Job Info for 1511-01-013

County: UPSHUR Highway: FM 993 Date: 03/06/2024 (8 months ago) Engineer's Estimate: $2,229,422 Control Number: 1511-01-013
Project: BR 2024(791) District: ATLANTA Time: 0 X Type: REPLACE BRIDGE AND APPROACHES
Bidder's List
Informational:
Email All | Notice | Questions
HCS
Pay Estimates: 1 | 2 | 3 | 4 | 5 | 6
Plans: Plans | Proposal

Bidders

Name Total Amount Place Over/Under Est Amt Left From Low Bid Delta Between Bidders
Engineer's Estimate $2,229,422.25
THK CONSTRUCTION LLC   $1,790,148.09 1
-19.7% | -$439,274.16
TRUE ROADS CONSTRUCTION, LLC   $1,939,811.60 2
-12.99% | -$289,610.65
8.36% | $149,663.51
HODGES AND SON CONSTRUCTION COMPANY, INC.   $1,994,460.00 3
-10.54% | -$234,962.25
11.41% | $204,311.91
2.82% | $54,648.40
EAST TEXAS BRIDGE, INC.   $2,039,492.20 4
-8.52% | -$189,930.05
13.93% | $249,344.11
2.26% | $45,032.20
Subcontractor Percentage Amount
HODGES AND SON CONSTRUCTION COMPANY, INC. 7.02% $106,965.01
R & G CONSTRUCTION, LLC 5.44% $82,890.26
A K CONTRACTING, LLC 4.87% $74,205.07
MORRIS COUNTY CONTRACTORS, L.L.C. 1.84% $28,036.41
STRIPING TECHNOLOGY, L.P. 0.85% $12,951.60
FLEX SUPPLY, LLC 0.68% $10,361.28
TEXOP CONSTRUCTION 0.60% $9,142.31
CAP RIVER LLC 0.32% $4,875.90
PENHALL COMPANY 0.27% $4,114.04
TORO BRAVO CONSTRUCTION, LLC 0.26% $3,961.67
Total: 22.15% $337,503.55

