VAL VERDE US 277 (0160-05-049)
Items: 29
County: VAL VERDE
Length: N/A
Highway: US 277
District: LAREDO
Control Number: 0160-05-049
DBE Goal: N/A
Project: F 2024(060)
Guaranty: N/A
Time: 133 WORKING DAYS
Engineer's Estimate: $11,697,331.78
Date: 09/06/2023 (2 years ago)
Contract Number: N/A
Type: SEAL COAT
Mail/Deliver Bids To: N/A
ELIUD DELOSSANTOS
ANGEL MARTINEZ
Bidders (4)
| Bidder | Total Amount | Over/Under Est | Amt Left From Low Bid | Delta Between Bidders |
|---|---|---|---|---|
|
E
Engineer's Estimate
|
$11,697,331.78 | |||
| $9,710,710.72 |
-16.98%
-$1,986,621.06
|
|||
| $10,502,727.85 |
-10.21%
-$1,194,603.93
|
8.16%
$792,017.13
|
||
| $11,553,728.23 |
-1.23%
-$143,603.55
|
18.98%
$1,843,017.51
|
-10.01%
-$1,051,000.38
|
|
| $13,572,752.79 |
16.03%
$1,875,421.01
|
39.77%
$3,862,042.07
|
-17.48%
-$2,019,024.56
|
E
Engineer's Estimate
$11,697,331.78
1
Awarded
$9,710,710.72
Over/Under Est:
-16.98%
-$1,986,621.06
$10,502,727.85
Over/Under Est:
-10.21%
-$1,194,603.93
Amt Left:
8.16%
$792,017.13
$11,553,728.23
Over/Under Est:
-1.23%
-$143,603.55
Amt Left:
18.98%
$1,843,017.51
Delta:
-10.01%
-$1,051,000.38
$13,572,752.79
Over/Under Est:
16.03%
$1,875,421.01
Amt Left:
39.77%
$3,862,042.07
Delta:
-17.48%
-$2,019,024.56
| Subcontractor | Percentage | Amount |
|---|---|---|
| HIGHWAY BARRICADES AND SERVICES, LLC | 26.32% | $2,553,738.65 |
| VIZCAINO, L.P. | 1.95% | $189,201.76 |
| FLASHER EQUIPMENT COMPANY | 1.22% | $118,372.38 |
| MPB, INC. | 0.86% | $83,442.83 |
| Total: | 30.35% | $2,944,755.62 |