900.000 $15,000.000
WINGWALL (PW - 1) (HW=6 FT)
EA 1.000 $26,500.000 $30,000.000 $17,900.000 $17,000.000
WINGWALL (PW - 1) (HW=7 FT)
EA 2.000 $30,800.000 $40,000.000 $24,600.000 $30,000.000
SET (TY II) (18 IN) (RCP) (3: 1) (C)
EA 7.000 $1,500.000 $1,000.000 $955.000 $700.000
SET (TY II) (18 IN) (RCP) (4: 1) (C)
EA 6.000 $1,200.000 $1,000.000 $1,087.000 $800.000
SET (TY II) (18 IN) (RCP) (6: 1) (C)
EA 4.000 $1,500.000 $1,200.000 $1,570.000 $1,000.000
SET (TY II) (18 IN) (RCP) (6: 1) (P)
EA 244.000 $1,500.000 $1,150.000 $903.000 $1,000.000
SET (TY II) (24 IN) (RCP) (3: 1) (C)
EA 5.000 $2,000.000 $1,350.000 $1,490.000 $1,100.000
SET (TY II) (24 IN) (RCP) (4: 1) (C)
EA 1.000 $1,900.000 $1,550.000 $1,780.000 $1,200.000
SET (TY II) (24 IN) (RCP) (6: 1) (P)
EA 18.000 $2,000.000 $1,800.000 $1,465.000 $1,400.000
SET (TY II) (30 IN) (RCP) (3: 1) (C)
EA 2.000 $2,000.000 $1,900.000 $2,075.000 $2,200.000
SET (TY II) (30 IN) (RCP) (4: 1) (C)
EA 1.000 $2,625.000 $2,200.000 $2,300.000 $2,500.000
SET (TY II) (36 IN) (RCP) (3: 1) (C)
EA 5.000 $2,900.000 $2,500.000 $2,940.000 $3,000.000
SET (TY II) (36 IN) (RCP) (6: 1) (C)
EA 1.000 $5,600.000 $4,500.000 $6,715.000 $4,500.000
SET (TY II) (36 IN) (RCP) (6: 1) (P)
EA 10.000 $6,250.000 $7,000.000 $5,930.000 $6,500.000
CLEAN EXIST CULVERTS
EA 17.000 $1,222.000 $3,000.000 $2,220.000 $5,000.000
REMOV STR (PIPE)
EA 137.000 $782.670 $550.000 $550.000 $1,000.000
MOBILIZATION
LS 1.000 $2,256,451.030 $2,611,000.000 $1,250,000.000 $2,400,000.000
BARRICADES, SIGNS AND TRAFFIC HANDLING
MO 18.000 $12,500.000 $25,000.000 $20,000.000 $50,000.000
ROCK FILTER DAMS (INSTALL) (TY 1)
LF 500.000 $33.000 $33.000 $32.000 $35.000
ROCK FILTER DAMS (INSTALL) (TY 2)
LF 500.000 $38.500 $37.000 $37.000 $38.000
ROCK FILTER DAMS (REMOVE)
LF 1,000.000 $9.000 $10.000 $9.500 $10.000
EARTHWORK (EROSN & SEDMT CONT, IN VEH)
CY 1,000.000 $40.000 $20.000 $80.000 $35.000
BACKHOE WORK (EROSION & SEDMT CONT)
HR 300.000 $127.000 $55.000 $125.000 $100.000
TEMP SEDMT CONT FENCE (INSTALL)
LF 10,000.000 $3.640 $3.250 $3.750 $3.500
TEMP SEDMT CONT FENCE (REMOVE)
LF 10,000.000 $1.320 $0.700 $0.300 $1.000
TRACKHOE WORK (EROSION & SEDMT CONT)
HR 300.000 $127.000 $92.000 $150.000 $125.000
INTERSECTIONS (ACP)
SY 2,210.000 $53.000 $85.000 $120.000 $65.000
DRIVEWAYS (ACP)
SY 8,942.000 $64.500 $74.000 $82.000 $65.000
TURNOUTS (ACP)
SY 880.000 $70.000 $140.000 $140.000 $75.000
DRIVEWAYS (CONC) (HES)
SY 654.000 $125.000 $150.000 $250.000 $175.000
MTL W-BEAM GD FEN (STEEL POST)
LF 850.000 $32.750 $28.000 $29.000 $30.000
SHORT RADIUS
LF 25.000 $75.000 $550.000 $25.000 $800.000
DRIVEWAY TERMINAL ANCHOR SECTION
EA 1.000 $1,000.000 $1,600.000 $685.000 $1,300.000
MTL THRIE-BEAM GD FEN (STEEL POST)
EA 12.000 $2,350.000 $2,600.000 $2,365.000 $2,200.000
REMOVE METAL BEAM GUARD FENCE
LF 1,400.000 $5.000 $2.300 $3.250 $2.500
REMOVE TERMINAL ANCHOR SECTION
EA 3.000 $200.000 $225.000 $135.000 $200.000
RM MTL BM GD FENCE TRANS (THRIE-BEAM)
EA 8.000 $320.000 $225.000 $265.000 $200.000
GUARDRAIL END TREATMENT (INSTALL)
EA 11.000 $3,100.000 $3,000.000 $3,000.000 $3,200.000