Bid Items

Items: 76, 0 filtered
UPSHUR FM 993  |  ATLANTA  |  1511-01-013  |  03/06/2024  |  $2,229,422  |  BR 2024(791)  |  REPLACE BRIDGE AND APPROACHES  |  0 X
Item code Description Unit Quantity Engineer's Estimate THK CONSTRUCTION LLC TRUE ROADS CONSTRUCTION, LLC HODGES AND SON CONSTRUCTION COMPANY, INC. EAST TEXAS BRIDGE, INC.
104 6009 REMOVING CONC (RIPRAP) SY 122.000 $45.000 $7.000 $10.000 $18.000 $30.000
104 6054 REMOVING CONCRETE(MOW STRIP) LF 650.000 $15.000 $5.000 $4.000 $6.000 $15.000
105 6076 REMOV STAB BASE AND ASPH PAV (2"-15") SY 2,184.000 $15.000 $12.000 $7.000 $15.000 $13.500
110 6001 EXCAVATION (ROADWAY) CY 508.000 $30.000 $20.000 $24.000 $15.000 $25.000
132 6006 EMBANKMENT (FINAL)(DENS CONT)(TY C) CY 1,953.000 $50.000 $20.000 $24.000 $30.000 $30.000
160 6003 FURNISHING AND PLACING TOPSOIL (4") SY 2,832.000 $5.500 $4.500 $4.500 $3.000 $4.000
164 6054 BOND FBR MTRX SEED (PERM)(RURAL)(SAND) SY 2,832.000 $1.500 $2.680 $0.700 $2.000 $1.100
164 6055 BONDED FBR MTRX SEED (TEMP)(WARM) SY 1,416.000 $1.250 $0.010 $0.700 $1.000 $0.900
164 6056 BONDED FBR MTRX SEED (TEMP)(COOL) SY 1,416.000 $1.250 $0.010 $0.700 $1.000 $0.900
168 6001 VEGETATIVE WATERING MG 91.000 $160.000 $10.000 $30.000 $1.000 $10.000
169 6002 SOIL RETENTION BLANKETS (CL 1) (TY B) SY 160.000 $4.500 $2.000 $2.400 $4.000 $2.000
247 6236 FL BS (RDWY DEL)(TY A GR 1-2)(FNAL POS) CY 727.000 $110.000 $175.000 $140.000 $100.000 $85.000
275 6001 CEMENT TON 95.000 $325.000 $250.000 $350.000 $300.000 $375.000
275 6010 CEMENT TREAT (SUBGRADE) (8") SY 3,319.000 $6.750 $5.750 $6.000 $7.000 $5.000
275 6078 CEMENT TREAT (NEW BASE)(DC)(8") SY 3,267.000 $5.250 $5.750 $6.000 $7.000 $5.000
310 6009 PRIME COAT (MC-30) GAL 818.000 $12.000 $8.360 $10.000 $15.000 $10.000
400 6005 CEM STABIL BKFL CY 137.000 $300.000 $300.000 $310.000 $300.000 $300.000
416 6002 DRILL SHAFT (24 IN) LF 275.000 $275.000 $206.220 $275.000 $195.000 $230.000
416 6004 DRILL SHAFT (36 IN) LF 240.000 $375.000 $272.070 $425.000 $275.000 $315.000
420 6014 CL C CONC (ABUT)(HPC) CY 27.800 $1,700.000 $1,100.000 $1,385.000 $1,600.000 $1,400.000
420 6030 CL C CONC (CAP)(HPC) CY 22.800 $1,700.000 $1,100.000 $1,320.000 $1,600.000 $1,500.000
420 6038 CL C CONC (COLUMN)(HPC) CY 8.500 $2,000.000 $1,500.000 $1,575.000 $1,800.000 $1,500.000
422 6008 REINF CONC SLAB (SLAB BEAM)(HPC) SF 4,848.000 $25.000 $19.500 $31.000 $22.000 $25.000
422 6016 APPROACH SLAB (HPC) CY 84.400 $895.000 $630.000 $700.000 $1,000.000 $1,000.000
425 6009 PRESTR CONC SLAB BEAM (4SB12) LF 414.000 $250.000 $235.000 $280.000 $250.000 $230.000
425 6010 PRESTR CONC SLAB BEAM (5SB12) LF 621.000 $260.000 $235.000 $280.000 $250.000 $230.000
432 6006 RIPRAP (CONC)(CL B) CY 2.400 $875.000 $950.000 $1,000.000 $950.000 $2,000.000
432 6031 RIPRAP (STONE PROTECTION)(12 IN) CY 566.000 $225.000 $160.000 $175.000 $200.000 $200.000
432 6039 BEDDING MATERIAL (6 IN) CY 108.000 $215.000 $140.000 $180.000 $180.000 $200.000
432 6045 RIPRAP (MOW STRIP)(4 IN) CY 30.000 $740.000 $750.000 $600.000 $600.000 $800.000
450 6111 RAIL (TY SSTR) (W/DRAIN SLOT) (HPC) LF 234.000 $165.000 $160.000 $135.000 $150.000 $150.000
454 6003 ARMOR JOINT LF 88.000 $195.000 $150.000 $90.000 $200.000 $100.000
454 6004 ARMOR JOINT (SEALED) LF 85.000 $200.000 $150.000 $110.000 $220.000 $150.000
464 6003 RC PIPE (CL III)(18 IN) LF 28.000 $105.000 $100.000 $90.000 $120.000 $80.000
467 6363 SET (TY II) (18 IN) (RCP) (6: 1) (P) EA 2.000 $1,700.000 $1,000.000 $1,500.000 $2,500.000 $1,200.000
496 6009 REMOV STR (BRIDGE 0 - 99 FT LENGTH) EA 1.000 $40,000.000 $25,000.000 $31,000.000 $50,000.000 $25,000.000
496 6016 REMOV STR (PIPE) EA 1.000 $2,000.000 $500.000 $525.000 $1,000.000 $500.000
