Job Info for 0095-06-071

County: VAN ZANDT Highway: US 80 Date: 05/07/2019 (5 years ago) Engineer's Estimate: $557,547 Control Number: 0095-06-071
Project: STP 2019(853)HESG District: TYLER Time: 63 WORKING DAYS Type: CENTERLINE & EDGELINE PROFILE PAVMENT MARKINGS

Bidders

Name Total Amount Place Over/Under Est Amt Left From Low Bid Delta Between Bidders
Engineer's Estimate $557,546.90
TOTAL HIGHWAY MAINTENANCE, LLC   $499,197.05 1
-10.47% | -$58,349.85
STRIPE-A-ZONE, INC.   $519,916.60 2
-6.75% | -$37,630.30
4.15% | $20,719.55
TRP CONSTRUCTION GROUP, LLC   $553,092.90 3
-0.8% | -$4,454.00
10.8% | $53,895.85
6.38% | $33,176.30
STRIPING TECHNOLOGY, L.P.   $595,027.45 4
6.72% | $37,480.55
19.2% | $95,830.40
7.58% | $41,934.55
CENTERLINE TECHNOLOGIES, LLC   $698,169.10 5
25.22% | $140,622.20
39.86% | $198,972.05
17.33% | $103,141.65

Bid Items

Items: 17, 0 filtered
VAN ZANDT US 80  |  TYLER  |  0095-06-071  |  05/07/2019  |  $557,547  |  STP 2019(853)HESG  |  CENTERLINE & EDGELINE PROFILE PAVMENT MRK  |  63 WORKING DAYS
Item code Description Unit Quantity Engineer's Estimate TOTAL HIGHWAY MAINTENANCE, LLC STRIPE-A-ZONE, INC. TRP CONSTRUCTION GROUP, LLC STRIPING TECHNOLOGY, L.P. CENTERLINE TECHNOLOGIES, LLC
500 6001 MOBILIZATION LS 1.000 $11,000.000 $12,000.000 $29,000.000 $30,000.000 $20,000.000 $65,000.000
502 6001 BARRICADES, SIGNS AND TRAFFIC HANDLING MO 4.000 $5,000.000 $3,400.000 $1,500.000 $3,000.000 $7,000.000 $1.000
666 6224 PAVEMENT SEALER 4" LF 750.000 $0.500 $1.000 $1.000 $1.250 $3.000 $4.000
666 6300 RE PM W/RET REQ TY I (W)4"(BRK)(100MIL) LF 18,670.000 $0.300 $0.450 $0.350 $0.350 $0.400 $0.350
666 6303 RE PM W/RET REQ TY I (W)4"(SLD)(100MIL) LF 7,500.000 $0.300 $0.360 $0.350 $0.300 $0.400 $0.350
666 6312 RE PM W/RET REQ TY I (Y)4"(BRK)(100MIL) LF 500.000 $0.300 $0.450 $0.350 $2.000 $0.400 $0.350
666 6315 RE PM W/RET REQ TY I (Y)4"(SLD)(100MIL) LF 13,880.000 $0.300 $0.360 $0.350 $0.300 $0.400 $0.350
666 6342 REF PROF PAV MRK TY I(W)4"(SLD)(100MIL) LF 516,110.000 $0.540 $0.510 $0.535 $0.540 $0.600 $0.660
666 6344 REF PROF PAV MRK TY I(Y)4"(BRK)(100MIL) LF 19,650.000 $0.550 $0.550 $0.535 $0.600 $0.900 $0.660
666 6345 REF PROF PAV MRK TY I(Y)4"(SLD)(100MIL) LF 260,650.000 $0.600 $0.520 $0.535 $0.550 $0.600 $0.660
672 6006 REFL PAV MRKR TY I-A EA 88.000 $3.000 $2.550 $3.000 $15.000 $2.650 $5.000
672 6009 REFL PAV MRKR TY II-A-A EA 5,938.000 $2.500 $2.550 $2.650 $3.000 $2.650 $4.000
672 6010 REFL PAV MRKR TY II-C-R EA 1,867.000 $3.000 $2.550 $2.650 $3.000 $2.650 $5.000
677 6001 ELIM EXT PAV MRK & MRKS (4") LF 750.000 $1.000 $1.000 $1.000 $5.000 $3.000 $15.000
6056 6002 PREFORMED CENTERLINE RUMBLE STRIP LF 4,550.000 $5.000 $5.000 $4.450 $6.000 $4.000 $10.000
6185 6001 TMA (STATIONARY) EA 2.000 $2,500.000 $250.000 $30.000 $2,500.000 $150.000 $1.000
6185 6005 TMA (MOBILE OPERATION) DAY 63.000 $300.000 $45.000 $30.000 $25.000 $50.000 $1.000
Totals: $557,546.90 $499,197.05 $519,916.60 $553,092.90 $595,027.45 $698,169.10