GUARDRAIL END TREATMENT (REMOVE)
EA 9.000 $270.000 $225.000 $265.000 $250.000
MAILBOX INSTALL-S (TWG-POST) TY 2
EA 71.000 $406.000 $350.000 $235.000 $300.000
MAILBOX INSTALL-D (TWG-POST) TY 2
EA 6.000 $482.000 $400.000 $265.000 $350.000
MAILBOX INSTALL-M (TWG-POST) TY 2
EA 3.000 $775.000 $750.000 $570.000 $650.000
IN SM RD SN SUP&AM TY10BWG(1)SA(T)
EA 94.000 $903.000 $1,000.000 $790.000 $850.000
IN SM RD SN SUP&AM TY10BWG(1)SA(U)
EA 13.000 $1,165.000 $1,000.000 $875.000 $950.000
IN SM RD SN SUP&AM TY10BWG(2)SA(P)
EA 1.000 $1,278.000 $1,500.000 $1,260.000 $1,500.000
IN SM RD SN SUP&AM TYS80(1)SA(T)
EA 7.000 $1,000.000 $1,100.000 $1,025.000 $1,200.000
IN SM RD SN SUP&AM TYS80(1)SA(U)
EA 5.000 $800.000 $1,200.000 $1,000.000 $1,300.000
REMOVE SM RD SN SUP&AM
EA 121.000 $220.000 $115.000 $80.000 $125.000
INSTL DEL ASSM (D-SW)SZ (BRF)CTB (BI)
EA 18.000 $20.700 $28.000 $21.000 $30.000
INSTL DEL ASSM (D-SW)SZ 1(BRF)GF2(BI)
EA 36.000 $26.260 $40.000 $27.000 $40.000
INSTL OM ASSM (OM-2Z)(WFLX)GND
EA 72.000 $66.000 $85.000 $58.000 $60.000
WK ZN PAV MRK NON-REMOV (W)6"(SLD)
LF 92,334.000 $0.550 $0.550 $0.600 $0.550
WK ZN PAV MRK NON-REMOV (W)8"(SLD)
LF 120.000 $1.000 $1.150 $0.860 $1.100
WK ZN PAV MRK NON-REMOV (W)24"(SLD)
LF 194.000 $14.880 $5.500 $4.040 $6.000
WK ZN PAV MRK NON-REMOV (Y)6"(BRK)
LF 3,750.000 $0.540 $0.550 $0.600 $0.550
WK ZN PAV MRK NON-REMOV (Y)6"(SLD)
LF 77,641.000 $0.560 $0.550 $0.600 $0.550
WK ZN PAV MRK SHT TERM (TAB)TY W
EA 4,673.000 $2.820 $1.150 $0.840 $2.000
WK ZN PAV MRK SHT TERM (TAB)TY Y-2
EA 4,682.000 $2.290 $1.150 $0.530 $2.000
REFL PAV MRK TY I (W)8"(SLD)(100MIL)
LF 120.000 $1.770 $2.250 $1.580 $2.250
REFL PAV MRK TY I (W)24"(SLD)(100MIL)
LF 194.000 $8.350 $9.000 $6.300 $9.000
PAVEMENT SEALER 6"
LF 1,092.000 $0.600 $1.150 $0.260 $1.100
RE PM W/RET REQ TY I (W)6"(SLD)(100MIL)
LF 92,334.000 $1.000 $1.000 $0.750 $1.000
RE PM W/RET REQ TY I (Y)6"(BRK)(100MIL)
LF 3,750.000 $0.720 $1.150 $0.750 $1.100
RE PM W/RET REQ TY I (Y)6"(SLD)(100MIL)
LF 77,641.000 $1.000 $1.000 $0.750 $1.000
REF PROF PAV MRK TY I(W)6"(SLD)(100MIL)
LF 92,154.000 $5.630 $1.150 $0.850 $1.100
REF PROF PAV MRK TY I(Y)6"(BRK)(100MIL)
LF 3,750.000 $6.000 $1.300 $0.850 $1.500
REF PROF PAV MRK TY I(Y)6"(SLD)(100MIL)
LF 77,461.000 $5.630 $1.150 $0.850 $1.100
REFL PAV MRKR TY I-A
EA 75.000 $4.830 $5.500 $5.250 $5.500
REFL PAV MRKR TY I-C
EA 24.000 $6.180 $5.500 $5.250 $5.500
REFL PAV MRKR TY II-A-A
EA 1,134.000 $7.000 $4.500 $5.250 $4.500
ELIM EXT PAV MRK & MRKS (6")
LF 1,092.000 $0.730 $1.150 $1.050 $1.100
PAV SURF PREP FOR MRK (6")
LF 1,092.000 $0.330 $1.150 $1.050 $1.100
PORTABLE CHANGEABLE MESSAGE SIGN
DAY 28.000 $212.000 $130.000 $300.000 $300.000
PORTABLE CHANGEABLE MESSAGE SIGN
EA 2.000 $14,800.000 $18,000.000 $20,000.000 $35,000.000
PREFORMED CENTERLINE RUMBLE STRIP
LF 130.000 $20.440 $13.000 $13.000 $40.000
TMA (STATIONARY)
DAY 200.000 $300.000 $200.000 $400.000 $300.000
TMA (MOBILE OPERATION)
DAY 200.000 $250.000 $150.000 $1.000 $300.000
Totals: $22,915,166.990 $17,084,796.240 $17,259,654.840 $25,436,732.150