496 6043 REMOV STR (SMALL FENCE) LF 858.000 $15.000 $5.000 $4.500 $5.000 $8.000
500 6001 MOBILIZATION LS 1.000 $175,000.000 $175,000.000 $60,000.000 $150,000.000 $200,000.000
502 6001 BARRICADES, SIGNS AND TRAFFIC HANDLING MO 6.000 $10,000.000 $1,500.000 $1,600.000 $4,500.000 $6,500.000
506 6002 ROCK FILTER DAMS (INSTALL) (TY 2) LF 100.000 $50.000 $47.700 $54.000 $1.000 $42.000
506 6003 ROCK FILTER DAMS (INSTALL) (TY 3) LF 15.000 $75.000 $53.000 $96.000 $1.000 $55.000
506 6011 ROCK FILTER DAMS (REMOVE) LF 115.000 $18.000 $10.600 $18.000 $1.000 $16.000
506 6020 CONSTRUCTION EXITS (INSTALL) (TY 1) SY 160.000 $37.500 $37.100 $42.000 $1.000 $40.000
506 6024 CONSTRUCTION EXITS (REMOVE) SY 160.000 $13.000 $7.420 $12.000 $1.000 $16.000
506 6038 TEMP SEDMT CONT FENCE (INSTALL) LF 1,608.000 $5.000 $4.770 $4.500 $1.000 $4.500
506 6039 TEMP SEDMT CONT FENCE (REMOVE) LF 1,608.000 $1.750 $1.060 $0.300 $1.000 $1.500
506 6042 BIODEG EROSN CONT LOGS (INSTL) (18") LF 355.000 $12.000 $12.460 $6.000 $5.000 $11.000
506 6043 BIODEG EROSN CONT LOGS (REMOVE) LF 355.000 $2.750 $1.590 $1.200 $1.000 $5.500
530 6005 DRIVEWAYS (ACP) SY 119.000 $115.000 $25.160 $100.000 $120.000 $75.000
540 6001 MTL W-BEAM GD FEN (TIM POST) LF 287.500 $30.000 $25.000 $27.000 $24.000 $25.000
540 6006 MTL BEAM GD FEN TRANS (THRIE-BEAM) EA 4.000 $2,500.000 $1,749.000 $2,000.000 $1,700.000 $1,850.000
542 6001 REMOVE METAL BEAM GUARD FENCE LF 400.000 $6.750 $2.120 $2.400 $2.000 $2.500
542 6005 RM MTL BM GD FEN TRANS (T101) EA 4.000 $300.000 $159.000 $180.000 $150.000 $200.000
544 6001 GUARDRAIL END TREATMENT (INSTALL) EA 4.000 $3,450.000 $3,047.500 $3,450.000 $2,900.000 $3,200.000
544 6003 GUARDRAIL END TREATMENT (REMOVE) EA 4.000 $410.000 $212.000 $240.000 $500.000 $250.000
552 6003 WIRE FENCE (TY C) LF 760.000 $35.000 $20.000 $21.000 $20.000 $32.000
552 6005 GATE (TY 1) EA 1.000 $3,450.000 $500.000 $900.000 $2,000.000 $1,200.000
644 6001 IN SM RD SN SUP&AM TY10BWG(1)SA(P) EA 1.000 $950.000 $1,500.000 $1,200.000 $1,500.000 $1,700.000
644 6060 IN SM RD SN SUP&AM TYTWT(1)WS(P) EA 2.000 $900.000 $1,500.000 $1,200.000 $1,500.000 $1,400.000
644 6076 REMOVE SM RD SN SUP&AM EA 1.000 $155.000 $500.000 $180.000 $500.000 $100.000
658 6014 INSTL DEL ASSM (D-SW)SZ (BRF)CTB (BI) EA 4.000 $45.000 $21.200 $24.000 $20.000 $30.000
658 6016 INSTL DEL ASSM (D-SW)SZ (BRF)GF1 (BI) EA 7.000 $35.000 $21.200 $24.000 $20.000 $30.000
662 6109 WK ZN PAV MRK SHT TERM (TAB)TY W EA 100.000 $2.500 $0.100 $2.400 $5.000 $3.000
662 6111 WK ZN PAV MRK SHT TERM (TAB)TY Y-2 EA 100.000 $3.000 $0.100 $2.400 $5.000 $3.000
666 6225 PAVEMENT SEALER 6" LF 608.000 $1.000 $2.120 $2.400 $2.000 $2.200
672 6009 REFL PAV MRKR TY II-A-A EA 22.000 $8.000 $10.600 $12.000 $10.000 $11.000
678 6002 PAV SURF PREP FOR MRK (6") LF 608.000 $0.750 $2.120 $2.400 $2.000 $2.200
678 6033 PAV SURF PREP FOR MRK (RPM) EA 4.000 $1.500 $26.500 $30.000 $25.000 $27.500
800 6001 NO. OF WORKING DAYS $/D 3,210.000 $102.000 $83.000 $102.000 $102.000 $102.000
3077 6032 SP MIXES SP-C PG76-22 TON 352.000 $180.000 $207.790 $234.000 $300.000 $245.000
6001 6002 PORTABLE CHANGEABLE MESSAGE SIGN EA 2.000 $15,950.000 $10,000.000 $18,000.000 $10,000.000 $15,000.000
6149 6004 REFL PAV MRK AWT (W) 6" (SLD) (100MIL) LF 1,720.000 $1.400 $3.180 $3.600 $3.000 $3.300
6149 6010 REFL PAV MRK AWT (Y) 6" (SLD) (100MIL) LF 1,720.000 $1.500 $3.180 $3.600 $3.000 $3.300
6185 6002 TMA (STATIONARY) DAY 5.000 $400.000 $400.000 $240.000 $150.000 $300.000
6185 6003 TMA (MOBILE OPERATION) HR 60.000 $92.000 $35.000 $60.000 $20.000 $30.000
Totals: $2,229,422.25 $1,790,148.09 $1,939,811.60 $1,994,460.00 $2,039,492.20